Attachment 7 Additional Questions from industry.pdf
PDF 36 KB Posted
- Attached to
- Construction - Sound Control Improvements Federal contract opportunity
- Solicitation number
- N6660421R0142
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 5 Questions and Answers from industry.pdf | ||
| Attachment 3 Covid Questionare.pdf | ||
| Attachment 4 DOD-GUIDANCE-ON-THE-USE-OF-CLOTH-FACE-COVERINGS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Please clarify that project is tax exempt.
A. Yes, a tax exempt number can be requested by the awardee.
2. Are we to assume that new Door 9 is to have a lite as shown on drawing A‐2 photo of existing?
A. This is not required.
3. Are we required to perform any sound testing upon completion of project?
A. Field testing is not required.