USS SHOUP (DDG-86) 6J2 INSULATION AND LAGGING REPLACEMENT, YOKOSUKA Japan
Solicitation number
N6264926RA028
Issued by

About this file

This is a Standard Form 30 (SF-30) amendment to solicitation N6264926RA028 for the United States Navy, issued on 30 January 2026 with an effective date of 30 January 2026. The amendment is not extended and contractors must acknowledge receipt prior to the specified deadline or risk offer rejection.

The amendment responds to two contractor questions regarding solicitation N6264926RA028, dated 27 January 2026, for insulation and lagging replacement work on USS SHOUP (DDG-86). The first question requested a location list for work scope, to which the government responded that various locations throughout the ship will be determined through a walkthrough with the contractor point of contact once the contract is awarded, with quantities measured in square feet or linear feet; no additional work will be required once contract quantities are reached. The second question requested material substitution to GFM, which the government denied, specifying that all material will be CFM with no GFM provided. The amendment clarifies that contractors are responsible for any required staging or scaffolding, SRF will remove interferences if necessary, and any hull or piping damage discovered after lagging or insulation removal will be evaluated by SRF. The amendment modifies Section J to reference Attachment (I) Work Specification WI 508-11-001 INSULATION AND LAGGING REPLACEMENT with a lagging location list, Attachment (II) Proposal Breakdown Form, and Attachment (III) Request for Information Sheet.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): Name of Vessel: USS SHOUP (DDG-86) The purpose of this solicitation amendment 0001 is to respond to the question.

DATE OF REQUEST: 27 January 2026

CONTRACTOR QUESTION(s):

1. There is no location indicated in specification, is it possible to provide us with Location List?

2. Is it possible to change material to GFM?

GOVERNMENT RESPONSE(s):

1. Various locations throughout the ship. SRF POC will walkthrough with the contractor POC once contract is awarded. Contractor and SRF POC will agree on the quantity (sq ft or linear ft). When/if quantity on the contract is reached, no additional amount will be required.

2. All material will be CFM. There will be no GFM provided.

Note: Any staging/scaffolding required is the responsibility of the contractor. SRF will remove any interferences, if required. If hull or piping is found to be damaged after lagging or insulation removal, it will be evaluated by SRF.

Section J - List of Attachments

Miscellaneous text in this section has been modified to:

Attachment (I) Work Specification(s)

WI 508-11-001 INSULATION AND LAGGING REPLACEMENT; ACCOMPLISH

- LAGGING LOCATION LIST

Attachment (II) Proposal Breakdown Form ( )Contractor Response Required

Attachment (III) Request for Information Sheet

N6264926RA0280001

IDCode: J
Page: 1
Pages: 2
AmendNo: 0001
EffDate: 30 Jan 2026
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N62649
AdmCode:
IssuedBy: NAVSUP FLT LOG CTR YOKOSUKA

PSC 473 BOX 11, FPO AP 96349-1500

FPO, AP 96349-1500

UNITED STATES

KAZUYA IWANAGA, Email: kazuya.iwanaga.ln@us.navy.mil Telephone: 046-816-9974 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N6264926RA028
SolDate: 27 Jan 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: Mr. Peter Jommel S. Arrieta
ContDate:
CODate: 30 Jan 2026

File details come from the government source that posted it. Updated .