This amendment to a solicitation modifies the quantities, response date, attachments, and questions and answers for a cost-plus-fixed-fee contract providing engineering support services to the Naval Foundry and Propeller Center. The solicitation seeks maintenance, parts, equipment, tools, and services to execute a preventative and corrective maintenance program ensuring at least 90% operational capacity of large CNC machines and ancillary support equipment. The response date is extended to February 12, 2024 and quantities across multiple contract line items are decreased by 126 each. Additional attachments include cost and rate substantiation templates and a pre-award accounting system survey checklist. Modifications to the statement of work and questions and answers clarify the distribution of option year costs and provide a missing cost spreadsheet attachment.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Summary of Changes
1. CONTRACT ID CODE PAGE OF PAGES
S 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jan-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6449824R4010
X 9B. DATED (SEE ITEM 11)
21-Dec-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jan-2024
CODE
NAVAL SURFACE WARFARE CENTER PHILA
CODE 02311, ANTHONY RICCIARDI
215-897-1494, ANTHONY.RICCIARDI@NAVY.MIL
5001 SOUTH BROAD STREET
PHILADELPHIA PA 19112
N64498 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6449824R4010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES (REVISED)
SUMMARY OF CHANGES
1) The subject amendment has extended the closing date, corrected the quantities, added attachments 1-3, revised Section J and provided Q&A as follows:
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 25-Jan-2024 04:00 PM to 12-Feb-2024 04:00 PM.
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0001
The pricing detail quantity has decreased by 126.00 from 3,390.00 to 3,264.00.
CLIN 0002
CLIN 0003
CLIN 0004
CLIN 0005
CLIN 0006
CLIN 0007
CLIN 0008
CLIN 0009
CLIN 0010
CLIN 0011
CLIN 0012
CLIN 0013
CLIN 0014
CLIN 0015
CLIN 0016
CLIN 0017
CLIN 0018
CLIN 0019
CLIN 0020
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
LIST OF ATTACHMENTS
Attachment 1 - Cost Summary Format Attachment 2 - Labor Rate Substantiation Table Attachment 3 - Pre-Award Survey of Prospective Contractor Accounting System Checklist Exhibit A1: Contract Data Requirements List (CDRL) DD Form A001 – A023)
Questions and Answers:
(1) The sum of the labor hours by period detailed in Section B do not tie into the total per the LOE. Which total should we use in pricing?
- Answer: The hours in Section B have been corrected and the sum of the hours now match the total identified in the LOE chart in the SOW.
(2) Section B specifies an NTE amount by year, but we are required to provide pricing by option, assuming quarterly. Are prospective bidders expected to divide the total provided per year by 4 and assume the costs are evenly distributed over each option?
- Answer: Yes.
(3) Cost spreadsheets have not been included in the documents that were provided. Please provide these at your earliest convenience.
- Answer: Spreadsheet is attached in this amendment.
(4) Will a wage determination be provided?
- Answer: No