DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND, PACIFIC
258 MAKALAPA DR., STE. 100
PEARL HARBOR, HI 96860-3134
N62742-19-R-0003
Notice No. 1
12 March 2019
PRE-PROPOSAL QUESTIONS & ANSWERS
ANNOUNCEMENT N62742-19-R-0003
INDENIFINTE DELIVERY INDEFINITE QUANTITY ARCHITECT-ENGINGEER
SERVICES FOR VARIOUS ELECTRICAL ENGINEERING PROJECTS AND RELATED
SERVICES AT VARIOUS LOCATIONS IN ALL AREAS UNDER COGNIZANCE OF
NAVAVL FACILITES ENGINEERING COMMAND, PACIFIC
NOTE: The following questions and answers are provided for INFORMATION ONLY. The announcement remains unchanged unless it is modified in writing.
1. Regarding announcement N6274219R0003, can you please clarify whether or not Attachment C can be included as an Appendix that is not counted as part of the 75 page limit of Part I?
ANSWER: Attachment C is not included in the 75 page limit of Part I.
2. We seek clarification for what is considered a relevant project for a design engineering firm.
The presolicitation states; A relevant project is:
1. Approximately $20 million or more in construction value; AND
2. Design and engineering services completed within the past 10 years
If an engineering firm provided Post Construction Award Services during the construction of the project, will this meet the requirement for “engineering services” identified in item (2) above?
PCAS services were provided after design was complete but provided within the last 10 years.
ANSWER: Completed in the past ten (10) years refers to final construction completion.
Relevant project with final design completion in the past ten (10) years and under construction (construction ongoing; not final construction completion) can be submitted; however, may be considered less favorably.
N62742-19-R-0003