16. PENETRATIONS - PIPE

16.1 Locate penetration(s) on wall panel and cut hole with 1/2" minimum clearance.

(Refer to Chapter 7 for panel cutting instructions).

figure 16.1a

Penetration through field of panel figure 16.1b

Penetration at panel joint figure 16.2bfigure 16.2a

16.2 For penetrations at panel joints or edges:

- plug interior joint above and below opening with butyl sealant (figure 16.2a)

- fill exterior reveal above penetration with color matched urethane sealant (not by panel manufacturer) to top of panel (figure 16.2b) figure 16.1c

Penetration at panel edge

Paul Line

Paul Line

Paul Oval

Paul Oval

16. PENETRATIONS - PIPE

figure 16.3a figure 16.3b

16.6 Repeat steps 16.4 and 16.5 for interior side.

figure 16.4a figure 16.6

16.3 Fill gap around penetration(s) with expandable foam.

figure 16.3c figure 16.4b figure 16.5

16.4 Apply urethane sealant around penetration(s). Cut sheet metal trims for lower and upper halves of opening and attach using 1/8" painted stainless steel pop rivets.

16.5 Apply 3/8" minimum bead of color matched urethane sealant around penetration(s).

Paul Line

Paul Line

16. PENETRATIONS - BEAM

Penetration through middle of panel

16.7 Locate penetration(s) on wall panel and cut hole with 1/2" minimum clearance. (Refer to Chapter 7 for panel cutting instructions).

Penetration at panel edge figure 16.7a figure 16.7b figure 16.7c figure 16.8a figure 16.8b

Penetration at panel joint

16.8 For penetrations at panel joints or edges:

- plug interior joint above and below opening with butyl sealant (figure 16.8a)

- fill exterior reveal above penetration with color matched urethane sealant (not by panel manufacturer) to top of panel (figure 16.8b)

Paul Line

Paul Line

Paul Oval

16. PENETRATIONS - BEAM

16.9 Fill gap around penetrations(s) with expandable foam.

16.12 Repeat steps 16.10 and 16.11 for interior side.

figure 16.9a figure 16.9b figure 16.9c

16.10 Apply urethane sealant around penetration(s). Cut sheet metal trims for lower and upper halves of opening and attach using 1/8" painted stainless steel pop rivets.

figure 16.12 figure 16.10a figure 16.10b figure 16.11

16.11 Apply 3/8" minimum bead of color matched urethane sealant around penetration(s).

Paul Line

Paul Line

NEW CI Wall Installation Guide PART I
NEW CI Wall Installation Guide 9.pdf
Blank Page
Blank Page

Blank Page

NEW CI Wall Installation Guide PART II 9.2.15
Blank Page
Blank Page
Blank Page
Blank Page
Blank Page

File details come from the government source that posted it. Updated .