N6449818R4015_AMENDMENT_0001.pdf

PDF 758 KB Posted

Attached to
HM&E system support for Division 41. Federal contract opportunity
Solicitation number
N6449818R4015
Issued by
Department of the Navy Naval Sea Systems Command

About this file

Amendment 0001

View the file

Other files for this federal contract opportunity

Other files attached to HM&E system support for Division 41., newest first.
File Type Posted
NSWCPD_SBPCD.xlsx XLSX spreadsheet
Cost_Summary_Format_Attachement.xls XLS spreadsheet
N6449818R4015.pdf PDF
Labor_Rate_Substantiation_Table_Attachment.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide a list of questions and answ ers, make applicable revisions to the RFP and to extend the due date of the RFP to 2:00 PM local time, 14 January 2019.

1. CONTRACT ID CODE PAGE OF PAGES

S 1 63

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Dec-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6449818R4015

X 9B. DATED (SEE ITEM 11)

30-Nov-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Dec-2018

CODE

NAVAL SURFACE WARFARE CENTER PHILA

CODE 0232, FRANCIS BRADY

215-897-7821, FRANCIS.J.BRADY@NAVY.MIL

5001 SOUTH BROAD STREET

PHILADELPHIA PA 19112

N64498 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6449818R4015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

Q1. Per the Solicitation, Offer and Award document (page 1 of 134), the proposal is due 31 Dec 2018 by 2:00

pm. Request that the Government extend the due date by two weeks given the holidays. If not, can the

Government confirm that the named personnel will be available on 31 December to receive the hard copies and digital copies required by the solicitation?

A1: The due date on RFP N6449818R4015 has been extended to 14 January 2019.

Q2. Section 3.0.3 (page 14 of 134) requires that the Contractor maintain a Quality Management System

(QMS). Further in Section L.3.5 Volume V (Factor 4) (page 116 of 134) states the Prime Contractor must demonstrate that it currently holds a QMS acceptance letter meeting the requirements of ASQ/ANSI/ISO

9001:2015 from an authorized Naval Sea Systems Command (NAVSEA) QMS Acceptance Authority. The requirements for the QMS are aligned with NAVSEA instructions and standard items that are appropriate to

Alteration Installation work, rather than the engineering services and support activities delineated in the

Statement of Work. Will the Government remove this requirement given its inconsistency with the Statement of Work scope?

A:2 Requirement for a QMS as per paragraph 3.0.3 will not be removed. In addition, adherence to NAVSEA

Technical Specification 9090-310 (latest version) could further be required at the task order level. See revised L and

M.

Q3. Page 31 of 134, Section 11.1.1 Key Personnel, b. Engineer IV, under Education, says the “Individual shall possess a Bachelor’s level degree…” and “…should also possess a Master’s degree in any engineering discipline.” Request the Government confirm that the second part should say “Individual shall also possess a

Master’s degree in any engineering discipline.”

A3: A Master's degree in any engineering discipline is recommended for this position.

Q4. How many awards does the government intend to make?

A4: Naval Surface Warfare Center Philadelphia Division, Philadelphia, PA intends to award multiple indefinite-delivery, indefinite quantity, cost-plus-fixed-fee type contract(s) providing support services as described in Section

C, Statement of Work.

Q5. Page 88 of 134 Clause 52.204-8 (2) indicates the size standard is $15M. Request that the Government revise the size standard to the size standard of $38.5M of NAICS 541330 that has been employed in NWSCPD solicitations.

A5: The size standard in Clause 52.204-8 has been updated to $38,500,000.00.

Q6. Page 99 pf 134, Section L.1 indicates questions are due within 15 days after solicitation release, yet

Section L.1.2 on that same page states “three weeks after date of solicitation release.” Can the Government clarify which is correct?

A6: Section L.1 has been revised to 21 days.

Q7. Pages 104 and 105 of 134, In Section L.3.2.2 Subfactor 1B – Management Approach, there are some sections which seem to be redundant, as follows:

· “a. Resources” seems to be almost entirely redundant of “d. Workflow Management.” Request the

Government delete “d. Workflow Management.”

· The last sentence of “a. Resources” begins “the offeror shall also discuss its plans to engage in full performance if the task order…” which is redundant of the topics covered by “e. Start-Up Plan” and that described in “Transition Plan” that follows at the end of “e. Start-up Plan.” Request the Government remove

“e. Start-up Plan.”

A7: L3.2.2 and M.2 have been revised. Please refer to the updated version of L 3.2.2 and M.2.

Q8. Page 105 of 134, Section L.3.2.2 Subfactor 1B – Management Approach, subparagraph c. Subcontract

Management, and Section L.3.2.4 Subfactor 1D – Subcontracting Commitment, subsection Subcontract

Management request information that is redundant with each other, and with the kinds of information often contained in the Small business Subcontracting Plan. Will the Government allow all of these topics to be addressed in the Small Business Subcontracting Plan? Alternatively, will the Government remove the redundancy between subfactors 1B and 1D?

A8: L3.2.2 and M.2 have been revised. Please refer to the updated version of L 3.2.2 and M.2.

Q9. Page 106 of 134, Section L.3.2.4.1 Small Business Participation Commitment Document (SBPCD) excel document requests information that is also called for earlier on page 105 of 134 in Section L.3.2.4. Can the offeror assume that the form can be used in place of a written narrative as called for in sentences one and two of Section L.3.2.4?

A9: As prescribed in Section L, please complete the form and provide a narrative.

Q10. Page 128 of 134, Section M.2 discusses the relative importance of all evaluation factors and subfactors.

Although Factor 4 Quality Assurance is listed on page 128 of 134 in Section M.3, it is never explicitly discussed in Section M.2. Request the Government provide more insight into the importance of Factor 4.

A10: Section M.2 has been revised.

Q11. Page 7 of 134, HQ B-2-0015 - PAYMENT OF FEES(S) (LEVEL OF EFFORT) – ALTERNATE I

(NAVSEA) (MAY 2010) paragraph (b) states “The Government shall make payments to the Contractor, subject to and in accordance with the clause in this contract entitled "FIXED FEE" (FAR 52.216-8) or

"INCENTIVE FEE", (FAR 52.216-10), as applicable. Such payments shall be submitted by and payable to the Contractor pursuant to the clause of this contract entitled "ALLOWABLE COST AND PAYMENT"

(FAR 52.216-7), subject to the withholding terms and conditions of the "FIXED FEE" or "INCENTIVE

FEE" clause, as applicable, and shall be paid at the hourly rate(s) specified above per man-hour performed and invoiced.” However, there are no Contractor fill-ins for man-hour fee rate(s) in the preceding paragraphs. Would the Government please clarify whether it is their intent for fixed fee to be paid as an hourly rate per man-hour performed and invoiced, and if so, include a table for Offerors to complete with their proposed hourly fee rate per man-hour?

A11: It is indeed the Government's intent for fixed fee to be paid as an hourly rate per man-hour performed and invoiced. Please see revisions to HQ B-2-0015.

Q12. Page 26 of 134, Section C 6. Place of Performance paragraph 6.1 states the “Performance may occur at the Government sites.” Page 29 of 134, Section C 11. Personnel, level of effort chart, lists the level of effort by labor category and performance year but does not distinguish between Government site and Contractor site performance. Would the Government please clarify how many hours by labor category the Government anticipates work being performed at Government site versus Contractor site for pricing and cost estimating purposes?

A12: C11.1 has been revised. The level of effort for the performance of the resultant contract is based on the following labor categories and hours per year (please use 25% Contractor site and 75% Government site as a basis for estimate for all labor categories). Additional level of detail requested isn't available. Specific task orders would be utilized to provide the scope of each order.

Q13. Page 31 of 134, Section C 11. Personnel, level of effort chart the eCraft Code for the Technician, Engineering IV and Technician, Engineering IV (OT) labor categories is 30083. Page 37 of 134, Section

11.1.2 Non-Key Personnel, paragraph y. TECHNICIAN, ENGINEERING IV, the eCraft Code is 30084.

Would the Government please clarify the correct eCraft Code for the Technician, Engineering IV labor category?

A13: C11.1 has been revised. Technician Engineering IV is eCraft Code 30084. Code 30084, not 30083, was intended for the level of effort chart for Technician Engineering IV. This was a mistake in the code number in the level of effort chart.

Q14. Page 31 of 134, Section C 11. Personnel, level of effort chart the eCraft Code for the Technician, Engineering VI and Technician, Engineering VI (OT) labor categories is 30084. Page 37 of 134, Section 11.1.2

Non‐ Key Personnel, paragraph z. TECHNICIAN, ENGINEERING VI, the eCraft Code is 30086. Would the

Government please clarify the correct eCraft Code for the Technician, Engineering VI labor category?

A14: C11.1 has been revised. Technician, Engineering VI is eCraft Code 30086. Code 30086, not 30084, was intended in the level of effort chart for Technician Engineering VI. This was a mistake in the code number in the level of effort chart.

Q15. Page 29 of 134, Section C 11. Personnel, level of effort chart shows 1920 hours per year for the Engineer

IV labor category. Page 31 of 134, Section C 11.1.1 Key Personnel paragraph b. ENGINEER IV, Level IV states “Although requiring one (1) resume, the level of effort table indicates that up to five (5) full-time equivalents (FTEs) could be necessary.” Page 104 of 134, Section L.3.2.1 SUBFACTOR 1A – PERSONNEL states “A level of effort of 1920 labor hours per man year should be utilized.” Would the Government please clarify whether the total FTEs and hours for the Engineer IV should be 1 FTE with 1920 hours per year as

Page 29 of 134 indicates, or 5 FTEs with a total of 9600 hours per year as Page 31 of 134 indicates?

A15: To clarify, the five full-time equivalents referred to in section C, 11.1.1, meant five full time equivalents could be necessary over the duration of the contract (5 years x 1920 hours/year). It wasn't assumed the same engineer would fulfill the role for the duration of the contract.

Q16. Page 49 of 134, HQ E-2-0015 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA)

(APR 2017), prior solicitations for engineering services that have been released by NSWCPD require that the contractor certify the use of quality systems during execution that in accordance with HQ E-2-0015 Quality

Management System Requirements (Sep 2009) that adhere to the requirements of ANSI/ISO/ASQ 9001-2008 or equivalent. The requirement for a QMS acceptance letter or in process QMS review is onerous given the scope of work described in the solicitation. Request the Government employ the standard clause cited and modify the solicitation accordingly.

A16: Request denied. Requirements remain unchanged.

Q17. Page 31 of 134, Section C 11.1.1 Key Personnel, the last sentence of the first paragraph states “The proposed combined expertise of all proposed key personnel shall cover at a minimum all requirements for task areas C.1-C.6 in the performance work statement.” However, there are no task areas C.1-C.6 in the performance work statement. Would the Government please clarify or amend this statement?

A17: Removed the sentence, "The proposed combined expertise of all proposed key personnel shall cover at a minimum all requirements for task areas C.1-C.6 in the performance work statement". The task areas referenced aren't called out in the performance work statement, and it would be too broad to capture all requirements with expertise provided by two key personnel listed.

Q18. Page 113 of 134, Section L.3.4.4 Cost Volume, Indirect Rates, and page 114 of 134, Section L.3.4.4 Cost

Volume, Indirect Costs, appear to be duplicate requirements. Would the Government please combine these two requirements so Offerors only need one cohesive response to indirect rates/costs?

A18: The Cost Volume and Indirect Rates on page 114 refer to the subcontractor(s).

Q19. Page 113 of 134, Section L.3.4.4 Cost Volume, Facilities Capital Cost of Money, and page 114 of 134, Section L.3.4.4 Cost Volume, Facilities Capital Cost of Money (FCCOM) appear to be duplicate requirements. Would the Government please combine these two requirements so Offerors only need one cohesive response to Facilities Capital Cost of Money?

A19: The FCCOM on page 114 refer to the subcontractor(s).

Q20. Page 113 of 134, Section L.3.4.4 Cost Volume, Fee and page 114 of 134, Section L.3.4.4 Cost Volume, Fee appear to be duplicate requirements. Would the Government please combine these two requirements so

Offerors only need one cohesive response to Fee?

A20: The Cost Volume and Fee on page 114 refer to the subcontractor(s).

Q21. Page 105 of 134, Section L, L.3.2.4 SUBFACTOR 1D – SUBCONTRACTING COMMITMENT states

“Offerors are encouraged to review DOD Small Business Prime Contracting Goals (available at the DOD

Office of Small Business Programs Website: http://www.acq.osd.mil/osbp/index.shtml ) when completing their offer.” The DOD SB Prime Contracting Goals are stated as 22% of total awarded contract value. This is consistent with the SeaPort-e Prime Contract goals which are 20% of total contract value.”

A21: This is not a SeaPort contract.

Q22. Page 106 of 134, Section L, L.3.2.4.1 SMALL BUSINESS PARTICIPATION COMMITMENT

DOCUMENT (SBPCD) states that the Minimum Quantitative Requirement for small business participation equal or greater than 40% of the total contract value. Proposals addressing the extent of small business performance shall be separate from subcontracting plans submitted pursuant to the clause at FAR 52.219-9 as required by DFARS 215.304 (c)(i)(B).

A22: The Offeror shall also provide a narrative on its plan to meet or exceed the baseline Minimum Quantitative

Requirement (MQR) for small business participation equal or greater than 40% of the Total Contract Value (TCV).

Q23. Page 106 of 134, Section L, L.3.2.4.1 SMALL BUSINESS PARTICIPATION COMMITMENT

DOCUMENT (SBPCD) also goes on to state that “ Although the information to be provided under this subfactor is different than the information required under Clause 52.219-9 “Small Business Subcontracting

Plan,” it should be in consonance with any subcontracting plan if required and with the information presented in its technical and cost proposal.” FAR 52.219-9 requires Offerors to express goals in terms of

Subcontracted value. Given the MQR of 40%, will the Government please clarify if this was intended to be expressed in terms of Subcontracted value which would bring it in line with the DOD and SPe TCV Goals?

A23: The Offeror shall also provide a narrative on its plan to meet or exceed the baseline Minimum Quantitative

Requirement (MQR) for small business participation equal or greater than 40% of the Total Contract Value (TCV).

Q24. Page 106 of 134, Section L, L.3.2.4.1 SMALL BUSINESS PARTICIPATION COMMITMENT

DOCUMENT (SBPCD) states, “In preparation of the SBPCD, please note the Minimum Quantitative

Requirement (MQR) specified in Section M,” however there is no MQR stated in Section M. Please Clarify?

A24: Removed the reference to the MRQ in Section M. The MQR is listed in 3.2.4.1:

In addition to the completion of Attachment 4, the Offeror shall also provide a narrative on its plan to meet or exceed the baseline Minimum Quantitative Requirement (MQR) for small business participation equal or greater than 40% of the Total Contract Value (TCV).

Q25. Page 31 of 134, Section 11.1.1 Key Personnel, a. MANAGER, PROGRAM/PROJECT II, under

Education states that “Individual shall possess a Bachelor of Science (B.S.) degree in any technical or managerial discipline from an accredited college or university.” Since a managerial discipline degree could be a Bachelor of Arts (B.A.), would the Government please modify the language to an “Individual shall possess a

Bachelor of Science (B.S.) or Bachelor of Arts (B.A.) degree”?

A25: Due to the technical nature of the work described in the SOW, it is intended that a BS degree, as indicated, would be required for the position of "Manager, Program/Project II".

Q26. Workflow Management, Start-up Plan, and Transition Plan are listed as being items that the Offeror must address in the Management Approach under section L.3.2.2 Subfactor 1B – Management Approach, but there are no evaluation factors listed in Section M for Workflow Management, Start-up Plan, and

Transition Plan. Would the Government provide evaluation factors for these sections?

A26: Section L.3.2.2 and M.2 have been revised.

Q27. Subcontract Management is listed as an item under Subcontracting Commitment in section L.3.2.4

Subfactor 1D – Subcontracting Commitment, but there are no evaluation factors listed in Section M for

Subcontract Management. Would the Government provide evaluation factors for this section?

A27: Section L.3.2.2 and M.2 have been revised.

Q28. In Section L.3.2.2 Subfactor 1B – Management Approach on pages 104-105, under part (a) Resources, the Government asks the offeror to address its “ability to respond to workload fluctuations and to perform overlapping and separate tasks in a timely manner” and to address its “plan to engage in full performance of the task order once the firm receives notice of award.” In the same section under part (d) Workflow

Management, the offeror is asked once again “provide information regarding its ability to respond to workload fluctuations and to perform overlapping and separate tasks in a timely manner.” Furthermore, in the same section under part (e) Start-up Plan, the offeror is asked once again to describe its “plan to engage in full performance of the contract once the firm receives notice of contract award.” Would the Government please clarify where offerors should address Workload Fluctuations and the Start-up Plan?

A28: Section L.3.2.2 has been revised and M.2 have been revised.

Q29. Would the Government confirm that Service Contract Labor Standards do not apply to this solicitation?

A29: This requirement is for professional services.

Q30. Page 100, Section L.2.1. states that tables are allowed for the list of key personnel. Is the Offeror permitted to use tables to display other information, for example to discuss the subcontractor information requested in Subfactor 1D? The use of tables in proposal will allow for the better presentation of information and readability.

A30: Information provided must be in the required format. Tables can be used in addition to information provided in the required format.

Q31. In Section 3.4, Other Support, on page 20 of the solicitation, it states that “Authorization for SECRET

Internet Protocol Router Network (SIPRNet) is required for some portions of work outlined in Sections 4.0, 4.1, 4.2, 4.3, 4.4, and 4.5.” These sections, under 4 Data Requirements, deal with CDRLs and likely do not require access to SIPRNet. Would the Government please clarify the sections of the statement of work that require access to SIPRNet?

A31: The sections referenced should not be, "4.0, 4.1, 4.2, 4.3, 4.4, and 4.5" for SIPRNet. The sections referenced were corrected to, "3.0, 3.1, 3.2, 3.3, 3.4, and 3.5." The requirements would also be addressed in greater detail at the task order level.

Q32. Page 2 of the solicitation in note 1 states that the ordering period for this procurement will be from date of contract award through sixty months thereafter. Will the Government provide an additional year in the period of performance to allow for work issued in option year four to be completed before the end of the performance period?

A32: Each task order will have its own period of performance. See revised Section B.

Q33. On page 121 of the solicitation, the Government has included clause 252.234-7001 for use of an Earned

Value Management System (EVMS). Since this is primarily a services vice acquisition contract, this requirement does not seem appropriate to this solicitation. Would the Government consider deleting this

EVMS clause from this solicitation?

A33: EVMS clause is required and will stay in the solicitation.

Q34. Page 32, Section 11.1.1 Key Personnel item b. ENGINEER IV, LEVEL IV states that “Although requiring one (1) resume, the level of effort table indicates that up to five (5) full-time equivalents (FTEs) could be necessary.” However the Level of Effort (LOE) table on page 29 does not support this statement.

Would the Government please clarify the anticipated LOE for this labor category?

A34: To clarify, the five full-time equivalents referred to in section C, 11.1.1, meant five full time equivalents could be necessary over the duration of the contract (5 years x 1920 hours/year). It wasn't assumed the same engineer would fulfill the role for the duration of the contract.

Q35. Will the Government allow for the hand delivery of Offeror’s proposals?

A35: Proposals must go through the mail room and cannot be hand delivered to the Contract Specialist or the

Contracting Officer.

Q36. Due to the number of questions needing clarification in combination with the upcoming holidays would the Government grant a two week extension?

A36: Due date on RFP N6449818R4015 has been extended to 14 January 2019

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 31-Dec-2018 02:00 PM to 14-Jan-2019 02:00 PM.

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been modified:

NOTES

1. CONTRACT TYPE: Naval Surface Warfare Center Philadelphia Division, Philadelphia, PA intends to award multiple indefinite-delivery, indefinite quantity, cost-plus-fixed-fee type contract(s) providing support services as described in Section C, Statement of Work. The resultant contract(s) will also contain provisions for task orders to be awarded on a fixed price basis when feasible. The contract shall have an ordering period from date of contract award through sixty (60) months thereafter. The ordering period for this acquisition is anticipated to be five (5) years, with a six (6) year potential period of performance.

2. BASIS OF COMPETITION:

a. At the Task Order level, award determination will be conducted in accordance with clause PD-I02 “ORDERING

PROCEDURES FOR DELIVERY/TASK ORDERS ISSUED UNDER MULTIPLE AWARD CONTRACTS” in accordance with FAR 19.502-2.

b. This multiple award contract will expire when either the ordering term expires or the cumulative total of all orders issued to all awardees equals the Government's total program estimate. To be specified at the time of award.

c. The contractor shall not be obligated to continue performance beyond the estimated total hours estimated in this

RFP.

d. The minimum value of services (including Cost-Plus-Fixed-Fee) that must be ordered from each awardee will be

$10,000. The minimum shall be satisfied by the issuance of the first Task Order issued under the resultant contract award(s).

e. The rate of man-hours used may fluctuate throughout the term of the contract provided such fluctuation does not result in the utilization of the total man-hours of effort prior to expiration of the term. If at any time during the performance of this contract, the number of direct labor hours (not including “excess hours*”) utilized under this contract exceeds 75% of the total estimated hours, the contractor shall immediately notify the contracting officer of such circumstances. *Excess hours represent hours exceeding the estimated LOE amount.

f. Nothing herein shall be construed to alter or waive any of the rights or obligations of either party pursuant to the clause hereof entitled “Limitation of Cost” and/or “Limitation of Funds”.

g. It is understood and agreed that the number of hours and total dollar amount of each labor category specified in any task order issued under these contracts are estimates only and shall not limit the use of hours or dollar amounts in any labor category which may be required and provided for under an individual task order.

h. The Government intends to reimburse Other Direct Costs (CLIN 0004) on the basis of actual reasonable and allowable costs incurred plus applicable indirect markup rates (i.e. G&A and material handling). (NO FEE WILL

BE PAID FOR ODC’S)

i. If an offeror fails to identify, as part of its proposal, an indirect cost rate(s) that would otherwise be applicable to one (1) of the support cost items, it shall not be allowed to invoice for the indirect rate(s) after award since the evaluation of its offer did not include the rate(s).

j. In accordance with 252.215-7010 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND

DATA OTHER THAN CERTIFIED COST OR PRICING DATA, please submit Other Than Certified Cost or

Pricing Data with your proposal submission in order to support your proposal.

HQ B-2-0015 - PAYMENT OF FEES(S) (LEVEL OF EFFORT) – ALTERNATE I (NAVSEA) (MAY 2010)

(a) For purposes of this contract, "fee" means "target fee" in cost-plus-incentive-fee type contracts, "base fee" in cost-plus-award-fee type contracts, or "fixed fee" in cost-plus-fixed-fee type contracts for level of effort type contracts.

TBD

(b) The Government shall make payments to the Contractor, subject to and in accordance with the clause in this contract entitled "FIXED FEE" (FAR 52.216-8) or "INCENTIVE FEE", (FAR 52.216-10), as applicable. Such payments shall be submitted by and payable to the Contractor pursuant to the clause of this contract entitled "ALLOWABLE COST

AND PAYMENT" (FAR 52.216-7), subject to the withholding terms and conditions of the "FIXED FEE" or

"INCENTIVE FEE" clause, as applicable, and shall be paid at the hourly rate(s) specified above per man-hour performed and invoiced. Total fee(s) paid to the Contractor shall not exceed the fee amount(s) set forth in this contract. In no event shall the Government be required to pay the Contractor any amount in excess of the funds obligated under this contract.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

Statement of Work for

Division 41 Engineering and Technical Services

1.0 INTRODUCTION

1.0.1 The Naval Surface Warfare Center Philadelphia Division (NSWCPD) is a Department of Defense entity responsible for research and development, test and evaluation, engineering and fleet support organization for the

Navy’s ships, submarines, military watercraft and unmanned vehicles. This requirement is for NSWCPD Division

41, which is responsible for Auxiliary Machinery Systems.

1.0.2 This contract is for non-personal services. It does not create employment rights with the U.S. Government whether actual, inherent, or implied

1.0.3 Government / Contractor Relationship

(a) The services to be delivered under this Task Order are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the task order between the Government and the

Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.

(b) The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence

(c) Contractor personnel under this task order shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.

(d) Employee Relationship:

1) The services to be performed under this Task Order do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.

2) Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.

(e) Inapplicability of Employee Benefits: This task order does not create an employer-employee relationship.

Accordingly, entitlements and benefits applicable to such relationships do not apply.

(f) Notice. It is the Contractor's, as well as the Government's, responsibility to monitor task order activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.

1) The Contractor should notify the Contracting Officer in writing within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or

Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the estimate in time by which the Government must respond to this notice to minimize cost, delay, or disruption of performance.

2) The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:

(i) Confirm the conduct is in violation and when necessary direct the mode of further performance,

(ii) Countermand any communication regarded as a violation,

(iii) Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or

(iv) In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.

1.1 BACKGROUND

This statement of work (SOW) establishes the level of effort required for providing services in support of programmatic, administrative, engineering, technical, logistical, maintenance, installations/alterations support, life cycle management, technical data management, and catalog update support for Hull, Mechanical and Electrical

(HM&E) systems for the Naval Surface Warfare Center Philadelphia Division (NSWCPD), specifically for the

Auxiliary Machinery Systems Division (Division 41).

1.2 SCOPE OF WORK

The overall scope of this SOW is to provide: programmatic; administrative; engineering; technical; training;

logistical; maintenance; installations/alterations; Life Cycle Management; technical data management; catalog updating, and general systems, and equipment support for HM&E systems for the NSWCPD, specifically for the

Auxiliary Machinery Systems Division (Division 41, consisting of Codes: 411, 412, 413, 414, 416, and 418) or

NSWCPD Support Codes that directly support the Auxiliary Machinery Systems Division. Tasks will include the following: alterations support; equipment life cycle management; ship change documents (SCDs); ship alterations

(SHIPALTS); data collection, and analysis; metrics; system design; development, and testing support; engineering development models; system operability testing, and logistic product development. Services will be rendered, as required, in Philadelphia, PA, and ports on the East Coast, West Coast and Outside the Continental United States

(OCONUS), refer to paragraph 7, “Travel” of this SOW.

Services in this SOW refer to all classes of U.S. Navy platforms, as well as U.S. Coast Guard, U.S. Army, and

Foreign Military Sales ships, and vessel classes.

The specific HM&E machinery and systems that shall be supported by the services described under this SOW are limited to Naval main propulsion steam systems, secondary steam systems, and auxiliary machinery, and systems, for all classes of aircraft carriers, surface ships, and submarines. Systems, and equipment must fall within the purview of Division 41, examples are as follows:

DIVISION 41 MAJOR SYSTEM AREAS:

Air Conditioning, and Refrigeration Systems

Steam Systems

Auxiliary Systems

Combat Support Systems

Life Support, and Ventilation Systems

Compressed Air Systems

CODE 411, AIR CONDITIONING, AND REFRIGERATION:

Air Conditioning Systems

Chlorofluorocarbon (CFC) Conversion

Refrigeration Systems

Thermal Management

Army Heating Ventilation, and Air Conditioning (HVAC)

Refrigerant Monitors

Modular Refrigeration Units (MRUs)

High Efficiency Small Capacity (HES-C) Air Conditioning Plant

CODE 412, STEAM SYSTEMS:

Navy/Power Boiler Systems

Stationary Plant Steam Systems

Deaerating Feed Tank

CVN Steam Catapult Launch System Accumulators

Steam Propulsion Turbines, and Ships Service Turbine Generators (SSTGs)

Steam Piping/Valves

Forced Draft Blowers

Condensers

CVN Propulsion Plant Steam Systems

CVN Reboilers

Unfired Pressure Vessels (UPVs)

Burner Ignitor/Management Systems (BIS/BMS)

Boiler Combustion Monitoring System

Boiler Combustion Optimization System

Military Sealift Command (MSC)/Marine Administration (MARAD)/Foreign Military Sales (FMS)

Steam System Support

Program Management for: Boiler Inspection, and Repair Management Information System

(BIRMIS); Steam Catapult Inspection, and Repair Management Information System

(SCIRMIS), and Reboiler Inspection, and Repair Management Information System

RIRMIS

Steam Generating Plant Inspectors (SGPI) Program

Excludes Steam System Readiness Program

CODE 413, AUXILIARY SYSTEMS:

Centrifugal/Positive Displacement (PD) Pumps

Pump Components

Auxiliary Turbines

Fuel Oil/Lube Oil System

Biofouling Technology

Purifiers

Ballast/Deballast System

Related Piping, Valves and Components

Submarine Fluid Systems, and Auxiliary Machinery

Submarine Safety (SUBSAFE) Design Review

Desalination Systems

Heat Exchangers

Main Feed/Condensate/Booster Systems

Fresh Water Systems

Reverse Osmosis Technology

Sea Water Systems

CODE 414, COMBAT SUPPORT SYSTEMS:

Vertical Launching System (VLS) Hull, Mechanical, and Electrical (HM&E) Systems

Chilled Water System

Electronic Cooling Water System

Sonar Dome Pressurization System

Smart Valves

Bleed Air/Prairie Masker

Weapon System Cooling

Related Piping, Valves and Components

Laser, and Rail Gun Cooling Systems

Main and Secondary Drainage

Valve Actuators

CODE 416, LIFE SUPPORT, AND VENTILATION SYSTEMS:

Automated Electrolytic Oxygen Generator (AEOG)

Electrolytic Oxygen Generator (EOG)

Low Pressure Electrolyzer (LPE)

Integrated Low Pressure Electrolyzer (ILPE)

Advanced Integrated Low Pressure Electrolyzer (AILPE)

Central Atmosphere Monitoring System (CAMS)

Gas Management System (GMS)

Carbon Dioxide (CO2) Scrubber

Carbon Monoxide (CO) – Hydrogen (H2) Burners

Collective Protection System (CPS)

Oxygen Candles

Cooling Coils

Fan Cooling Units

Ventilation Systems, and All Related Ductwork

CPS Filters

Coast Guard CPS

Advanced Carbon Dioxide Removal Unit (ACRU)

CODE 418, COMPRESSED AIR SYSTEMS:

Compressed Air Systems

Air Compressors

Air Dehydrators

Submarine Diver’s Air, and Emergency Main Ballast Tank (EMBT) Blow Support

Oxygen (O2) Nitrogen (N2) Plants

Vacuum Swing Absorber (VSA) Oxygen Producers

Membrane Nitrogen Producers

2.0 APPLICABLE DOCUMENTS

Note: The Contractor shall reference and utilize the latest version available when performing tasks within this SOW.

a. DODI 5000.02 Operation of the Defense Acquisition System

(http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/500002_dodi_2015.pdf?ver=2017-

08-10-112047-843)

b. Naval Sea Systems Command (NAVSEA) SL720-AA-MAN-030/TS9090-310G - Alterations to Ships

Accomplished by Alteration Installation Teams

(http://www.navsea.navy.mil/Portals/103/Documents/NSWC_Dahlgren/FiberOptics/Appendix_H_TS9

090-310G_Approved_2015-2-12.pdf)

c. Digital Technical Information for Multi-Output Presentation of Technical Manuals (Work Package

Concept) - MIL-STD-3001, dated 01 Dec 2016, (http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=280652)

d. Manuals, Technical: General Style and Format Requirements - MIL-STD-38784A(1), dated 11 Jul

2016, (http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=116799)

e. Database, Revisable Interactive Electronic Technical Manuals, for the Support of - MIL-PRF-87269D, dated 30 Jan 2014, (http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=109242) http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/500002_dodi_2015.pdf?ver=2017-08-10-112047-843 http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodi/500002_dodi_2015.pdf?ver=2017-08-10-112047-843 http://www.navsea.navy.mil/Portals/103/Documents/NSWC_Dahlgren/FiberOptics/Appendix_H_TS9090-310G_Approved_2015-2-12.pdf http://www.navsea.navy.mil/Portals/103/Documents/NSWC_Dahlgren/FiberOptics/Appendix_H_TS9090-310G_Approved_2015-2-12.pdf http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=280652 http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=116799 http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=109242

f. Manuals, Technical: General Acquisition and Development Requirements, General Specification for -

MIL-DTL-24784, (http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=114691)

g. Technical Manual Users Quick Reference Guide - S0005-AG-GYD-010

(https://mercury.tdmis.navy.mil – CAC, and TDMIS account required for weblink access. Document also available upon request.)

h. NAVSEA Technical Manual Management Program; Operations and Life Cycle Support Procedures –

S0005-AA-PRO-010

i. NAVSSES Instruction 4720.2F Process and Policy for Managing Shipboard Industrial Work

Performed by Alteration Installation Teams (AITs)

(https://navsea.navy.deps.mil/wc/pnbc-divproj/instructions/Instructions/s4720-

2f_Process%20andPolicyforManagingShipboard%20Industrial%20Work%20Performed%20by%20AI

Ts_Code%209170_2011-07-27.pdf)

j. NAVSEA TM S6434-AR-MMM-010 Pressure Reducing Manifolds for High Pressure Air, Oxygen

And Nitrogen Systems (https://mercury.tdmis.navy.mil – CAC, and TDMIS account required for weblink access. Document also available upon request.)

k. NAVSEA TM S6434-BE-MMA-010 High Pressure Gas Reducing Manifold

l. NAVSEA S9AA0-AB-GOS-010, "General Specifications for Overhaul (GSO) of Surface Ships".

(https://mercury.tdmis.navy.mil – CAC, and TDMIS account required for weblink access. (Document also available upon request)

m. NAVSEA 0948-LP-045-7010 Material Control Standard, Volume 1

(Note: This document is Distribution B and can only be obtained by request through NAVSEA. The

POC is listed in the remarks section for the manual in TDMIS.

n. Joint Fleet Maintenance Manual Vol. V, Part III, Chapter 6

(https://www.submepp.csd.disa.mil/JFMM/documents/00_JFMM.pdf)

o. Standard Department of Defense (DoD), DON, NAVSEA, Naval Ship Systems Engineering Station

(NAVSSES), NSWCPD, Occupational Safety and Health Administration/Agency (OSHA), and other task-specific regulations in effect during the performance of the contract.

p. OPNAVINST N9210.3, Safeguarding of Naval Nuclear Propulsion Information (NNPI) of 7 Jun 2010.

q. SECNAV M-5239.2, Cyberspace Information Technology and Cybersecurity Workforce Management and

Qualification Manual.

(https://doni.documentservices.dla.mil/SECNAV%20Manuals1/5239.2%20(2016).pdf)

r. DoD 8570.01-M, Information Assurance Workforce Improvement Program.

(http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodm/857001m.pdf)

s. DoD 8140, Cyberspace Workforce (CSWF) Management (pending issue, takes effect when issued, and will be addressed at task order level)

t. ISO-9001:2015 Quality Management Systems - http://www.iso.org http://quicksearch.dla.mil/qsDocDetails.aspx?ident_number=114691 https://mercury.tdmis.navy.mil/ https://mercury.tdmis.navy.mil/ https://navsea.navy.deps.mil/wc/pnbc-divproj/instructions/Instructions/s4720-2f_Process%20andPolicyforManagingShipboard%20Industrial%20Work%20Performed%20by%20AITs_Code%209170_2011-07-27.pdf https://navsea.navy.deps.mil/wc/pnbc-divproj/instructions/Instructions/s4720-2f_Process%20andPolicyforManagingShipboard%20Industrial%20Work%20Performed%20by%20AITs_Code%209170_2011-07-27.pdf https://navsea.navy.deps.mil/wc/pnbc-divproj/instructions/Instructions/s4720-2f_Process%20andPolicyforManagingShipboard%20Industrial%20Work%20Performed%20by%20AITs_Code%209170_2011-07-27.pdf https://mercury.tdmis.navy.mil/ https://mercury.tdmis.navy.mil/ https://mercury.tdmis.navy.mil/ https://www.submepp.csd.disa.mil/JFMM/documents/00_JFMM.pdf https://doni.documentservices.dla.mil/SECNAV%20Manuals1/5239.2%20(2016).pdf http://www.esd.whs.mil/Portals/54/Documents/DD/issuances/dodm/857001m.pdf

u. MIL-P-24534: Planned Maintenance System: Development of Maintenance Requirement Cards, Maintenance Index Pages, and Associated Documentation. http://everyspec.com/MIL-SPECS/MIL-

SPECS-MIL-M/MIL-M-38784A_12893/

v. NAVSEAINST 4120.8A, NAVSEA Policy for Commonality of Ships, Systems, Subsystems, and

Components https://navsea.navy.deps.mil/hq/Docs/Instructions/04120.08A.pdf

3.0 REQUIREMENTS

3.0.1 The Contractor shall provide engineering, technical, Program Management, and logistics support for Hull, Mechanical, and Electrical (HM&E) systems onboard U.S. Navy, and other maritime vessels. The Contractor shall be required to provide support to the Program Office, and the Program Field Offices.

3.0.2 The following outlines Contractor requirements, and will be supplemented by specific work statements in individual Task Orders. Task Orders will vary in the level, and complexity of requirements, from the full scope of the technical services of this Statement of Work (SOW) to portions of the SOW only. CDRL A009

Note: CDRLs A001, A002, A003, and A004 apply to all items in the requirements section.

3.0.3 The Contractor shall maintain a Quality Management System (QMS) in accordance with ASQ/ANSI/ISO

9001:2015 standards per Naval Sea Systems Command (NAVSEA) QMS Acceptance Authority or appropriate directorate requirements.

• All QMS packages are required to adhere to applicable NAVSEA Technical Specification 9090-310 and

NAVSEA Standard Item 009-04 requirements. Notify NSWCPD’s Quality Department in writing when any changes are made to the QMS that may affect work defined in accordance with NAVSEA Technical

Specification 9090-310.

• Submit its QMS Level 3 specific work procedures relevant to the requirements of the Solicitation, including the SOW at the Task Order level (i.e. welding, etc.).

3.1 ENGINEERING/TECHNICAL SERVICES

Engineering, and technical requirements in this section refer to the equipment, and systems listed in section 2.0 of this SOW, and systems under the cognizance of Division 41.

3.1.1 Recommendations on preliminary design, detail design, and drawings including manufacturing, and testing new components, and systems. CDRL A005

3.1.2 Tasks can include: quality assurance reviews; assistance with quality assurance workbooks (QAWBs); pre-, and post-installation ship checks to verify the accuracy of installation drawings; ensure correct equipment, and logistic configuration for verification, and technical accuracy; identify discrepancies between installation drawings, and actual vessel configuration; identify interferences, and support for ship change documents (SCD) Technical

Assessment Team (TAT) reviews to ensure timely delivery of quality products to the Fleet. This covers initial ship checks to establish as built conditions, trip report packages containing existing details, and design considerations.

CDRL A007

3.1.3 Provide support to the Enhanced Quality of Life (EQOL) for NSWCPD, including: program management, engineering, and design support for modification, and renovation of spaces onboard CVNs. Develop, and review engineering drawings for the installation of equipment, and space modifications to accommodate them. CDRL

A005

3.1.4 Project management, programmatic support (refer to paragraph 3.3 for details), engineering/technical support, including development of deficiency report responses, engineering change proposals, modification work orders, and http://everyspec.com/MIL-SPECS/MIL-SPECS-MIL-M/MIL-M-38784A_12893/ http://everyspec.com/MIL-SPECS/MIL-SPECS-MIL-M/MIL-M-38784A_12893/ https://navsea.navy.deps.mil/hq/Docs/Instructions/04120.08A.pdf alterations. Provide market research, engineering support, and recommendations on obsolescence, engineering deficiency, and new capability to support technical concerns. CDRL A008

3.1.5 Project management, programmatic, engineering/technical support, test procedure development, testing, and onsite coordination support for programs, including Machine Alterations (MACHALTs), and/or Source Control

Documents (SCDs) in accordance with the drawings/instructions provided including interface with: Program

Managers (PMRs); Regional Maintenance Centers (RMCs); Port Engineers; Type Commanders (TYCOMs);

Surface Orientation (SUFOR); Military Sealift Command (MSC); Foreign Military Sales (FMS), and Fleet components. CDRLs A005, A007, A008

3.1.6 Provide Ship system configuration, testing, training, support, and assessments of HM&E systems aboard the following hull types: Auxiliary, Submarine Tender Ship (AS); Guided Missile Cruiser (CG); Aircraft Carrier, Nuclear powered (CVN); Guided Missile Destroyer (DDG); Guided Missile Frigate (FFG); Amphibious Command

Ship (LCC); Littoral Combat Ship (LCS); Landing Helicopter Assault (LHA); Landing Helicopter Dock (LHD);

Amphibious Transport Dock (LPD); Land Ship Docking (LSD); Mine Countermeasures (MCM); Ship Submersible

Nuclear (SSN); Submersible Ship Ballistic-Missile Nuclear (SSBN); Ship Submersible Guided Missile-Nuclear

(SSGN), and other U.S. Navy, U.S. Coast Guard, U.S. Army, and FMS ship and vessel classes. Access to restricted areas/spaces that contain restricted data may be required. CDRL A007

3.1.7 Design, development, modeling, and testing of Ship systems. CDRL A007

3.1.8 Provide support for Ship system development and testing. This includes review of technical documentation, and distance support. CDRLs A007, A008

3.1.9 Support of Equipment Guide Lists (EGLs), and databases containing the results of the audits performed on ships. CDRL A007

3.1.10 Development, and modification of procedures, that include: testing; check-out; troubleshooting of systems, and equipment, and support in preparing Mission Readiness Panels (MRPs). CDRL A007

3.1.11 Aviation Certification Systems support, including assessments. CDRL A007

3.1.12 Identify, research, and analyze emerging technologies for current, and future ship classes, with a focus towards inclusion of this technology in the current, and future fleet.

3.1.13 Management and support of high visibility life cycle engineering concerns for the Navy Nuclear secondary propulsion systems including Warfighter Improvement Program (WIP) items, Steam Plant Action Requests

(SPARs), Steam Plant Liaison Inquiries (SPLIs), and Logistics Assessment Reviews (LARs).

3.1.14 Technical analysis, inspection, and assessments for systems, and equipment within the purview of Division

41. CDRL A007

3.1.15 Ship system support for process control equipment.

3.1.16 Participate in the design, development, or modification of new, and existing Systems Engineering Processes

(SEP), Capability Maturity Model Integration (CMMI), and documentation as directly related to systems. CDRL

A007, A008

3.1.17 Perform reviews of certification documentation and Objective Quality Evidence (OQE) in preparation of certification letters for ship platforms including SSNs and SSBNs. CDRL A007

3.1.18…