About this file
This document is an amendment to Solicitation N6426724Q0247 for the JSWTR Power System Revitalization requirement. The amendment adds serial numbers to Section C, attaches a Q&A document to Section J, and extends the solicitation close date from August 28, 2024 to August 30, 2024.
The requirement is for the revitalization and modular battery replacement of an APC Symmetra PX 100kW uninterruptible power supply (UPS) system, as well as the battery and DC capacitor replacement of a Galaxy 5000 50kVA UPS system. All work must be performed by Schneider Electric authorized and certified technicians using Schneider Electric or Schneider Electric certified equipment. The scope includes shipping, freight, disposal of old equipment, installation, and operational verification. The Government will award a single purchase order to the responsible offeror whose quote conforms to the requirements and is most advantageous based on the evaluation criteria.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Question and Answer.pdf | ||
| Combined Synopsis Solicitation.pdf | ||
| Brand Name Justification Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to add serial numbers to section C, attach Q&A to section J, and extend the solicitation close date.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Aug-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6426724Q0247
X 9B. DATED (SEE ITEM 11)
21-Aug-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Aug-2024
CODE
NAVAL SURFACE WARFARE CENTER CORONA DIV.
1999 FOURTH STREET BLDG 510
NORCO CA 92860
N64267 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6426724Q0247
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 28-Aug-2024 04:00 PM to 30-Aug-2024 02:00 PM.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
PURCHASE DESCRIPTION
SALES TAX EXEMPTION
The contractor is hereby advised that the United States Government and Agencies thereof are exempt from State and Local Government tax by virtue of Article 6 of the United States Constitution. No exemption certificate is required.
1.0 SCOPE
Symmetra PX Revitalization and Modular Battery Replacement and Galaxy 5000 Battery Replacement.
2.0 BACKGROUND
PMA-205 OSSA requirements are that the Schneider Electric equipment must be maintained according to manufacturer’s recommendations to include recommended battery replacements and revitalization.
3.0 SCOPE
1) APC Symmetra PX 100kW MPRS and modular battery replacement. All technicians must be authorized Schneider Electric technicians, certified by Schneider Electric to perform installations and maintenance on the equipment. All equipment must be Schneider Electric, or Schneider Electric certified or authorized equipment.
2) Galaxy 5000 50 kVA battery and DC Capacitor replacement. All technicians must be authorized Schneider Electric technicians, certified by Schneider Electric to perform installations and maintenance on the equipment. All equipment must be Schneider Electric, or Schneider Electric certified or authorized equipment.
3) Shipping, freight, disposal.
4) Installation and operational verification. All technicians must be authorized Schneider Electric technicians, certified by Schneider Electric to perform installations and maintenance on the equipment. All equipment must be Schneider Electric, or Schneider Electric certified or authorized equipment.
4.0 REQUIREMENTS
CLIN Part Number Description Qty
APC Symmetra PX 100kW Power Frame 208V
0001 WMBRS8-MB-T9B4 Modular Battery Replacement Service
(SYBT9-B4)
0002 WMPRS10-MP2-110 Modular Power Revitalization Service
(SYPM10KF2)
Galaxy 5000 50 kVA
0003 WBATTREPLC-G5-00 Battery Replacement Service - Install and Removal Labor per Battery
0004 WBATTDISP WBATTDISP - Battery Disposal Service
0005 0J-0M-34605676AA DC CAPA KIT G5K 40-60 KVA -
SPARE PART
0006 0J-234-3105SE CAP 1200VDC 1UF - SPARE PART 2
0007 0J-0P3822 FIAZN PCBA GALAXY5000 -SPARE
PART
0008 WCAPREPLC-G5-00 Complete DC Capacitor Replacement Service Labor
0009 QWBATT-
QMSC34411-NSUSD
(ENERSYS
NPX150RFR)
REPLACEMENT BATTERY
ENERSYS NPX150RFR
Model Description Serial
G5TUPS50 Galaxy 5000 C11738190031
SYCF100KF Symettra PX 100kW 208V PD1449150104
ACRD100 InRow RD 300mm 208-230V 60Hz JK1512002049
ACRD100 InRow RD 300mm 208-230V 60Hz JK1725002875
ACRD600 InRow RD 600mm 200-240V 50/60Hz JK1718000929
ACRD600 InRow RD 600mm 200-240V 50/60Hz JK1721000243
ACRD600 InRow RD 600mm 200-240V 50/60Hz JK1721000244
1) APC Symmetra PX 100kW MPRS and modular battery replacement. All technicians must be authorized Schneider Electric technicians, certified by Schneider Electric to perform installations and maintenance on the equipment. All equipment must be Schneider Electric, or Schneider Electric certified or authorized equipment.
2) Galaxy 5000 50 kVA battery and DC Capacitor replacement. All technicians must be authorized Schneider Electric technicians, certified by Schneider Electric to perform installations and maintenance on the equipment. All equipment must be Schneider Electric, or Schneider Electric certified or authorized equipment.
3) Shipping, freight, and disposal of old equipment, package containers, and other waste produced during the service.
4) Installation and operational verification. All technicians must be authorized Schneider Electric technicians, certified by Schneider Electric to perform installations and maintenance on the equipment. All equipment must be Schneider Electric, or Schneider Electric certified or authorized equipment.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been added by full text:
ATTACHMENTS
The following document(s), exhibit(s), and other attachment(s) form a part of this contract:
Question and Answer
(End of Summary of Changes)