CLIN 0001 Performance Based Payment Milestone Plan

View the file

Other files for this federal contract opportunity

Other files attached to Anechoic Chamber & Installation, newest first.
File Type Posted
Amendment_5_-_Updated_Government_Minimum_Requirements.pdf PDF
Amendment_5_-_Specification_Spreadsheet.xlsx XLSX spreadsheet
AMENDMENT_3_-_Updated_Government_Minimum_Requirements.pdf PDF
Contract_Data_Requirements_List_Redacted.pdf PDF
Government_Minimum_Requirements.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N66604-19-Q-2526 Performance Based Payments Milestone Plan

Events
Severable or Cumulative
Percent

CLIN 0001

Price Milestone Completion Verification Method

Milestone 1:

Material Ordered

Severable
25%
Contractor provides internal report to Government POC which provides proof that the material was ordered (Purchase Order (PO) number(s) and date issued). Government Point of Contact (POC) reviews and accepts.

Milestone 2:

Material Received

Cumulative – based on Milestone 1
25%
Contractor provides internal report to Government POC which provides proof that the material was received against the PO(s) that were placed. Government POC reviews and accepts.

Milestone 3:

Pre-Installation Testing

Cumulative – based on Milestone 1 & 2
30%
In accordance with CDRL A001, contractor submits pre-shipment testing report. Government POC reviews and accepts.
TOTAL
80%

NOTE 1

Performance Based Payment events can be of two kinds: severable (i.e., stand-alone) or cumulative (i.e., dependent):

· Severable events do not require the accomplishment of any other events.

· Cumulative events require the prior or concurrent completion of other events in order to be successfully accomplished.

NOTE 2

Contractor Performance Based Payment requests may not be submitted more often than monthly, as the Defense Finance and Accounting Service (DFAS) will only make one payment in a month. This does not mean, however, that a monthly payment request cannot cover payment for more than one payment event. Payment requests must clearly identify the event or events covered by the monthly submission and must refer to the applicable contract provision so that the amount to be paid can be unambiguously determined.