This document is an amendment to a solicitation for a construction project at the Naval Undersea Warfare Center Division, Newport (NUWCDIVNPT). The key details are:
The solicitation, number N6660424Q0355, is for the renovation of several laboratories and collaboration spaces at NUWCDIVNPT. The project is a 100% small business set-aside under NAICS code 236220 with an estimated magnitude between $100,000 and $250,000. The proposal due date has been extended from August 20, 2024 to August 27, 2024. The contractor must be registered in the System for Award Management (SAM) to be considered for award. The technical proposal must address the offeror's experience, capability, and technical solution to complete the project within the specified timeframe. Past performance references are also required. Pricing shall be submitted for the entire project, including bond premiums and merchant bankcard processing fees.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6660424Q0355 Amendment 0005.pdf | ||
| N6660424Q0355 Amendment 0004.pdf | ||
| N6660424Q0355 Amendment 0004.pdf | ||
| I. H. Davis-Bacon Act WD # RI20240001 20240823.pdf | ||
| N6660424Q0355 Amendment 0003 draft.pdf | ||
| N6660424Q0355 Amendment 0002.pdf | ||
| N6660424Q0355 Amend 0001.pdf | ||
| RI Davis Bacon Wage Determination 12 July 2024.pdf | ||
| I. E. Davis-Bacon Act WD # RI20240001 20240705.pdf | ||
| N6660424Q0355.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1301148046
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See section A.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 19-Aug-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6660424Q0355
X 9B. DATED (SEE ITEM 11)
17-Jul-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Aug-2024
CODE
NAVAL UNDERSEA WARFARE CENTER
JAY PARKER, CODE 0221
CONTRACTS DEPARTMENT
1176 HOWELL STREET
NEWPORT RI 02841
N66604 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6660424Q0355
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 20-Aug-2024 02:00 PM to 27-Aug-2024 02:00 PM.
The required performance has changed from PROJECT TITLE AND DESCRIPTION: Lab and Collaborative Space Reno ProjectProposal Due: 20 August 2024 before 2:00 pm ET. Email to jay.a.parker2.civ@us.navy.mil and michael.n.ouellette.civ@us.navy.mil. Offeror MUST be registered in the System for Award Management to be considered for award.This requirement is 100% Small Business Set-Aside: NAICS 236220; $45 MillionMagnitude per FAR 36.204: Between $100,000 and $250,000.Site Visit: 10:00 AM ET 7 August 2024. Meet at Building 80 NUWC Division Newport. Please allow for sufficient time to process site visit request. See Section A for complete details.IMPORTANT: PLEASE NOTE THAT TECHNICAL INFORMATION
IS REQUIRED WITH SUBMISSION OF OFFER. PLEASE SEE SECTIONS L AND M FOR SPECIFIC
REQUIRMENTS. OFFERORS NOT SUBMITTING THIS INFORMATION RISK BEING EXCLUDED FROM
CONSIDERATION FOR AWARD to PROJECT TITLE AND DESCRIPTION: Lab and Collaborative Space Reno ProjectProposal Due: 27 August 2024 before 2:00 pm ET. Email to jay.a.parker2.civ@us.navy.mil and michael.n.ouellette.civ@us.navy.mil. Offeror MUST be registered in the System for Award Management to be considered for award.This requirement is 100% Small Business Set-Aside: NAICS 236220; $45 MillionMagnitude per FAR 36.204: Between $100,000 and $250,000.Site Visit: 10:00 AM ET 7 August 2024. Meet at Building 80 NUWC Division Newport. Please allow for sufficient time to process site visit request. See Section A for complete details.IMPORTANT: PLEASE NOTE THAT TECHNICAL INFORMATION IS REQUIRED WITH SUBMISSION OF OFFER. PLEASE SEE SECTIONS L AND M FOR SPECIFIC REQUIRMENTS. OFFERORS
NOT SUBMITTING THIS INFORMATION RISK BEING EXCLUDED FROM CONSIDERATION FOR
AWARD.
The following have been modified:
GENERAL INFORMATION
Distribution: To be provided at award NUWCDIVNPT PR Number: To be provided at award
NUWCDIVNPT PID: N66604-24-SIMACQ-NPT-10-0237
NUWCDIVNPT Points of Contact: Jay Parker, jay.a.parker2.civ@us.navy.mil and Michael Ouellette Michael.N.Ouellette.civ@us.navy.mil
Amendment 0003: The purpose of this amendment is to:
1. Extend the proposal due date from 20 Aug 2024 @ 1400 EST to 27 Aug 2024 @1400 EST.
2. Provide responses to RFI 0002:
1. One more item I wanted to inquire about for clarification was painting of any raceways/surface mounted EMT. Are those items getting painted over?
Response: EMT and raceways are not to be painted.
2. Will anything in the way be moved by navy ahead of time, for all Buildings jobs.
Response: Government will remove furniture, systems furniture and equipment prior to start of work or during work as in B1320 which will have several mobilizations.
3. I didn't see anywhere on the prints regarding approximately the ceiling heights in the rooms ( Or if any rooms are out of the ordinary size of most of them ).
Response: Most ceiling heights are 10’. There are no exceptionally high or low rooms.
4. What type of shape are most of the room walls in as far as prep work needed. ( I couldn't make it too the walk through )
Response: The walls are generally in good shape. Wall preparation is necessary but minimal but for the exception of B17 lab in B1319, which requires removal of about 2 dozen surface-mounted conduits.
5. Is there any wall covering to be removed on this project.
Response: There are no wall coverings but there are some wall-mounted equipment such as TVs and whiteboards.
6. What is systems furniture, is that like cubies.
Response: Yes, systems furniture refers to the Herman-Miller cubicle partitions.
7. The revised drawings appear to still be scope for B1371, please confirm that as per amendment #2 that all scope in Building 1371 is being removed from the Scope of Work? If not please clarify what has been removed and what still remains.
Response: Revision contained inaccurate wording. B1371 was not descoped in its entirety. The work that remains in B1371 is reflooring the elevators. B1371 R260-R263 secure labs were descoped.
All other terms and conditions remain unchanged.
SECTION F - DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date of award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after award. The time stated for completion shall include final cleanup of the premises.
(End of clause)
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
PROPOSAL REQUIREMENTS
1.0 GENERAL NOTES TO OFFERORS:
The RFP will be made available only through the Government Point of Entry, also known as Contract Opportunities (formerly FBO) at: http://www.sam.gov
Offerors are hereby notified that, from time to time, the Government may post additional information to the SAM.gov web site relating to this RFP (e.g., responses to questions, amendments, etc.). It is the Offeror’s responsibility to check the web site for any such information.
All questions concerning this procurement, either technical or contractual, must be submitted via email. No direct discussion between the technical representative and prospective Offeror will be conducted. Questions shall be submitted to the following point of contact no later than 20 August 2024:
PRIMARY: ALTERNATE:
Name: Jay Parker Name: Michael Ouellette Email: jay.a.parker2.civ@us.navy.mil Email: Michael.n.ouellette.civ@us.navy.mil
1.1 PROPOSALS
Offerors shall submit proposal by electronic means. All electronic submissions shall be sent to jay.a.parker2.civ@us.navy.mil and Michael.n.ouellette.civ@us.navy.mil. Submissions must be received by the closing date and time located on the cover page of the SF 1442. Proposal will consist of a single Adobe PDF attachment.
(A) Proposal Format. This section specifies the format that Offerors shall use in submitting proposals in response to this solicitation. Offerors shall comply with the detailed instructions for the format and content of the proposals; proposals that do not comply may be considered unacceptable and may render the Offeror ineligible for award.
(B) Organization. In the Technical Proposal, the Offeror shall provide information and documentation to clearly and concisely identify the Offeror’s overall ability to meet the requirements of the so solicitation. The Offeror shall divide the Technical Proposal into the following factors in the order listed below:
2.0 TECHNICAL PROPOSAL
Organization. In the Technical Proposal, the Offeror shall provide information and documentation to clearly and concisely identify the Offeror’s overall ability to meet the requirements of the solicitation. The Offeror shall divide the Technical Proposal into the following factors in the order listed below:
2.1 Factor 1: Technical Capability
2.1.1 Subfactor (a): Experience and Capability to Complete Project
Offeror shall provide a technical capability statement outlining their experience and capability to complete the project identified in the Specification and Drawings.
2.1.2 Subfactor (b): Technical Solution to Complete Project
Offeror shall provide a narrative describing their understanding and technical solution to completing the project described in the solicitation. Narrative must describe steps to complete the project, demonstrating that project will be completed within timeframe specified in the solicitation.
2.2 Factor 2: Past Performance
The Offeror shall provide a maximum of three (3) past performance references, if available, that reflect recent and relevant experience performed within three (3) years of the solicitation closing date. The Offeror shall include contract/task order number, contract/task order type (firm fixed price, time & material or cost type), total contract/task order amount, short description of work performed, and names and e-mail addresses for Contracting Officer, Contracting Officer’s Representative (COR) if applicable, Government Program Manager (PM) or Construction Manager (CM), or industry equivalent (if non Government effort).
Past performance references shall demonstrate the ability to handle the scope and magnitude of this proposed construction project. The Offeror shall include a brief discussion on how the references provided are relevant to the work being proposed.
3.0 PRICE PROPOSAL
3.1 Factor 3: PRICE
Offerors shall fill in Section B for Contract Line Item Number (CLIN) 0001. Provide one price to complete the entire job, inclusive of bond premiums and merchant bankcard processing fees.
Note CLIN 0002 is not separately priced.
(End of Summary of Changes)