Questions_and_Answers_of_N6426719R0034.docx
DOCX document 12 KB Posted
- Attached to
- VLS Drill Fixtures
- Solicitation number
- N6426719R0034
About this file
Additional Questions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_of_N6426719R0034.docx | DOCX document | |
| Solicitation_Amendment.pdf | ||
| N6426719R0034_.pdf | ||
| https://www.fbo.gov/notices/92acbda295dfb5fd06e30f49b6484b9c | HTML file | |
| SOW_VLS_Drill_Fixture_Draft.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers of N6426719R0034 Question: For VLS Drill Fixtures, the SOW states the first two fixtures are due 4 months after contract date and the solicitation document states 6 months. Which of these time periods is correct?
Answer: Refer to the solicitation for delivery dates and all specifications. The Draft SOW that was used in the Pre-solicitation phase has since been modified. The most current version of the SOW can be found in Section C of the Solicitation.
Question: Would the Navy consider proposals offering greater lead times than (6) months?
Answer: Delivery timeframe is a requirement for technical acceptability. Each offer should contain the offeror’s best terms from a technical and price standpoint.
Question: Is there CAD available to support this requirement?
Answer: CAD or other model will not be available; only available drawings.