Questions and Answers for Solicitation N66001-19-Q-6400

- Is hand delivery acceptable? We are located close by, and would like to personally deliver the materials to your location. This will also allow us to keep costs low for shipping.

Answer – Hand delivery is NOT acceptable; all products must enter through the receiving docks.

- How would you like the part labeled (engraved, labeled on packing boxes only, etc.)?

Answer – Please label the package with the purchase order that will be provided on the contract.

- What is the required delivery date of the parts?

Answer – within 8 weeks after receipt of the order.

-When will work be awarded?

Answer – approximately 2 weeks after the RFQ closes.

- Is it correct to infer from the drawings that parts are to be completely assembled? Some of our customers in the past wanted them separately.

Answer – Each part should be assembled.

- The drawings reference McMaster parts. Must these be used, or are they just referenced in the drawings.

Answer – The parts do NOT have to be McMaster’s

- Finally, is DFAR compliant material acceptable?

Answer - Yes