AMENDMENT 5 - SPECIFICATION SPREADSHEET

View the file

Other files for this federal contract opportunity

Other files attached to Anechoic Chamber & Installation, newest first.
File Type Posted
Amendment_5_-_Updated_Government_Minimum_Requirements.pdf PDF
AMENDMENT_3_-_Updated_Government_Minimum_Requirements.pdf PDF
Contract_Data_Requirements_List_Redacted.pdf PDF
Government_Minimum_Requirements.pdf PDF
CLIN_0001_Performance_Based_Payment_Milestone_Plan.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

CONTRACTOR NAME:
QUOTE NUMBER:
MINIMUM SPECSWHERE DOES THE QUOTE MENTION THIS REQUIREMENT?
(PARAGRAPH / SECTION)MEETS REQUIREMENT
(Y OR N)IF NO

PROVIDE DETAIL AS TO WHY

SOW 2.1 - Chamber ExteriorWidth: 17’9” (+0% / -10%)between 16' 0" and 17' 9"
Height: 14’11” (+0% / -10%)between 13' 6" and 14' 11"
Depth: 17’3” (+0% / -10%)between 15' 6" and 17' 3"
The exterior of the chamber shall be painted.
SOW 2.2.1 - Chamber InteriorWidth: 13'4"
Height: 12'0"
Depth: 14'8"
SOW 2.2.2.1One (1) panel, 24” x 24” or larger
Pass-through panel shall be located on the left side of the chamber when looking at the door from the outside.
Chamber shall meet acoustic performance requirements (SOW 3.0), while cabling in use.

SOW 2.2.2.2 Minimum of six (6) internal low profile light fixtures with an external switch.

SOW 2.2.2.3One (1) panel, 6” x 12” or larger OR eight (8) threaded ¾” hose connections, four (4) on the inside and four (4) on the outside of the chamberspecify which requirement your quote meets
Panel (or hose connections) shall be located on the left side of the chamber when looking at the door from the outside.
Chamber shall meet acoustic performance requirements (SOW 3.0), while water piping is connected.
SOW 2.2.2.4Six (6) noise level meter mounting mechanisms that allow for height adjustment.
Affixed roughly in the center of each surface.
Mounting mechanisms shall be placed as follows: one (1) on each wall not containing a door for a total of three (3); one (1) on the door; and at least one (1) on the ceiling.
SOW 2.2.2.5Two (2) quad 20A receptacles
One (1) located on the left side, and one (1) located on the right side of the chamber.
SOW 2.3 - VentilationThe chamber shall be ventilated to allow for passive air exchange such that the chamber does not exceed an average of 10 degree temperature increase in one (1) hour with a 4 kilowatt heat load.
Ventilation connections to Government air conditioning system shall be provided on the wall containing the door, or on the left side of the chamber, as looking at the door from the outside.
SOW 2.4 - DoorOne (1) manually operated door, with opening bar or knob.
The chamber door shall be hinged on the right hand side of the exterior, opening outward from the chamber.
The chamber door shall be equipped with acoustic wedges or panels to support the acoustic performance requirements of the chamber as specified in SOW paragraph 3.1.
The chamber door shall be a minimum of 7’ wide and a maximum of 8’ wide x 8’ tall.
The chamber door shall be placed in the 17’9” side of the chamber
SOW 3.1 - Acoustic Noise ReductionFrequency (Hz)631252505001000200040008000
Noise Reduction (dB) -Threshold1020202020202020
Noise Reduction (dB) - Goal1525252525252525

SOW 3.2 - Cut off Frequency The hemi-anechoic chamber cut-off frequency shall be equal to or less than 250Hz.

SOW 4.0 - Pre-Shipment TestingThe contractor shall test the chamber for operation and conformance in accordance with the purchase specifications prior to shipment.
Results of the Pre-Shipment Testing shall be delivered in accordance with CDRL A001.
SOW 5.0 - On Site AssemblyThe contractor shall conduct on-site assembly of the equipment at the Naval Undersea Warfare Center Division, Newport RI.
Upon on-site assembly, the contractor shall test the chamber for operation and conformance in accordance with the purchase specifications.
A report on the results of the On-Site Assembly Testing performed shall be delivered in accordance with CDRL A001.