N6523617R0001 Follow-On QA to 6-21-18 Responses 6-22-18.pdf
PDF 242 KB Posted
- Solicitation number
- N65236-17-R-0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4A Prime Pricing Model v2.1 6-26-18.xlsx | XLSX spreadsheet | |
| N6523617R0001 Questions and Answers.pdf | ||
| N6523617R0001 Follow-On QA to Government 6-26-18 Answers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N6523617R0001
Follow-On Questions to Government Answers Provided on 21 June 18
22 June 18
1. Will Certified cost and pricing data be required for subcontractors?
a. In accordance with FAR 52.244-2(e)(1)(v) of the RFP - The subcontractor’s current, complete, and accurate certified cost or pricing data and Certificate of Current Cost or
Pricing Data, if required by other contract provisions.
i. Offerors shall submit certified cost and pricing data in accordance with FAR
52.215-12
2. Does the prime submit subcontractor information required by 52.244-2 with the proposal?
a. In accordance with Section of L the RFP, offerors shall provide the data required under
FAR 52.244-2, paragraph (e)(1) for all Subcontractors the offeror intends to identify as an Approved Subcontractor to utilize for performance under issued task or delivery orders under this contract
i. Offerors’ submitted analysis shall be based on their evaluation of their proposed subcontractor’s pricing data obtained as necessary to comply with the requirements of FAR 52.244-2.
3. Does the prime include subcontractor burdened rates in their proposal submission?
a. In accordance with FAR 52.244-2(e)(1)(A), offerors shall provide the principle elements of the subcontract price negotiations. Rates shall be submitted if they were utilized by the prime to determine the subcontractors price fair and reasonable.
4. Will the Government request and evaluate proprietary information from subcontractors of the offeror selected for award?
a. The Government will only evaluate the FAR 52.244-2 data submitted by the prime to determine the viability for inclusion of these subcontractors in the contract award under
FAR clause 52.244-2. The Government will not request or evaluate propriety information from the subcontractor.