Solicitation Amendment N62645-18-R-0008-0002

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N6264518R0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS -0002

Notes (Changes not addressed in questions):

1. In the Attachment V table, 2.1.17 was revised from “Hearing Conservation Research Associate II” to “Hearing Conservation Research Assistant I”, so that the table and 2.1.17 matched. The “II” was changed to “I” and the word “associate” was changed to “assistant”.

2. Attachment V: “4.1.21 Biomedical Engineer”. The Biomedical Engineer was erroneously listed as 4.1.21. The numbering for the Biomedical Engineer has been revised to 2.1.21.

3. Attachment V: 2.1.29 has been revised to state that “(Historically this has been a Subcontractor)”, so that the 2.1.29 Position/Objective Description matched the table.

4. Attachment V:The following sections have changed: 2.1.1, 2.1.3, 2.1.4, 2.1.7, 2.1.9, 2.1.23, 2.1.24, 2.1.25, 2.1.27, 2.1.33, 2.1.34, and 2.1.35.

Question 1: Two RFP files were issued; one on January 5 and one on January 8, 2018. Please confirm the latter file is the correct one to use.

A: Both files and attachments are identical. The posting on January 8th was of the identical RFP document and DD254 that was posted on January 5th. The only difference was the addition of attachment V (The Initial Task Order PWS), that was erroneously left out when the RFP package was posted on January 5th.

Question 2: Will the government provide a one-week extension, to February 12, 2018, so that non-incumbent bidders may have time to adjust proposals based on answers to questions?

A: The proposal submission time has been revised. Please see section L.

Question 3: Section L.8.2.1, page 77, states: “Type for graphics, tables, and reproductions shall be no smaller than a font size of 10 with a minimum of 1” margins.” Please confirm that we should assume a minimum of one-inch margins for all of Volume I, not just the graphics.

A. The replicated sentence (“Type for graphics, tables, and reproductions shall be no smaller than a font size of 10 with a minimum of 1” margins.”) is in reference to graphics, tables, and reproductions only.

Question 4: Section L.8.2.1, page 77, states: “Type shall be no smaller than a font size of eleven (11) and shall have 1.0 line spacing.” Is the line spacing meant to be single-spaced regardless of font chosen?

A: Yes, line spacing is required to be single spaced.

Question 5: Section M.3.4, page 86, states: “The following shall evidence small business participation: a. The extent to which such firms, as defined in FAR Part 19, are specifically identified in proposals; b. The extent of commitment to use such firms (enforceable commitments will be weighted more heavily than non-enforceable ones).” In order for bidders to receive an Acceptable rating in this proposal, is there a requirement that subcontractors from one or more of the six procurement goals (i.e., HUBZone, SDB, etc.) be proposed in the initial task order approach?

A: The Government is evaluating the offeror’s Small Business Participation Plan and Subcontracting Plan for the offerors proposed small business participation over the entire period of performance of the base IDIQ contract and not simply for the initial task order.

The Government does not specify what subcontractors an offeror has to propose. To receive an “Acceptable” rating under this evaluation factor the offerors proposal must meet the following:”Proposal indicates an adequate approach and understanding of small business objectives.”

Question 6: Section L.9.3, page 79, states: “Additionally, the offeror shall demonstrate a thorough understanding of the technical requirements and provide a schedule for task completion.” Since non-incumbents are not familiar with the status of specific tasks, planned deliverables, and work products, etc. under the current contract, could you please confirm that the requirement for an initial 12-month task order schedule is for bidders to address the staffing and hours only, such as is shown in the LOE chart in TO PWS 3.

On a related note, may bidders exempt the use of a similar chart from page count?

A: The requirement to “provide a schedule for task completion”, has been removed from section L. Please see the revised section L.

Question 7: Attachment V, Task Order PWS, Section 2.1.14, page 10, states: Is 2.1.14 Hearing Conservation Research Assistant II the same position as Hearing Conservation Research Associate II that is listed in the TO PWS 3. table (p. 26)? The information in 2.1.14 states that this position is historically a consultant. Should bidders maintain this consulting arrangement? Also, has the Hearing Conservation Program Research Assistant I been a consultant?

A: No. The Hearing Conservation Research Associate II (re-titled as a Hearing Conservation Research Assistant I-as noted above)) correlates to 2.1.17.

The 2.1.14 Hearing Conservation Research Assistant I was erroneously omitted from the Attachment V table. Please see the revised Attachment V for the corrected table.

The Government is unsure where the offeror is seeing that 2.1.14 is historically a consultant, as this is not listed in 2.1.14.

The Government clarified in the line above, that 2.1.14 has not historically been a consultant. For general information purposes, the Government does not specify whether an offeror should utilize consultants or subcontractors.

The Hearing Conservation Program Research Assistant I (2.1.16) has not historically been a consultant.

Question 8: Attachment V, Task Order PWS, page 25: The table states that the Mathematical and Fleet Liaison Support is fulfilled by a subcontractor but does not provide LCAT, educational requirements, etc. data. Please provide that information so that non-incumbent bidders may propose personnel with the right qualifications. Personnel choices also affect cost.

A: The table in Attachment V has been revised to include education and experience requirements.

Question 9: Attachment V, Task Order PWS, Section 2.1.18, page 12: Effects of Wakefulness on Operationally Relevant Indicators has been a subcontractor. The table at TO PWS 3 does not provide any data (LCAT, educational requirements, etc.); please provide.

A: The table in Attachment V has been revised to include education and experience requirements.

Question 10: Attachment V, Task Order PWS, page 25: The table lists Human Performance and Decision- Making Support. Is 2.1.24 Human Factors Research Scientist Support on p. 16 the position/objective description for this task and position (including the RFP PWS task reference)?

A: No. The task title of “Human Performance and Decision- Making Support” has been removed. The title has been changed to “Psychology Research Post Doc Support” because this position supports 2.1.7. There are now two positions in the Attachment V table that support 2.1.7 (Psychology Research Post Doc Support).

The table in Attachment V has been revised to add the corresponding position/objective description numbers.

Question 11: Attachment V, Task Order PWS, page 25: The table lists Psychometrician Support. Where is the corresponding position/objective description for this task and position (including the RFP PWS task reference)?

A: Psychometrician Support corresponds with 2.1.6.The table in Attachment V has been revised to add the corresponding position/objective description numbers.

Question 12: Attachment V, Task Order PWS, page 25: The table states that Industrial Hygiene SME Support for SAHAP is filled by a consultant. Is there a more specific labor category that is relevant (affects qualifications, cost)? Also, should bidders maintain this position as a consultant?

A: The table in Attachment V has been revised to include education and experience requirements. In general, the Government does not specify whether an offeror should utilize consultants or subcontractors.

Question 13: Attachment V, Task Order PWS, page 26: The table lists sub-contract for the position of the Laboratory Technical Support - Principal Scientist task. Is principal scientist the correct position (LCAT)? Also, which RFP PWS task(s) does this position support? ‘ A: The table in Attachment V has corrected the title from “Laboratory Technical Support - Principal Scientist task” to “Support on Conclusion of Navy OAE Development-Principal Scientist”. The table has been revised to add the corresponding position/objective description numbers.

Question 14: Attachment V, Task Order PWS, page 26: The table lists sub-contract for the position of the Laboratory Technical Support - Associate Scientist task. Is associate scientist the correct position (LCAT)? Also, which RFP PWS task(s) does this position support?

A: The table in Attachment V has corrected the tile from “Laboratory Technical Support - Assistant Scientist task” to “Support on Conclusion of Navy OAE Development-Assistant Scientist”. The table has been revised to add the corresponding position/objective description numbers.

Question 15: Attachment V, Task Order PWS, page 26: The table states that the Virtual Tactical Simulator is fulfilled by a subcontractor but does not provide data (LCAT, educational requirements, etc.). Please provide.

A: This task is deliverable oriented and not support services oriented. Therefore education requirements etc are not provided.

Question 16: Attachment V, Task Order PWS, page 26: The table states that the SAHAP Badge Analysis is fulfilled by a subcontractor but does not provide data (LCAT, educational requirements, etc.). Please provide.

A: This task is deliverable oriented and not support services oriented. Therefore education requirements etc are not provided.

Question 17: Section L.9.5.1 Section 1 - Cost Breakdown (page 81): "If subcontractors are unwilling to submit their direct labor rates (only) to the prime contractor, they shall submit those rates directly to the Government utilizing the same proposal submission instructions and due date and time located in this section.” Question: If our subcontractors will be under a T&M subcontract, is a direct labor rate sealed package from them still required?

A: Offerors shall use the subcontracting costs provided in Attachment V. This figure is the Governments estimate of the value of supporting all tasks that have traditionally been provided by subcontractors. If the offeror proposes to use a subcontractor to provide support for a task that is not identified in Attachment V. as traditionally been supported by a subcontractor, then they are required to provide direct labor rates.

Question 18: Section C Performance Work Statement (PWS) – Section 4 Technical Requirements/Initial Task Order (ITO) Performance Work Statement – Section 2 Position/Objective Description. As the purpose of the Initial Task Order (ITO) PWS is to supplement the PWS contained in the base contract and further define what is required for each of the positions, will the Government increase the page count limit for the Technical Approach to accommodate the supplement ITO PWS requirements?

A: The Government will increase the page count for Volume I: Subpart III, Technical Approach for Initial Task Order from 10 to 15 pages. Please see the revised table in Section L.

Question 19: L.9.3 Volume I, Subpart III - Resumes (page 81): To ensure Labor Category Requirements are covered as thoroughly as possible in each resume per the ITO PWS and to add a list of Select Publications and Presentations for Proposed Candidates, it is requested that resumes be increased to a 3-page limit.

A: The resume page limit will remain unchanged.

Question 20: Attachment V, Initial Task Order - Section 3 -Level of Effort, Education, and Experience Requirements (page 25) Please confirm that the Task: Psychology Research Post Doc Support should be a Research Scientist II (Psych/Phys/Aud); the education and experience requirements do not reflect a Research Scientist II (Psych/Phys/Aud).

A: The education and experience requirements are correct as provided.

Question 21: Attachment V, Initial Task Order - Section 3 -Level of Effort, Education, and Experience Requirements (page 25) Please confirm that the Task: Research Scientist, Position: Research Scientist I (Psych/Phys/Aud) requires 4+ years of experience; the experience requirement seems to reflect a Research Scientist II.

A: The education and experience requirements are correct as provided.

Question 22: Please confirm that offerors in possession of a TOP SECRET facility clearance are eligible to bid as a prime contractor in accordance with RFP section L.9.1.5 SECTION V: VERIFICATION OF SECURITY CLEARANCE LEVEL of the RFP which states: “The Offeror shall submit documentation verifying a TOP SECRET facility clearance.

A. Yes, offerors in possession of a Top Secret Security Clearance are eligible.

The following have been deleted:

QUESTIONS AND ANSWERS

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been modified:

INSTRUCTIONS TO OFFERORS

L.1 CONTRACT SPECIALIST

The Contract Specialist (CS) is the point of contact for this acquisition. Any questions or concerns regarding this acquisition shall be submitted electronically via e-mail to jennifer.m.reed20.civ@mail.mil. Please place the RFP number (N62645-18-R-0008) in the subject line.

L.1.1 PERIOD FOR ACCEPTANCE OF OFFERS

The period for acceptance of offers is one hundred eighty (180) days after the closing date of the solicitation.

L.2 PRE CONTRACT COSTS

The Contractor will not be reimbursed for any costs incurred prior to the effective date of the contract.

L.3 CONTRACT AWARD

L.3.1 TYPE OF SOLICITATION

This Solicitation is being issued as a full and open competition under which all contractors eligible for Federal contracts are encouraged to participate.

L.3.2 ONE PROPOSAL

The Government will evaluate only one proposal from each prime offeror.

L.3.3 TYPE OF CONTRACT (FAR 52.216-1) (APR 1984)

The Government contemplates award of a single award IDIQ Contract (with Cost Plus Fixed Fee (CPFF) task orders) resulting from this solicitation.

L.3.4 CEILING AMOUNT AWARD ON INITIAL OFFER

At award, a ceiling amount will be added to the basic contract. This ceiling amount shall be, $28,511,148.16, and will serve as the cumulative ceiling for all task orders issued under this contract.

L.3.5 GUARANTEED MINIMUM / INITIAL TASK ORDER (ITO)

The Government will distribute the initial task order simultaneously with the contract award. The ITO award value will be based on the successful offeror’s proposed cost for the ITO. The ITO will have a guaranteed minimum value of $25,000.00. The guaranteed minimum is only applicable to the successful offeror and only within the base period. After satisfying the guaranteed minimum in the base period, the successful offeror is not guaranteed any further task orders.

L.4 AWARD ON INITIAL OFFER

The Government intends to evaluate proposals and award a contract without discussions with Offerors (except clarifications as described in FAR 15.306(a)). Therefore, the Offeror’s initial proposal should contain the Offeror’s best terms from a price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary (FAR 52.215-1(f)(4)).

L.5 PROPOSAL SUBMISSION

a. Offerors are invited to submit a proposal in accordance with Paragraph L.8, Proposal Preparation Instructions, to arrive electronically through the AMRDEC SAFE website no later than the proposal due date for this solicitation. The Government does not authorize submission of telegraphic, facsimile, paper or CDROM offers via hand carry or mail carrier for this solicitation.

b. The proposal due date is 10:00 AM Eastern time on 14 February 2018.

c. All proposals submitted in response to this solicitation will be submitted electronically via the AMRDEC SAFE website. No paper copies or electronic copies submitted outside of the SAFE website (i.e., emailed directly to the any NMLC email address) will be accepted.

d. Submitting your proposal:

The AMRDEC SAFE application is used to send large files to individuals which would normally be too large to send via email. There are no user accounts for SAFE - authentication is handled via email and Civilian Access Card (CAC). The application is available for use by offerors.

The AMRDEC SAFE application can be accessed via https://safe.amrdec.army.mil/safe.

Offerors shall proceed as “Non- CAC Users” under all circumstances.

After selecting the “Non- CAC Users” option above, the page will be redirected to the package upload form. Fill in all the required input fields (field names are in italics):

Personal Information:

Your Name - Your name, Your Company Name.

Your Email address - Your email address.

Confirm Your Email Address - Re-enter your email address.

File Information:

Description of File(s) - Enter a description for the package;

File(s) - Click the "Browse" button to select your file(s). You may add up to 25 files per package, so long as the total file size does not exceed 2GB. The total file size is the combined file size of all submitted files.

Deletion Date – Leave this date at the default setting of two weeks (14 days) from the submission date.

Recipient Information:

Manually Enter Email Address: Input jennifer.m.reed20.civ@mail.mil and hit the add button. (To remove a recipient, highlight their name and click the "Remove" button.)

Email Settings:

Check all four of the boxes:

- Encrypt email message when possible.
- Notify me when file(s) downloads are STARTED.
- Notify me when file(s) downloads are COMPLETED.
- Require CAC for Pick-up (all recipients will need to log in with a CAC to download file(s).

To the right of “Email Settings” is a nondescript box with two options (None or FOUO). Select the FOUO option and select “sensitive” from the dropdown menu below.

Review all fields for accuracy and hit the ‘submit” button. Clicking the "Submit" button will upload the files and submit the package. Guest users will need to check their email to verify their email address before the recipients will be notified. After the package has been uploaded, the Government will receive a link to the package download page as well as a password. These passwords are unique for each recipient (not the package), and will be disabled once SAFE detects that the user successfully downloaded each file within the package.

Once the offeror has submitted their proposal, they shall send a confirmation email to thomas.l.hood26.civ@mail.mil and jennifer.m.reed20.civ@mail.mil and provide their company name and contact information as well stating that they have submitted a complete proposal to SAFE in response to solicitation N62645-18-R-0008.

Submission of proposals is a onetime affair (unless in unusual circumstances multiple SAFE submissions are required because an offeror exceeded the 25 file limit per SAFE submission.). Additional documents will not be accepted after receipt of the confirmation email from the offeror to thomas.l.hood26.civ@mail.mil and jennifer.m.reed20.civ@mail.mil, which confirms successful submission of the proposal.

e. Any data previously submitted in response to another solicitation, whether submitted to the Naval Medical Logistics Command or another agency, should be assumed to be unavailable during this proposal evaluation and source selection process. Proposal data shall not be incorporated into the proposal by referring to another proposal or other source.

f. The Government reserves the right to request additional information after receipt of Offeror’s response to the RFP. The proposal shall be valid for not less than 180 calendar days from the proposal due date. The Offeror shall make a clear statement that the proposal is valid until such date in Volume I.

g. Offerors are cautioned that in order for their proposal to be eligible for award, the proposal shall be in compliance with all of the terms and conditions set forth in the RFP.

h. A company with multiple Divisions (and each division registered separately in SAM) is permitted to submit a separate proposal by Division for award consideration. However, Offerors are cautioned that if one company submits separate proposals from multiple Divisions, each Division’s proposal should address the full RFP requirements uniquely based on their particular Division’s capabilities. For example, management processes, small business participation plans, and/or past performance submissions of a different Division may not be used in support of the Division submitting the proposal. The proposal must be specific to the Division submitting the proposal.

L.6 SEQUENCE OF EVENTS

The Government will employ source selection techniques to evaluate proposals, conduct negotiations and determine the successful Offeror in this acquisition. "Offer," for the purposes of this solicitation, shall be defined as a response to the solicitation that, if accepted, would bind the Offeror to perform the resultant contract. If the Government deems discussions necessary, a competitive range determination will be made.

The following describes the sequence of events Offerors can expect during proposal evaluation and negotiation:

a. The Offeror's proposal shall be submitted in accordance with Paragraph L.8, Proposal Preparation Instructions.

b. Upon receipt, the proposals will be reviewed for completeness and compliance with RFP requirements. If a proposal is incomplete or received late (in part or in full) the proposal will not be evaluated. The proposals will receive a detailed evaluation employing the process and criteria identified in Section M of this RFP.

c. In accordance with FAR 15.306, the Government may conduct exchanges with Offerors after receipt of proposals leading to the establishment of the competitive range and any subsequent competitive range determination that may be made.

d. The Government may conduct exchanges with Offerors prior to establishment of the competitive range that may be made in order to enhance the Government’s understanding of proposals; allow reasonable interpretation of the proposal; or facilitate the Government's evaluation process. Such communications shall not be used to cure proposal deficiencies or material omissions, materially alter the technical or price elements of the proposal, and/or otherwise revise the proposal. Such communications may be considered in rating proposals for the purpose of establishing the competitive range. Furthermore, such communications do not and will not permit Offeror's to modify, revise, or otherwise change any element of their proposal.

e. The Government reserves the right to make award without entering into discussions. Offerors shall be prepared to enter into discussions and/or negotiations and, if authorized by the Contracting Officer, may be allowed to revise or modify their proposals. For those Offerors in the initial competitive range, the Government will submit Discussion Items, which will require a response per instructions that will be provided at that time.

f. The Government will incorporate into the resultant contract any and/or all commitments made in the Offeror’s proposal.

L.7 NOTICE OF HUMAN USE RESEARCH

There is a high probability that Human Use Research will be conducted by the successful offeror under their proposed PWS that would be incorporated into a task order award.

a. The performance of research involving human subjects shall be conducted in accordance with Defense Federal Acquisition Regulation Supplement (DFARS) clause 252.235-7004 “Protection of Human Subjects,” 32 CFR 219 “The Common Rule,” 10 USC 980 “Limitation on Use of Humans as Experimental Subjects,” Department of Defense (DoD) Instruction 3216.02 “Protection of Human Subjects and Adherence to Ethical Standards in DoD-Supported Research,” and Secretary of the Navy Instruction 3900.39 (series) “Human Research Protection Program,” as well as other applicable federal and state law and regulations, and Department of the Navy guidance.

Bureau of Medicine and Surgery (BUMED) Instruction 6500.3 (Series) “Research Integrity, Responsible Conduct of Research Education, and Research Misconduct” applies to research sponsored or funded by Navy Medicine.

Federal regulations governing current Good Clinical Practice (cGCP) are found in 21CFR 11, 50, 54, 56, 312, and 314 and important guidelines are in the FDA Information Sheets. Additional regulations for human subjects protection are found in 45 CFR 46. The International Convention on Harmonization Guidelines for Good Clinical Practice are also standards governing the conduct of research trials.

The Contractor must be cognizant of and abide by the additional restrictions and limitations imposed on the DoD regarding research involving human subjects, specifically as they regard vulnerable populations, recruitment of military research subjects, and informed consent and surrogate consent and chemical and biological agent research. Food and Drug Administration regulation and policies may also apply. The Contractor shall rely on the local command’s designated Institutional Review Board (IRB) as the IRB of record for the research to be supported under the contract. The Contractor shall also comply with the standard research training requirements of NSMRL.

The Contractor shall hold an active (i.e., not expired) Federalwide Assurance (FWA) appropriate for research to be supported under the contract. The FWA shall remain active for the duration of the contract. The FWA is issued by the Department of Health and Human Services.

b. The following requirements must be completed prior to the Contractor’s performance of research involving human subjects or expenditure of funding on such effort, whichever occurs first:

(1) The Contractor shall enter into a DoD Institutional Agreement for Institutional Review Board (IRB) Review (IAIR) with the local command. The IAIR will apply to all human subject research supported under the contract. The IAIR shall be executed by the parties no later than 30 days after the effective date of the contract, or before commencement of performance of research involving human subjects or expenditure of funding, whichever occurs first.

(2) Contractor personnel providing support under the contract shall complete initial and ongoing research ethics and human subject protections training appropriate to each individual’s level of involvement, duties, and responsibilities.

(3) The Contractor shall obtain written notice from the local command that: (i) Contractor personnel identified as supporting human subject research under the contract have been added to the applicable research protocol; (ii) performance of the protocol has been approved by the Command’s Institutional Official and that performance may begin; (iii) a determination that the protocol meets exemption criteria including the exemption category or classification of research risk (e.g., minimal risk); (iv) confirmation of continuing acceptability of the Contractor’s assurances; and (v) Human Research Protection Official (HRPO) review of the protocol in accordance with DFARS clause 252.235-7004 has been completed. Contractor personnel shall not commence performance of research involving human subjects until stated notice is received.

(4) The Contractor shall notify the local command of personnel changes under the contract. New personnel that will perform research involving human subjects will be required to complete applicable training and will be added to the applicable research protocol(s) as discussed above.

c. The Contractor shall support administrative efforts by the local command to ensure compliance with the terms of this requirement. This support includes identifying Contractor personnel that may support human subject research under the contract and maintaining records of training and other documentation to demonstrate compliance with human research protection requirements under the contract. The Contractor shall also assist with the continuing review of the human subject research that is supported under the contract.

d. Failure of the Contractor to comply with the terms of this requirement will result in the issuance of a stop-work order under Federal Acquisition Regulation clause 52.242-15 (Alt 1) to immediately suspend, in whole or in part, work and further payment under this contract, or will result in other issuance of suspension of work and further payment for as long as determined necessary at the discretion of the Contracting Officer.

e. The terms of this requirement are applicable to and shall be included in all Subcontracts that may include the support of human subject research.

L.8 PROPOSAL PREPARATION INSTRUCTIONS

L.8.1 SOLICITATION QUESTIONS

Questions concerning the proposal are due no later than 2:00 PM Eastern Time, 19 January 2018. RFP number N62645-18-R-0008 shall be included in the email subject line. Questions shall be submitted to Contracting Officer and Contract Specialist at thomas.l.hood26.civ@mail.mil and jennifer.m.reed20.civ@mail.mil by the required time, and no questions shall be addressed after this cutoff date. Offerors shall submit one set of questions only; multiple emails shall not be accepted. An amendment to the solicitation will be issued providing responses to the questions.

L.8.2 ELECTRONIC PROPOSAL SUBMISSION

Proposals shall be submitted in two electronic Volumes:

Volume I: Non-Cost Volume II: Cost

Volume I and Volume II will be reviewed and evaluated. Each volume shall be a stand-alone document and shall clearly and completely provide the information being requested. The two volumes will be evaluated as part of the source selection evaluation process (see Section M).

L.8.2.1 ELECTRONIC PROPOSAL

The overall proposal shall consist of the following separate, individually titled volumes.

MS Word is an acceptable file format for Volume I of the proposal. MS Word and MS Excel are acceptable file formats for Volume II of the proposal. Adobe Acrobat is an acceptable format for those items requiring fill-in.

Volumes and number of copies each are identified below. The Government cannot consider pages submitted in excess of the stated page limitations. Page limitations include all text, graphs, pictures, appendices, references and exhibits unless otherwise noted. Cross reference matrices, tabs, index sheets, tables of contents, dividers and other such aids that are solely used to assist the evaluator in locating information and are advisory in nature, imparting no other information other than the identification of content, will not be counted against any page limits stated within this RFP. Type shall be no smaller than a font size of eleven (11) and shall have 1.0 line spacing. Type for graphics, tables and reproductions shall be no smaller than a font size of 10 with a minimum of 1” margins. Page size shall not exceed 8 ½” x 11”. The page limits described below do not include Title Page, Table of Contents, and Glossary. Double column pages are not allowed. Separate electronic files shall be used for Volume I and Volume II.

Volume Number
Title

Page Limit

Volume I: Subpart I
Administrative:

Section I- Executive Summary

Sec I- 1 Page limit

Section II- Solicitation Documents

Sec II- Signed SF33 front page and all acknowledged amendments

Section III- Reps and Certs

Section IV- Small Business Participation Plan and Subcontracting Plan

Section V- Verification of Security Clearance Level

Sec III- No page limit

Sec IV- No page limit (Subcontractor consents may be an attachment to Subpart IV and are not included in the page count.)

Sec V- No page limit

Volume I: Subpart II
Management Approach/Risk

20 Page Limit

Volume I: Subpart III
Technical Approach for Initial Task Order

15 Page Limit (Key Personnel resumes are an attachment to Subpart III and are not included in the page count.)

Volume I: Subpart IV
Past Performance

8 Page Limit

Volume II: Subpart I
Cost Proposal for the Initial Task Order

No Page Limit

L.9 EVALUATION APPROACH

L.9.1 VOLUME I, SUBPART I: ADMINISTRATIVE

The offeror shall submit all of the following sections to Volume I: Subpart I or the proposal will be considered incomplete:

L.9.1.1 SECTION I: EXECUTIVE SUMMARY

The offeror shall provide a high level summation of its proposal.

The offeror shall make a clear statement in the Executive Summary, that the proposal is valid for not less than 180 calendar days from the proposal due date.

L.9.1.2 SECTION II: SOLICITATION DOCUMENTS

Offeror(s) shall complete the OFFER part of the Standard Form (SF) 33 format (cover page). An official having the authority to bind the firm contractually must sign the cover page. If this individual is not an officer of the company, the proposal shall be accompanied by some form of written evidence of the individual's authority to bind the company, under contract, to a particular course of action. This might include such evidence as a written delegation of said authority, signed by an officer of the company.

The Offeror(s) shall acknowledge all amendments either in block 14 of the SF33 or by signing the cover sheet of each amendment and returning them as part of this volume.

L.9.1.3 SECTION III: SECTION K (REPS AND CERTS)

The offeror shall complete the annual representations and certifications electronically through the System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM/. The offeror shall verify their annual representations and certifications are current, accurate, complete and applicable to this solicitation as of the date of this offer and are incorporated in this offer by reference. (Refer to SAM Annual Representations and Certifications Certification Sheet in Section K.)

The applicable NAICS code for this solicitation is 541715, with a small business size standard of 1000 employees.

In addition to submission to SAM the offeror shall complete the SAM Annual Representations and Certifications Certification Sheet and the fill-ins required by the full text clauses in Section K, and submit an electronic copy of each in Section III of the Volume I Subpart I. (Refer to SAM Annual Representations and Certifications Certification Sheet and the full-text clauses in Section K.)

The offeror shall complete and submit FAR provisions 52.204-8, 52.209-7, 52.209-11 (via 52.204-7), 52.219-28 (via 52.204-7), 52.222-22 (via 52.204-7), 52.222-25 (via 52.204-7) and the “SAM Certification” in Section K.

L.9.1.4 SECTION IV: SMALL BUSINESS PARTICIPATION PLAN AND SUBCONTRACTING PLAN

All offerors are required to submit a small business participation plan. If applicable (for other than small business concern offerors under the assigned NAICS code herein), the offeror shall submit a subcontracting plan in accordance with FAR Clause 52.219-9 Alt II DEV and DFARS Clause 252.219-7003 DEV (for reference see FAR 19.704 and DFARS 252.219-704). The subcontracting plan requirement is not applicable to small business concerns qualified as such under the NAICS code assigned to this solicitation. Master subcontracting plans can be included as an appendix to the subcontracting plan and will not count towards the page count.

L.9.1.5 SECTION V: VERIFICATION OF SECURITY CLEARANCE LEVEL

The offeror shall submit documentation verifying a TOP SECRET facility clearance. A completed DD Form 254 will be provided at time of contract award.

L.9.2 VOLUME I, SUBPART II: MANAGEMENT APPROACH/RISK

The Offeror shall provide its approach that clearly reflects how it plans to accomplish the work identified in the PWS.

The Management Approach should address the following:

· Management structure with regard to roles and responsibilities, lines of authority, span of control, flow of information, and communication strategies amongst the contractor team, any subcontractors, requiring activities, and external organizations,

· Ability to monitor contract activities,

· Subcontract Management,

· Strategies / processes to identify and manage / mitigate risk,

· Approach to managing cost, schedule, and performance for multiple task orders,

· Recruiting and retention.

Required Attachment to Volume I: Subpart II: Management Approach/ Risk:

Attachments do not count towards the overall page limit for Subpart I.

Attachment A: Organizational Conflict of Interest (OCI) Mitigation Plan: The Offeror must present its Organizational Conflict of Interest (OCI) Mitigation Plan in response to an actual, potential, or perceived conflict of interest associated with performance of this requirement. The OCI Mitigation Plan is limited to 10 pages.

Attachment B: Human Use Documentation: The offeror shall include in their proposal, proof of an active (i.e., not expired) FWA. If a subcontractor may perform human subject research, they shall have their own active (i.e., not expired) FWA. The subcontractors FWA must be possessed by the subcontractor and they are not allowed to work under the prime contractor’s FWA. You must state clearly if a subcontractor employee will not be performing human subject research and that is why proof of an active FWA is absent.

Attachment C: Indemnification and Medical Liability Insurance (IAW with Section H- “Patient Care and Medical Liability Insurance” and FAR 52.237-7): The supporting documentation shall prove that the offeror possesses current insurance and shall show the expiration date of the policies as well as including individual and aggregate limits for each of the required area of coverage.

Attachment D: Liability Insurance (IAW Section H –“Standard Liability Insurance” and FAR 52.228-7): The supporting documentation shall prove that the offeror possesses current insurance and shall show the expiration date of the policies as well as the including individual and aggregate limits for each of the required areas of coverage.

L.9.3 VOLUME I, SUBPART III: TECHNICAL APPROACH/RISK FOR THE INITAL TASK ORDER

Technical proposals will demonstrate that the offeror's proposed labor mix and level of effort are adequate to complete the tasks listed in the PWS. Additionally, the offeror shall demonstrate a thorough understanding of the technical requirements of the task order. The offeror shall demonstrate the ability to provide any products or reports as part of the task.

Resumes: The Offeror must present resumes for all key personnel positions. Key Personnel are delineated in the initial task order PWS. Resumes should include: the individual’s name, descriptions of past/current responsibilities, relevant work experience, and any certification in the main program areas. Proposed personnel shall demonstrate sufficiently to the proposal evaluator(s) that the person proposed has the knowledge and experience relevant to accomplish the required tasks. DO NOT include Social Security Number (SSN), date of birth, home address, or personal telephone number of the person on the resume. Resumes are limited to 2 pages per key personnel and do not count towards the overall page limit of 10 pages.

Estimated level of effort in the PWS: The Government estimates that this task order will require an approximate level of effort as outlined in the PWS. Please note that the Government estimate is only put in place for Offerors to ascertain the approximate or estimated level of effort for this task and to allow Offerors to better understand the general scope of this effort. Offerors are encouraged and expected to submit a level of effort consistent with your technical approach.

Government Furnished Equipment: Offerors need to specify any Government Furnished Equipment / Information / Property, necessary to perform this task. This shall include any Contractor purchased or acquired/ Government-owned items. This attachment should include the following information: item description, quantity, and current location. Detailed Bills of Materials shall be submitted along with the proposal; noting part numbers, prices, and need dates for all required GFE. The contractor may assume that equipment typically available on a Government site will be available and does not have to be listed. Any GFE past what is typically available for contractors in an office environment, which the contractor needs to complete the work listed in the PWS, needs to be listed.

L.9.4 VOLUME I, SUBPART IV: PAST PERFORMANCE

All information required pertains to all proposed first-tier subcontractors with whom the Offeror is teaming, as well as the Offeror. The Offeror shall submit with its proposal the first tier subcontractor’s letter(s) of consent allowing the Government to disclose the subcontractors' past performance to the Offeror during negotiations.

L.9.4.1 Past Performance Information Sheets.

Past Performance has a page limit of eight pages (to include past performance information sheets).

The first four pages will be the submission of a maximum of four Past Performance Information Sheets (Section J, Attachment VI – Past Performance Information Sheet). If more than four Past Performance Information Sheets are provided, only the first four will be considered. If a Past Performance Information Sheet contains more than one page (inclusive of narrative), only the first page will be considered.

The second four pages afford the offeror four pages to cover the items highlighted under the paragraph below titled “Additional Four Pages”.

The Offeror shall submit up to four (4) Past Performance Information Sheets (Section J, Attachment VII – Past Performance Information Sheet) for contracts over the past three (3) years which are similar to the size and scope of the PWS in this solicitation. Two of the four contracts must have been held by the prime offeror.

Contracts cited must be current, or have ended not more than three years prior to the closing date of the solicitation. If the contract performance ended more than three years prior to the closing date of the solicitation it will be determined not relevant.

Each of the Past Performance Information Sheets shall be completed in its entirety. The Past Performance Information listed on each sheet shall be for services related to the services required under this solicitation. For each of the Past Performance Information Sheet submitted the offeror shall describe the objectives achieved detailing how the effort is similar to the requirements of this solicitation (referencing the PWS in Section C). The offeror may include contracts that demonstrate the prior experience of key personnel or subcontractors/teaming partners who will be performing in support of the contract resulting from this solicitation; such contracts shall be clearly identified to show the relationship of the past performance entry to the offeror.

Each Past Performance Information Sheet may include one or more task orders if they are under a single IDIQ contracts. Otherwise, contracts should be limited to one per sheet. Sheets should list applicable task orders and not just the IDIQ base contract number.

Each Past Performance Information Sheet shall identify no more than one Point of Contact (POC) and if more than one POC is provided for any Past Performance Information Sheet, only the first POC will be considered. The Government may contact the POCs listed on the Past Performance Information Sheets. POCs must be either Government personnel (civil service or military) or employees of private sector clients with whom you have provided services. Information provided by or for POCs who work directly for your company, or indirectly (i.e., in a prime/ subcontractor or mentor/protégé relationship, etc.), will be determined not relevant. The Government may contact the POCs listed on the Past Performance Information Sheets.

Additional Four Pages: Any and all contracts (to include any contract or contracts listed on a Past Performance Information Sheet) terminated for cause in whole or in part during the past three (3) years (to include those currently in the process of such termination) are considered relevant. Please provide a brief background, issues with contract performance, any cure notices or show cause letters received and description of any corrective action taken. The second four pages afford the offeror four pages to cover these items.

In addition to the Past Performance Information Sheets, the Government reserves the right to use alternative resources to gather past performance information.

L.9.4.2. Subcontracting Concerns

If Past Performance is submitted for a contract under which the offeror (or proposed subcontractor, partner, mentor, protégé, parent company, sister company, etc.) provided services as a subcontractor, partner, mentor, protégé, parent company, sister company, etc., the Past Performance Information Sheet shall clearly describe the corporate relationships among those who provided the services, citing key responsibilities for each, to include identifying the specific services provided (in terms of numbers and types of personnel, locations, etc) and nature of services provided (e.g., consulting services, subject matter expertise). If the submission does not clearly detail the specific responsibilities and relationship under a contract, it will be determined not relevant.

If a subcontracting, teaming, partnering, mentoring or other relationship is proposed, the offeror shall submit written consent from the subcontractor, partner, etc. to disclose their Past Performance information to the contractor. If such consent is not provided as part of the submission, the Past Performance of the subcontractor, partner, etc., it will be determined not relevant.

If neither the offeror nor its subcontractor(s), teaming partner(s), etc. possess relevant past performance, the offeror shall submit a statement affirming that they possess no relevant Past Performance.

L.9.5. VOLUME II: COST

VOLUME II, SUBPART I: COST PROPOSAL FOR THE INITIAL TASK ORDER

Offerors are cautioned that their proposed costs should be consistent with the proposed technical approach and reflective of the effort required by the solicitation. Unrealistically low proposed costs may be grounds for eliminating a proposal from the competition on the basis that the offeror does not understand the requirement.

The initial task order PWS contains the Governments estimated amounts for subcontracts, consultants, other direct costs (ODC) and travel. The offeror shall use these amounts in the constriction of their cost proposal. The amounts are unburdened and may be burdened by the offeror in accordance with their accounting system.

L.9.5.1 Section 1 - Cost Breakdown

The proposed Cost Plus Fixed Fee amount for the initial task order shall be adequately supported in order for the Contracting Officer to make the determination that the costs are fair and reasonable. Therefore, you are required to provide a breakdown that shows the application of direct labor hours, direct labor rates, overhead and other indirect cost rates, subcontract costs, other direct costs, and fixed fee. The proposed fixed fee shall not exceed ten percent (10%) of the estimated contract cost (excluding fee). The offeror shall prepare and submit the cost support in accordance with Table 15-2 of FAR 15.408. The offeror will not be required to certify this cost support.

If an offeror blends rates, they shall show how they arrived at the blended rate.

If subcontractors are unwilling to submit their direct labor rates (only) to the prime contractor, they shall submit those rates directly to the Government utilizing the same proposal submission instructions and due date and time located in this section.

The information shall be provided on an MS Excel spreadsheet showing all cost elements, amounts, and the application of direct and indirect rates.

Offeror’s shall not lock out spreadsheets, so that formulas are not visible or link to other spreadsheets where the Government cannot access the underlying value. All calculations and formulas shall allow the Government to view all numerical values in the calculations or shall link to cells in the same spreadsheet that allow the Government to view the values.

Offerors are responsible for determining which of their proposed labor categories are covered by the SCA and they shall specify if any SCA covered labor categories in their price proposal along with providing the applicable wage determination schedule and revision number.

L.9.5.2 Section 2 – Other Information

The offeror shall provide the following information:

a. A narrative along with the MS Excel Cost Sheet that describes how rates are applied, which includes the cost base that the rates are applied against.

b. Accounting System – Provide evidence of an adequate accounting system. See FAR 16.301-3(a)(3). This may include completed Standard Form 1408s (Preaward Survey of Prospective Contractor Accounting System).

c. Purchasing System – Provide evidence of an approved purchasing system. See FAR Subpart 44.3.

d. Rate Agreements – Provide a copy of any current rate agreement or forward pricing rate agreement that supports the proposed contract rates. Copy in this context is defined as a direct and full copy of the actual applicable pages from your FPRA (to include cover sheet) and not offeror created tables or excerpts. These agreements may be with the Defense Contract Management Agency (DCMA), Department of Health and Human Services (DHHS), or other Federal Government contracting offices.

e. Defense Contract Audit Agency (DCAA) Audit – Provide a copy of any DCAA audit that supports the proposed contract rates or costs.

f. DCAA Office – Provide the offeror’s cognizant DCAA office, including telephone number for points of contact and the DCAA DODAAC number.

g. DCMA Office - Provide the offeror’s cognizant DCMA office, including telephone number for points of contact.

L.9.5.3 Section 3 - Proposal Assumptions

The offeror shall include any assumptions used to develop the proposed costs.

(End of Summary of Changes) image1.wmf