Attachment 1 - Performance Based Milestones.pdf
PDF 161 KB Posted
- Attached to
- OB-122 Outboard Electronics Canisters for the Wide Aperture Array and TD-1479 Outboard Electronics Canisters for the Large Spherical Array Federal contract opportunity
- Solicitation number
- N66604-23-R-0143
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6660423R0143 Amendment 0004.pdf | ||
| N6660423R0143 Amendment 0003.pdf | ||
| N6660423R0143 Amendment 0002.pdf | ||
| N6660423R0143 Amendment 0002.pdf | ||
| N6660423R0143 Amendment 0001.pdf | ||
| N6660423R0143.pdf | ||
| Exhibit A - Contract Data Requirements List.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Based Payments Milestones Applicable to CLIN 0001
Events Severable/ Cumulative
Percent per
SLIN
Total Value for SLIN
TBD ($ TBD
per unit
(QTY TBD) /
$ TBD total)
Milestone Completion Verification Method
Milestone 1:
90% of Material Line Items Ordered
Severable 20%
No more than $ TBD total ($ TBD per unit)
Contractor provides internal report to Government Point of Contact (POC) which provides proof that material was ordered (Purchase Order (PO) number(s), values, and date issued).
Milestone is complete if Government
POC accepts the report.
Milestone 2:
50% of Material Line Items Received
Cumulative
– based on completion of Milestone
15%
Cumulative Payment, no more than
$ TBD total ($ TBD per unit)
Contractor provides internal report to Government POC which proves that the material was received against the
PO(s) that were placed.
Milestone is complete if Government
POC accepts the report.
Milestone 3:
90% of Material Line Items Received
Cumulative
– based on completion of Milestones 1
& 2
15%
Cumulative Payment, no more than
$ TBD total ($ TBD per unit)
Contractor provides internal report to Government POC which proves that the material was received against the
PO(s) that were placed.
Milestone is complete if Government
POC accepts the report.
TOTAL 50%
$ TBD total ($ TBD per unit)
NOTE 1
The remaining 50% may be invoiced after inspection and acceptance of each unit. The payments for the units under SLIN(s) TBD shall not exceed 50% of the unit price if payment is made per the schedule above.
NOTE 2
Performance Based Payment events can be of two kinds: severable (i.e., stand-alone) or cumulative (i.e., dependent):
• Severable events do not require the accomplishment of any other events.
• Cumulative events require the prior or concurrent completion of other events in order to be successfully accomplished.
NOTE 3
Contractor Performance Based Payment requests may not be submitted more often than monthly, as the Defense Finance and Accounting Service (DFAS) will only make one payment in a month. This does not mean, however, that a monthly payment request cannot cover payment for more than one payment event. Payment requests must clearly identify the event or events covered by the monthly submission and must refer to the applicable contract provision so that the amount to be paid can be unambiguously determined.
NOTE 4
This is a generic schedule. TBD fields will be filled in at the delivery order level.