This document is a Standard Form 30 Amendment of Solicitation/Modification of Contract for a corrosion abatement maintenance service at the Center for Security Forces (CENSECFOR) Learning Site in Yokosuka, Japan. The contract involves maintenance services for a Tactical Training Simulator (TTS), which consists of 16 conex containers, requiring exterior corrosion removal, treatment, and repainting. The Period of Performance is from 29 September 2025 to 31 March 2026, with work to be completed by the end date to avoid interfering with student training.
Key details include requirements to inspect and remove exterior rust, replace deteriorated areas, apply anti-corrosion treatment, and repaint to match the existing structure. The work covers exterior walls, railings, handrails, ladder wells, roof, and platforms, including spray poly foam insulation areas. Contractors must comply with specific environmental and safety standards, conduct proper waste disposal, and handle hazardous materials according to Japanese and U.S. regulations. The solicitation is being amended to extend the response date to 09 September 2025 and provide clarifications to potential quoters through a series of questions and answers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6264925QB096-0001.pdf | ||
| N6264925QB096.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1301238099-0001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide the answ er to the technical questions from potential quoters and change the Section 5 in Performance Work Statement (PWS).
According to the changes above, the solicitation close date and time w ill be extended.
The other terms and conditions remain unchanged.
Please see the continuation sheet.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 11
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Sep-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6264925QB096
X 9B. DATED (SEE ITEM 11)
18-Aug-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Sep-2025
CODE
NAVSUP FLC YOKOSUKA
CONTRACTING DEPARTMENT (CODE 200)
BLDG F-157
1 BAN-CHI TOMARI-CHO
YOKOSUKA 238-0001
N62649 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6264925QB096
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 05-Sep-2025 02:00 PM to 09-Sep-2025 02:00 PM.
The following have been added by full text:
QUESTIONS AND ANSWERS
1) On PWS Page 4, the Period of Performance is listed as 29 September 2025 to 31 March 2026; however, the next paragraph (Description of Requirement) states that "work shall be completed within two-months of receipt of contract." Which is correct?
FLCY answer: PoP 29 September 2025 to 31 March 2026 is correct, as stated in PWS Paragraph 3. PWS Section 5 will be revised as follows:
From: within two-months of receipt of contract To: by the end date of the Period of Performance
2) It is my understanding that only exterior areas of the TTS require corrosion abatement and recoating. No interior walls, stairs, etc. will be worked on this contract, is that correct?
CENCECFOR answer: That is correct, we are not requesting any interior work be conducted during this contracted work.
3) Is there any information available on the current coating system applied to the TTS?
CENCECFOR answer: We do not have specific information on the current coating. We have documentation on the structure and supports, and environmental engineers visited the Site to confirm no asbestos in the coating, but specificity beyond that is not information we have readily available.
4) Can the Government provide detailed pictures to show the condition of the TTS so that vendors can accurately estimate this project?
FLCY answer: Yes, we can provide the pictures provided from Center for Security Forces (CENSECFOR), Yokosuka. These pictures are For Official Use Only (FOUO). Therefore only SAM registered company who is duly authorized to operate and do business in JAPAN can request the pictures to Contract Specialist, Mr. Rokutan at Masanori.Rokutan2.LN@us.navy.mil.
5) On Page 6, paragraph 10 (Services Performance Time), the PWS states that work performance is dependent on the CENSECFOR class schedule. Are we to understand that training will be going on throughout this project and there may be times that the facility is not available to the Contractor? Can the Government provide a schedule of classes for planning purposes?
CENCECFOR answer: Our class schedule is as follows: 8-19 September, 27
October-7 November, 1-12 December, 5-16 January, 2-13 February, 23 February-6 March, 16-27 March, 6-17 April, 4-15 May, 1-12 June. Our training requires the use of the TTS facility and the surrounding outdoor areas. In previous contracted work on the facility, work is conducted during off-weeks, and fully removed when we have class running. We have ample space to provide a laydown and storage area, as required.
7) Does this effort require a CAC?
FLCY answer: Not required Common Access Card (CAC). Generally, contractor's gate pass can be issued for the contractual Period of Performance.
8) Is the use of local nationals allowed?
FLCY answer: Usage of subcontractor or local nationals (DoD allied countries) are allowed.
9) Can the Government confirm a FFP quote is all that is needed?
FLCY answer: As stated page 26 of 33 in N6264925QB096, Quote with the signed SF1449 and a cost breakdown of the quote are required. Also, as stated page 10 of 33, Quoters may be required to submit additional documentation demonstrating their ability to perform in Japan prior to award. Quoters also are required to complete SAM registration or annual-renewal before submitting quotes.
10) Has there been any questions/answers posted on AsiaNECO?
FLCY answer: Questions and Answers will be posted on AsiaNECO and SAM.gov.
11) The work period of performance is listed as 60 days, but the contract period of performance is through March 2026. Can the Government please clarify the dates?
FLCY answer: Please see the Answer to the Question 1.
12) Given lead times for doors, rails and ladders-will the Government consider extending the work period beyond 60 days.
CENCECFOR answer: POP can be modified to account for delivery lead times.
13) Our experience performing this exact service on this exact trainer allowed for a 90 day ramp up period for inspection, planning and fabrication, followed by a 90 day work period. Will the Government considering this timeframe? (i.e. water tight doors take 12 weeks from order to delivery CONUS).
CENCECFOR answer: POP can be modified to account for delivery lead times.
14) Will the Government consider extending the due date until after all questions are answered?
FLCY answer: TBD. Contracting Officer may consider to extend the quote submission due date, according to the all reasonable decisions together.
15) Is there training planned during the period of performance? When is the next training date?
CENCECFOR answer: See the Answer to the Question 5.
The following have been modified:
PWS
(updated 3 SEP 2025)
PERFORMANCE WORK STATEMENT
for CENSECFOR LS Yokosuka’s Tactical Training Simulator (TTS)
Maintenance (Corrosion Abatement) Services
1. INTRODUCTION
1.1 Center for Security Forces (CENSECFOR) Learning Site Yokosuka is a tenant command on Commander, Fleet Activities Yokosuka (CFAY). Sailors receive necessary training on coordinating team responses in an asymmetrical environment, to include, tactical team movements, offensive/defensive perimeters in lighted, low-light and no light situations, tactical communications, personnel restraint equipment, employment of force up to and including deadly force. To make training as realistic as possible, marking cartridges are used for active shooter scenarios. It is essential to have a safe environment in which to conduct live-fire scenarios, and without a well-maintained Tactical training Simulator (TTS) CENSECFOR, Learning Site Yokosuka, is not able to carry out their mission.
2. APPLICABLE DOCUMENTS
The following documents are hereby incorporated by reference and become a part of this PWS to the extent specified herein. In the event of a conflict between documents referenced herein and the contents of this PWS, the contents of this PWS take precedence. Nothing in this PWS, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained. Contractors shall use the most recent and up to date versions of these training documents, which will be provided by the Government.
1. CENSCFORINST 3550.1, Range Operation and Maintenance
2. Japanese Law Relative to Disposal and Cleaning of waste (Haikibutu no Shori oyobi Seisou ni Kansuru Houritsu.)
3. JIS (Japan Industrial Standard)
4. Technical Rules of Class NK (Nippon Kaiji Kyokai)
5. EM385-1-1, Safety and Health Requirements Manual
(http://www.usace.army.mil/CESO/Pages/Home.aspX)
6. JEGS, Japan Environmental Governing Standards (https://www.usfj.mil/Resources/JEGS/)
7. CFAYINST 5090.19A, CFAY Instruction 5090.19A, Environmental Policy
ENCLOSURE:
1. Environmental Brief Checklist (prior to commencement of work)
2. Environmental Protection Plan (prior to commencement of work)
3. HAZMAT Inventory Log (prior to commencement of work, and close-out)
4. CFAY HAZARDOUS WASTE DISPOSAL REQUEST FORM (Hazardous waste turn-in sheet)
(when the contractor turn-in HW to Bldg.1822,HWSA)
5. Contractor Turn in of Recyclable Materials (when the contractor turn-in recyclable material to Blfg.4856, CFAY QRP)
6. CFAY Solid Waste Tonnage Report (Close out)
3. PERIOD OF PERFORMANCE
29 September 2025 – 31 March 2026
4. PLACE OF PERFORMANCE
Center for Security Forces Learning Site Yokosuka, Bldg. 4818 (TTS), Commander, Fleet Activities (CFA) Yokosuka, Japan.
5. DESCRIPTION OF REQUIREMENT
The required action is to deliver maintenance services (corrosion control) on a Tactical Training Simulator at Commander Fleet Activities (CFA), Yokosuka, Japan. The requirement is to identify and then abate all external corrosion that currently exists on the TTS training facility.
This work shall be done in accordance with CENSCFORINST 3550.1, Range Operation and Maintenance.
The work shall be completed by the end date of the Period of Performance in order to not interfere with student training. The requirement includes the one-time corrosion control maintenance for the TTS which is considered Training Unique Equipment (TUE) and categorized as Class Three Personal Property.
The (1) structure, manufactured by Iconix International is , fabricated out of 16 conex containers bolted together. It is approximately 50 feet in length, 35 feet in height, and 20.5 feet in width.
Structure consists of 12 distinct rooms, three passageways, three exterior stairways, and three interior stairways. Flooring is hardwood, Passageway walls and ceilings are joiner work (typical ship construction), walls in individual rooms are painted conex container walls.
The contractor shall inspect and remove all exterior rust, replace if necessary areas deteriorated beyond repair, treat with anti-corrosion, and paint to color match existing structure in place.
This includes exterior walls, railings, handrails, ladder wells, roof, and platforms. The exterior walls are covered with a spray poly foam insulation. If corrosion is evident on these walls, the foam insulation will be removed, the wall will be repaired and painted, and new foam insulation reapplied and color match painted with existing structure. Prior to removing any rust or foam installation, the vendor must conduct sampling and analysis by a qualified inspector to ensure no exposure to lead or asbestos exists. All resulting samples must be properly disposed. Quick acting water-tight doors will also require repair, or replacement with a similar replica door.
(Note that a replacement water-tight door can be used. It does not have to conform to Navy Standards.) The following steps shall be accomplished:
a. Provide and install any required containment structure/tent in support of the rust removal process.
b. Remove spray poly foam insulation on exterior walls as needed to access and address corrosion. (Look for areas that have separated from the wall and have allowed water to penetrate.)
c. Remove all exterior corrosion, and loose paint areas, down to base metal. For all rust removal operations, ensure that all applicable containment and environmental requirements are adhered to.
d. At locations where the rust has caused significant damage, the TTS component (wall section, door, frame, railing, steps/ladders, etc.) shall be replaced or structurally repaired (typically welded) prior to re-painting.
e. Replace the removed TTS component (wall section, door, frame, railing, steps/ladders, etc.).
f. Seal, prime, and repaint all work areas and new components. Apply color matching rust resistant paint upon removal/replacement of all areas requiring corrosion removal and/or replacement.
g. Reapply spray poly foam insulation on walls where it was removed. Apply primer and color matching, corrosion resistant Paint.
Clean entire area of any work related materials and debris that may cause safety hazard to training of students.
6. MAINTENANCE SERVICES
The services shall be performed on site during operational hours mutually agreed upon and scheduled between the Contractor and the requiring activity. Personnel qualified to conduct corrosion inspection and mitigation of Force Protection Training Ship Simulator exterior and interior stairways, railings, and supporting structural components are authorized to perform corrosion maintenance on the Tactical Training Simulator. Such services shall include technical inspection, cleaning and replacement parts (where needed) to keep the equipment in serviceable condition for the facilitation of safe student training.
7. LIST OF MAINTENANCE FOR TTS
The following list is the maintenance for Tactical Training Simulators. Walls – Free of corrosion and re-painted to color match with non-corrosive paint
a. Handrails and Railings – Securely mounted to structure, free of corrosion and re-painted to color match with non-corrosive paint
b. Ladder Wells and Stairs – Securely mounted to structure, treads securely in place, free of corrosion and painted or treated with non-corrosive paint or traction adhesive material
c. Quick Acting Watertight Doors & Frames – Securely mounted to structure, repair or replace with similar replicas, free of corrosion and re-painted to color match with non-corrosive paint
d. Platforms – Free of corrosion, remove and treat where corrosion evident and re-painted to color match with non-corrosive paint
e. Roof Grating – Ensure roof is water resistant and repels moisture from weather elements. Where corrosion is evident, repair/replace affected area and re-paint and/or re-treat with protective non-corrosive covering to ensure water resistant capability
8. INSPECTION
Inspection of services performed hereunder shall be made by the CENSECFOR Learning Site Yokosuka Site Director or higher requiring activity. The Contractor shall report to the Site Director when starting and upon completion of each work day. Upon completion of the work, the Contractor shall provide a copy of the work performed, signed by the contract lead, certifying that the work has been performed and that the equipment is back to serviceable condition.
9. WORK PERFORMED
All CENSECFOR TTS work performed must contain the following minimal information:
a. Contract Number
b. Replacement Part Numbers and Description
c. Details of Maintenance Performed
d. Service performance date and time
e. Name of Technician
10. SERVICES PERFORMANCE TIME
The scheduled maintenance services shall be performed from 0800 to 1600, Monday through Friday. (Dependent on CENSECFOR class schedule and availability.) Any other hours as mutually agreed upon between the Contractor and the requiring activity. For phone call support during working operational hours (0800-1600, Monday through Friday):
CENSECFOR LS Yokosuka Main Office: DSN: (315)243-6172 or (315)243-2530; CONUS:
(757)242-1706.
11. CONTROL AND DISPOSAL OF WASTE
The Contractor will dispose of all wastes generated from the rust removal, painting, and foam application process selected by the contractor base on analysis results and waste characterizations in accordance with the following standards and Japanese law.
a. Japan Environmental Governing Standards (JEGS).
b. CFAY Hazardous Waste Management Plan, when applicable.
c. Japanese Law Relative to Disposal and Cleaning of waste (Haikibutu no Shori oyobi
Seisou ni Kansuru Houritsu.)
No waste shall be brought onto the Government property from off-base nor shall no waste be abandoned on any Government or off-base property. Do not discharge any waste to a sanitary sewer, storm drain, or surface waters or conduct waste treatment or disposal on the Government property without written approval from the CFAY PWD Environmental via the Contracting Officer.
The Contractor will identify, characterize, and determine any recyclable items and wastes, and then handle, collect, containerize/pack, label, accumulate/store, transport, and disposed of them properly. Wastes herein include all wastes such as solid waste to include recyclable item, hazardous waste, industrial waste, and contractor generated hazardous waste. In order to characterize the waste, sampling and analysis must be performed in accordance with applicable regulations and standards. Once waste is characterized and determined, solid waste and/or industrial waste and contractor generated hazardous waste must be disposed of directly at off-base by the contractor while hazardous waste and recyclable item must be dispositioned through the government unless an approval for direct off-base disposition is obtained. Contact CFAY PWD Environmental and CFAY Qualified Recycling Program Office for hazardous waste disposal and recycling opportunities, respectively, for further guidance.
If the work requires the temporary storage/collection of hazardous wastes on site overnight, a Contractor Hazardous Waste Accumulation Point (HWAP) shall be established at or near generating point and operated to comply with the applicable regulations and requirements. When hazardous waste will be removed for disposal from the job site properly daily, the Contractor HWAP is not required. For further guidance, contact the CFAY PWD Environmental.
Any non-hazardous solid waste/debris other than recyclable scrap metals generated from this operation will be properly segregated and transported /disposed of at permitted offbase solid industrial waste disposal/landfill facility by a government approved solid /industrial waste transportation/disposal contractor in accordance with local and prefectural solid industrial waste transportation and disposal laws and regulations. A legible copy of Waste Disposal Manifest (a copy of receipt "E") with the completion date of landfill, and CFAY Solid Waste Tonnage Report with accurate weight unit (Kg) and monetary unit (Both Dollar and Yen with the timely exchange rate) MUST BE submitted to the Solid Waste Manager, CFAY PWD Environmental.
The CFAY Solid Waste Tonnage Report must include the totals of, 1) the accurate weight unit (Kg), 2) monetary unit** (Both Dollar and Yen with the timely exchange rate).
**If the material disposed or recycled off-base was sold for profit, you must indicate the amount the material was sold for, using < > symbols around the amount. (i.e. <$150> or <¥15,000>).
All recyclable scrap metals must remain the property of the Government unless indicated, and deliver to the recycling Storage Facility (Bldg. 4856 in Yokosuka). Before delivering the scrap metal, submit the attached form “CONTRACTOR TURN-IN OF RIPPED OUT MATERIAL” filled out blanks and contact PRY35 CFAY Solid Waste/QRP department. Size a piece of the scrap metal not larger than 2.5 meter wide, 6.0 meter length, and 2.5 meter height; and not exceed 4,000 kg. Off-base recycling requires justification to be submitted and be approved by CFAY QRP before recycling off-base.
12. GENERAL REQUIREMENTS
Unless otherwise specified, all work shall conform to the standards for overhauling work of this contract described below. However, if a conflict between below publication and the specification of this contract is found, the specification of this contract precedes.
a. JIS (Japan Industrial Standard)
b. Technical Rules of Class NK (Nippon Kaiji Kyokai)
c. The Shipbuilding Association of Japan (Nihon Zosen Kogyo-kai)
d. Contractor furnished material and government furnished material. The Contractor shall provide all facilities, equipment, materials, and services to perform the requirements of this contract. The government will not provide the facility, equipment, material, and services under this contract.
13. ACTIVITY REGULATIONS
The Contractor will not schedule maintenance during holidays. Contractor shall schedule all required maintenance during the government’s normal working hours from 0800 to 1600 Monday through Friday except for the following Federal Holidays:
a. New Year’s Day (1 January, unless this day falls on a weekend)
b. Martin Luther King, Jr. Day (third Monday in January)
c. President’s Day (third Monday in February)
d. Memorial Day (last Monday in May)
e. Juneteenth (June 17th, unless this day fall on a weekend)
f. Independence Day (4 July, unless this day falls on a weekend)
g. Labor Day (second Monday in September)
h. Columbus Day (second Monday in October)
i. Veteran’s Day (11 November, unless this day falls on a weekend)
j. Thanksgiving Day (fourth Thursday in November)
k. Christmas Day (25 December, unless this day falls on a weekend)
14. SAFETY AND ENVIRONMENTAL REQUIREMENTS
All work shall be conducted in a safe manner and shall comply with the current safety and environmental requirements as indicated in EM385-1-1, Safety and Health Requirements Manual issued by the U.S. Army Corps of Engineers and JEGS, Japan Environmental Governing Standards issued by Headquarters, U.S. Forces Japan. In addition, CFAYINST 5090.19A, Environmental Policy, must be met to perform work activities on CFAY.
Environmental Protection Performance Requirements:
The Contractor must submit the proposed Environmental Protection Plan (EPP) within 14 days after award of this contract and must not perform any work until CFAY PWD Environmental Division approves the EPP. Anytime the Contractor’s process and/or procedures require a change(s) to perform tasked operations and services, the Contractor shall immediately inform the COR and the KO and submit an updated/revised EPP to CFAY PWD Environmental via the COR and KO for review and approval in a timely manner but no later than 14 days from the notification.
Hazardous Material Requirements:
a) No HAZMAT shall be abandoned on government property nor brought onto the government property that are not directly related to requirements for the performance of this contract. All HAZMATs must be brought in and out from and to off base every day, and overnight HAZMAT storage on site is not authorized unless an approval is granted. For further guidance, contact the CFAY PWD Environmental.
b) If any HAZMATs (e.g., paint, thinner, adhesives, greases) are brought or used on work site, submit a HAZMAT Inventory Log along with the latest corresponding Safety Data Sheets (SDSs) including required information, such as material name, manufacturer, physical state, maximum storage quantity, to CFAY PWD Environmental and obtain an approval for use prior to the commencement of work.
The (copies of) SDSs prepared by manufacturers must be written in English and Japanese, if Japanese is the predominant language in the work area, and maintained on the work site at all times.
c) HAZMATs shall be handled and stored in accordance with SDS and other regulations and requirements. For example, flammable HAZMATs and corrosive HAZMATs must be stored separately and acids must be stored away from alkali/bases. Containers of HAZMAT must not be leaking and must have Globally Harmonized System (GHS) of Classification and Labelling of Chemicals labels or their equivalent.
d) HAZMAT dispensing area must be located away from catch basins and floor/storm drains, properly managed, and maintained. Drip pans and/or absorbent materials must be placed under HAZMAT containers to catch drips and/or leaks.
15. CONTRACTOR’S RESPONSIBILITY
These above listed requirements and contracted work responsibilities shall be considered a part of this Performance Work Statement. Consideration shall be given to these requirements and responsibilities and shall be reflected in the Contractor’s bid/offer. The Contractor shall comply with all National, prefecture and local environmental regulations. The Contractor shall assume these responsibilities and perform as required. Contractors unless otherwise specified, shall conform to the standards for overhauling work of this contract described below. However, if a conflict between below publication and this work specification of this contract is found, the work specification of this contract precedes.
a. JIS (Japan Industrial Standard)
b. Technical Rules of Class NK (Nippon Kaiji Kyokai)
c. The Contractor’s appearance shall be neat, well-groomed, and professional at all times.
d. The Contractor shall conduct himself/herself in an efficient and professional manner consistent with CFAY Port Operations business standards. The Contractor shall interact with CENSECFOR in a courteous, polite, and professional manner.
e. Alcohol/Drug use in the workplace will not be tolerated. Any Contractor/sub-contractor found to be under the influence of, consuming, or using alcohol or drugs while on duty will be subject to administrative action from the Contracting Officer, which may include contract termination.
f. The Contractor shall provide each employee with identification (ID) badge made of nonmetallic material that is easily readable, and includes employee’s name, Contractor’s name, and recent color photograph of the employee.
g. Display of ID badges. Contractor personnel shall wear the ID badge at all times when performing work under this contract at a government site, including while attending government meetings and conferences that may take place outside the government facility. Unless otherwise specified in the contract, each contractor employee shall wear the ID badge in a conspicuous place on the front of exterior clothing and above the waist except when safety or health reasons prohibit such placement.
h. The Contractor shall remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of National Security.
i. Work Permits. All contractors and sub-contractors who do not reside within Japan shall have a valid work permit/working visa prior to reporting to CFAY. All contractors and sub-contractors shall be registered with the U.S. or Japan.