N63394-17-R-0030_AMENDMENT_0002.pdf
PDF 92 KB Posted
- Attached to
- Gun Mount Control Panel Federal contract opportunity
- Solicitation number
- N63394-17-R-0030
About this file
Amendment 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ESS21202-02a.docx | DOCX document | |
| GMCP_A004_DI-NDTI-80809B_Test_Inspection_Report_09Feb17.pdf | ||
| GMCP_A003_DI-NDTI-80603A_Test__Procedure__09Feb17.pdf | ||
| N63394-17-R-0030_AMENDMENT_0001.pdf | ||
| N63394-17-R-0030.pdf | ||
| CDRLs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide answ ers to technical questions.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 23-Feb-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N63394-17-R-0030
X 9B. DATED (SEE ITEM 11)
20-Jan-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriat ion date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not , is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
23-Feb-2017
CODE
NAVAL SURFACE WARFARE CENTER
PORT HUENEME DIVISION
4363 MISSILE WAY
PORT HUENEME CA 93043-4307
N63394 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N63394-17-R-0030
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been added by full text:
QUESTIONS & ANSWERS II
QUESTIONS AND ANSWERS – PART II
All of the following questions pertain to the ESS21202‐02a document:
Question 1). Section 3.2 Test Overview: Question: Is a Vibration Survey required on every unit? How many response accelerometers would be required and where would they be mounted?
Answer 1). The vibration survey is not required for each unit. A new vibration survey would be required in the case that the original is no longer valid or applicable, such as when significant changes have been made to the vibration fixture or mounting. The number and location of sensors is not prescribed and will depend on the vibration fixture and mounting being utilized.
Question 2). Section 4.3 Test Procedure: Question: Can you provide a copy of the ESU7402675‐002 Environmental Setup Sheet for P/N 7402675?
Answer 2). No, ESU7402675-002 is not a Government document and will not be provided.
Question 3). Figure 4.0‐1 GMCP Axis Definition page 7: Question: What is the length of the cable attached to that supplemental box ‐ does it go on the table as well?
Answer 3). The "supplemental box" is GMCP unit A3 "Isolation Transformer Assembly". It is part of the GMCP and is required to undergo ESS as part of the complete GMCP assembly. Note that these cables are functionally equivalent to W35262 and W35263 in SOW appendix B, however the cables being delivered with the unit are to be terminated at one end only. The contractor will likely want to prepare a separate pair of "test" cables to support ESS and acceptance testing. Such cables should not be longer than specified in appendix B but may be shorter than specified to facilitate testing.
Question 4). Figure 4.0‐2, GMCP ESS Vibration Profile ‐ X‐Axis: Question: A 6 GRMS profile is indicated in several places however the figures below show a Ref GRMS of a lesser value?
Answer 4). The initial 6 GRMS profile was notched per the results of the vibration survey as described in MIL-
HBDK-2164A.
N63394-17-R-0030
Question 5). Figure 4.0‐2, GMCP ESS Vibration Profile ‐ X‐Axis: Question: We need the break point table for this PSD curve, can you provide it?
Answer 5). No, the break point table will not be provided.
Question 6). Section Test Procedure, Bullet (A7) ‐ Question: Can you provide notional diagram of setup and/or ICD?
Answer 6). Unclear how "notional diagram of setup and/or ICD" relate to "Test Procedure, Bullet (A7)". The unit ICD is already provided (X7402676). ESS-specific setup information is in ESU7402675-002 addressed above.
Question 7). Table 5.0‐I, GMCP Thermal Cycle Programming Table: Question: This corresponds to 80 hours of test, not 40? Please clarify.
Answer 7). The unit is only powered on during certain portions of the cycle; the unit is powered on for 40 hours of the 80+ hour total time indicated.
(End of Summary of Changes)