16. PENETRATIONS - PIPE
16.1 Locate penetration(s) on wall panel and cut hole with 1/2" minimum clearance.
(Refer to Chapter 7 for panel cutting instructions).
figure 16.1a
Penetration through field of panel figure 16.1b
Penetration at panel joint figure 16.2bfigure 16.2a
16.2 For penetrations at panel joints or edges:
- plug interior joint above and below opening with butyl sealant (figure 16.2a)
- fill exterior reveal above penetration with color matched urethane sealant (not by panel manufacturer) to top of panel (figure 16.2b) figure 16.1c
Penetration at panel edge
Paul Line
Paul Line
Paul Oval
Paul Oval
16. PENETRATIONS - PIPE
figure 16.3a figure 16.3b
16.6 Repeat steps 16.4 and 16.5 for interior side.
figure 16.4a figure 16.6
16.3 Fill gap around penetration(s) with expandable foam.
figure 16.3c figure 16.4b figure 16.5
16.4 Apply urethane sealant around penetration(s). Cut sheet metal trims for lower and upper halves of opening and attach using 1/8" painted stainless steel pop rivets.
16.5 Apply 3/8" minimum bead of color matched urethane sealant around penetration(s).
Paul Line
Paul Line
16. PENETRATIONS - BEAM
Penetration through middle of panel
16.7 Locate penetration(s) on wall panel and cut hole with 1/2" minimum clearance. (Refer to Chapter 7 for panel cutting instructions).
Penetration at panel edge figure 16.7a figure 16.7b figure 16.7c figure 16.8a figure 16.8b
Penetration at panel joint
16.8 For penetrations at panel joints or edges:
- plug interior joint above and below opening with butyl sealant (figure 16.8a)
- fill exterior reveal above penetration with color matched urethane sealant (not by panel manufacturer) to top of panel (figure 16.8b)
Paul Line
Paul Line
Paul Oval
16. PENETRATIONS - BEAM
16.9 Fill gap around penetrations(s) with expandable foam.
16.12 Repeat steps 16.10 and 16.11 for interior side.
figure 16.9a figure 16.9b figure 16.9c
16.10 Apply urethane sealant around penetration(s). Cut sheet metal trims for lower and upper halves of opening and attach using 1/8" painted stainless steel pop rivets.
figure 16.12 figure 16.10a figure 16.10b figure 16.11
16.11 Apply 3/8" minimum bead of color matched urethane sealant around penetration(s).
Paul Line
Paul Line
| NEW CI Wall Installation Guide PART I |
| NEW CI Wall Installation Guide 9.pdf |
| Blank Page |
| Blank Page |
Blank Page
| NEW CI Wall Installation Guide PART II 9.2.15 |