This document contains Questions and Answers from an Industry Day event for the AH-1Z & UH-1Y Aircraft Maintenance and Repair contract solicitation. The key details are:

The solicitation will be for Scheduled and Unscheduled Maintenance, Repair and Overhaul (MRO) services for U.S. Marine Corps AH-1Z & UH-1Y aircraft forward deployed in the U.S. Indo-Pacific Command (USINDOPACOM) Area of Responsibility. The contract solicitation is intended to be full and open competition, and the Government does not anticipate awarding it as an 8(a) direct award to a Small Business. The Government estimates 2-3 Planned Maintenance Inductions per contract year, and confirms that Flight Clearance Flight support will not be required from the contractor. The Government plans to post the solicitation on SAM.gov in mid to late 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

H-1 Industry Day 07 November 2024 Questions and USG Responses

Releasable to SAM.Gov

Question 1: Is the Relocation CLIN going to be FFP?

USG Answer: The Relocation CLIN will be FFP, however any relocation determination will be negotiated prior to issuance of a task order. The Ordering Officer may request the Contractor provide Data Other than Certified Cost or Pricing Data to support a determination of a fair and reasonable price for the required work.

Question 2: Does the USG anticipate the contract solicitation to be full and open competition?

USG Answer: Currently, the AH-1Z & UH-1Y Aircraft Maintenance and Repair contract solicitation is intended to be full and open competition.

Question 3: What is the expected timeline for the upcoming Solicitation?

USG Answer: Currently, the USG intends to have the solicitation posted on SAM.GOV in mid to late 2025.

Question 4: Does the USG have any interest in awarding this contract as a 8(a) direct award to a Small Business?

USG Answer: Currently, the USG is not anticipating awarding the H-1 follow-on contract as a 8(a) direct award to a Small Business.

Question 5: What is the estimated number of PMI inductions a contract year?

USG Answer: Currently, we estimate two (2) to three (3) PMI inductions each contract year.

Question 6: Will FCF support be included in the scope of the contract?

USG Answer: No. FCF support will be performed by the reporting custodians with no support required from the contractor, and is not a requirement of this contract.