1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT J 1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

AM0003 14 Jun 2018

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

NAVFAC Hawaii Construction Acquisition Division (OPHA2) 400 Marshall Road See Item 6 Pearl Harbor, Hawaii 96860-3139

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.

N62478-18-R-4035

X 9B. DATED (SEE ITEM 11)

19 Apr 2018

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[ X ]The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ X ] is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning __1__ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required) NA

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: FAR CLAUSE 52.243-4, CHANGES

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor [ ] is not, [ ] is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N62478-17-R-4035, FY16 MCON PROJECT P-416 ENERGY – PMRF POWER GRID CONSOLIDATION

AT THE PACIFIC MISSILE RANGE FACILITY, KEKAHA, KAUAI, HAWAII

(See page 2 )

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105 STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

AM0003

SF30, BLOCK 14 CONTINUED

1. Attached hereto are new pages to the solicitation. The revision mark “AMENDMENT 0003” is shown on each new page.

a. DELETED SECTIONS/CLAUSES/PROVISIONS/PAGES/PARAGRAPHS.

Document 00900 Appendix A Responses to Questions Submitted by Planholders Document 00900 Appendix B, Site Visit Attendee List

b. NEW SECTIONS/CLAUSES/PROVISIONS/PAGES/PARAGRAPHS

Document 00900 Appendix D Responses to Questions Submitted by Planholders Document 00900 Appendix E, Site Visit Attendee List

2. The date for receipt of proposals is June 28, 2018, 2:00 P.M., HST.

Amendment 00003

DOCUMENT 00900

APPENDIX D

RESPONSES TO QUESTIONS

SUBMITTED BY PLANHOLDERS

FOR

RFP NO. N62478-18-R-4035

Q1. We went over the project specs and plans and did not find any Covered Defense Information (CDI) requirement. Please confirm.

A1. Confirmed.

Q2. We have this note in the bottom of every drawing. Please clarify on how we can deliver the drawings to the subs and suppliers:

A2. Disregard Unclassified//For Official Use Only markings.

Q3. The attached .pdf file was also found on a few sheets. Please advise how to treat and deal with this info and if it’s okay to send to the subs/suppliers.

DISTRIBUTION STATEMENT C. DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR

CONTRACTORS PER CONTRACT N00604‐09‐D‐0001 OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO CODE 7030

A3. Disregard Distribution Statement C.

Q4. Factor 1. Experience requires a minimum of 1 and maximum of 3 relevant construction projects. Designer experience is NOT listed in the RFP as an evaluation factor; however, Attachment A is titled Construction & Design Experience Project Data Sheet. Will the designer experience and past performance be added as an evaluation factor for this LPTA proposal, or will the government provide a revised Attachment A?

A4. See Document 00110 Evaluation Factors for Award, Attachment A revised by Amendment 0002.

Q5. Typically, DoD design-build projects identify a funding limitation. We are not able to locate where this is listed in the solicitation documents. Will the funding limit be provided?

A5. See Document 00100 paragraph 1.8 revised by Amendment 0002.

Q6. Will the small business plan due date be allowed to be submitted 24 hours after the price proposal is submitted? There are current MILCON projects bidding in Hawaii for the Navy that allow an extra day, which is extremely helpful.

A6. Yes. In accordance with Document 00100 paragraph 1.7, “Plan shall be submitted prior to contract award.” Contracting Officer will contact the apparent successful offeror to request the subcontracting plan prior to contract award.

Q7. Please confirm that the explicit access to the bid documents from the Navy is only for the prime contractors and is NOT required to be carried through to the subcontractors and vendors. Unless advised otherwise, we expect that the prime contractor has no restrictions on sharing the bid documents to obtain quotations.

A7. Confirmed

Q8. We have noticed that a substantial portion of the project will require heavy clearing for the installation of the duct bank system. Are there any clearing limits established in which we are limited? Unless told otherwise, we are going to assume that we will be able to clear what is necessary to install the duct bank system.

A8. See DB RFP Part Three, section G1010 for site clearing requirements.

Q9. If we reduce the cleared vegetation to chips, would we be able to leave these materials on site and distribute over the duct bank right of way?

A9. See DB RFP Part Three, section G1010 for site clearing requirements.

Q10. This project will generate an excess amount of soil from the excavation. Will we be able to waste this excess material onsite? If so, please let us know where this disposal site is located.

A10. See DB RFP Section 01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS

Q11. The bridging documents provided us shows little to none of the existing utilities that we may encounter during our duct bank system installation. In an effort to level the assumptions we would need to make for these encounters, would if be possible for you to provide us a set amount of assumed existing utility crossings in which all bidders can base our proposals on?

A11. See DB RFP Part 6 Reference Drawings. Known existing utilities are shown on PMRF Site General Development Maps.

Q12. What are we to assume for contaminated soil, if anything?

A12. Contaminated soils are not expected to be encountered as indicted in DB RFP Part Three, section F2020.

Q13. What are we to assume for asbestos materials, if anything?

A13. See DB RFP Part Three, section F2020 for asbestos material identification and disposal requirements.

Q14. What are we to assume for hazardous materials, if anything?

A14. See DB RFP Part Three, section F2020 for hazardous component abatement requirements.

Q15. On Drawings SK-E108 and E109 you indicate that we are to use existing duct line for new 12KV Tie To1, FDR06, and Fiber Cable. Can you provide us as-built drawings for these existing systems, or at least lengths between manholes for cable installation requirements?

A15. See DB RFP Part 6 Reference Drawings. Topographic Survey Drawings (SKCS series) provides location of manholes.

Q16. On Drawings SK-E110, E111, and E112 you state “Reuse existing 12KV Feeder Fiber Duct bank.” Does this mean we are not installing any wire in this location and we are connecting to the existing system at the start and end of this section? Or is it the same as the system on SKE108 and E109 in which we are to install cable in existing duct? If so, please provide us as-built drawings with manhole layouts.

A16. Drawing SK-E001 provides distinguishing line-weight differences for existing and new work. Drawings SK-E110, SK-E111 and SK-E112 show existing ductbank (light line-weight) to be used for FDR05 and show requirement for new ductbank (heavy line-weight) for T02 and FIBER. Specific requirements for existing ductline and manhole layout record drawings should be provided as part of the DB Contractor scope of work.

Q17. This project is Design-Build construction; however, Factor 1-Experience does not have a requirement for designer experience. To provide a qualified design-build team, we request that you add a requirement for design projects to be included under Factor 1, utilizing similar relevant criteria of underground electrical distribution experience.

Attachment A is already set up to differentiate between Design Projects and Construction Projects.

A17. See Response to RFI #4

Q18. What are the requirements for surface restoration in areas outside of paved roads and parking lots? Are we to hydroseed these areas?

A18. See DB RFP Part Three, section G2050 for landscaping requirements

Q19. On the Drawings SK 102 to SK 103 you have provided us a note that states:

“Ductline Routing Shown passes through archaeological and historic areas of low to medium sensitivity.” What are the requirements for this work? If archaeological monitors are required, will the government supply these personnel? If we are to supply these archaeological monitors, how many are required? And at what frequency will they be required to be on site?

A19. See DB RFP Part Three, Section 3.3 Cultural Resources for archaeological monitoring requirements.

Q20. Will there be any escorts required for on-base deliveries? If so, who is to provide these escorts?

A20. No escorts will be provided. Following PMRF access requirements, delivery person(s) will submit a PMRF Visitor Access request. Once cleared for entry, the delivery person can enter the base unescorted.

Q21. Will we be allowed to discharge our dewatering water onsite?

A21. See DB RFP Part Three, Section G103010 for dewatering requirements.

Q22. For the duct bank work that is in the “Runway Clearance Zone” as shown on Drawings SK-E103, E104 and E105, are there any restrictions as to work hours to complete this work? Nightshift only? Temporary shutdowns for aircraft landings?

A22. See DB RFP Section SECTION 01 35 13.05 20 SPECIAL PROJECT PROCEDURES FOR DESIGN-BUILD and DB RFP Part 6 AC No: 150/5370-2G

OPERATIONAL SAFETY ON AIRPORTS DURING CONSTRUCTION

Q23. For the duct bank work that is in the “Runway Clearance Zone” as shown on Drawing SK-E103, E104, and E105, are there any restrictions as to open trenches? Will we need to cover trenches each night? Height of stockpile soil?

A23. See response to RFI #22.

Q24. For the duct bank work that is in the “Runway Clearance Zone” as shown on Drawings SK-E103, E104, and E105, are there any restrictions as leaving our equipment parked in this area overnight? Or maximum height of construction equipment in the area?

A24. See response to RFI #22.

Q25. Will we be allowed to install the fiber optic cable and conduit in the same trench as the power cable and ducts TO1 and TO2 and other power runs? If yes, will this still be allowed if you select Options items 1 and 2?

A25. Provide fiber optic cable installation in accordance with NAVFAC Hawaii PUBLIC WORKS UTILITIES CRITERIA PW6 600-01, 10 April 2006, section 2.7 found in DB RFP Part 6, Section 06 NAVFAC CRITERIA and in accordance with applicable UFCs.

Q26. Will the concrete encasements of the electrical power ducts require thermally-approved concrete? If so, please provide specification for this material and testing requirements.

A26. As indicated in Part 3 Chapter 2 paragraph 2.4, DB Contractor and his designer of record should provide ductbank thermal calculations in accordance with UFC 3-501-01 load analysis criteria in order to determine characteristics of concrete required for ductbanks. See also UFC 3-550-01 section 3-12 for concrete for underground systems.

Q27. Will the compacted backfill above the concrete duct bank encasement require thermally-approved backfill? If so, please provide specification for this material and testing requirements.

A27. As indicated in Part 3 Chapter 2 paragraph 2.4, DB Contractor and his designer of record should provide ductbank thermal calculations in accordance with UFC 3-501-01 load analysis criteria in order to determine characteristics of backfill required for ductbanks.

Q28. On Drawing ES502 you have a note #3 that states: “provide root barrier as required to protect new duct banks located near trees from root penetrations damage.”

Please provide us a detail of the root barrier material.

A28. DB Contractor and his designer of record shall provide design and installation of root barrier in accordance with DB RFP Part 3, Chapter 6 Section G205005

PLANTINGS.

Q29. Section 011400.0520, paragraph 1.3.1.2 – Identification Badges and Installation Access. If the contractor chooses to use the DBIDS service for annual badge in lieu of daily passes, we ask for the following clarifications:

a. What is the average duration of time for the application to be processed?

b. Is there a fee required for each person to submit their application for security clearance check?

A29. See Commander Navy Installation Command, Pacific Missile Range Facility Barking Sands website:

https://cnic.navy.mil/regions/cnrh/installations/pacific_missile_range_facility_barking_sa nds.html

Q30. Please confirm that an individual NPDES permit is not required and the Government will provide the NPDES permit for this project.

A30. See DB RFP Section 01 57 19.01 20 - SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS and G1030 for Contractor responsibilities regarding NPDES permit requirements.

Q31. Section 01 50 00.05 20, paragraph 1.4, Temporary Utilities. Please provide the rates to the contractor for use of electricity and potable water at the project site.

A31. Current rates at PMRF effective 01 October 2017 to 30 September 2018 are as follows: AC electricity is $337.10 per MWhr; potable water is $1.68 per kgal. Rates change every fiscal year.

Q32. At the site visit several possible laydown areas were observed adjacent to the main gate and south portion of the base. Is there a designated laydown area for the construction of this project?

A32. See DB RFP Section 01 33 10.05 20 - DESIGN SUBMITTAL PROCEDURES.

DB Contractor and his designer of record shall coordinate laydown areas, hauling routes, etc. as part of their Design submittal documents.

Q33. At the site visit it was observed that the base is maintaining the dirt road right-of way. Several piles of root and tree branches were observed laying to the side of the access route. Will the Government remove this debris?

A33. Debris will be removed by the Government.

Q34. Please provide the site visit attendee list for the contractors’ review.

A34. See Document 00900 Appendix B incorporated by Amendment 0002

Q35. Will the due date of May 30th be extended by a few weeks to allow the contactor additional time to 1) complete the preliminary design for bidding purposes; and 2) locate local resources for this remote project location?

A35. See proposal due date revised by Amendment 0002

Q36. Section 01 50 00.05 20, paragraph 3.1.1.2. Fencing along the construction site is required at all open excavations and tunnels to control access by unauthorized people.

Please clarify if this requirement is only necessary where the pedestrian traffic is expected in the vicinity of the personnel occupied areas; i.e., power plant, main gate, and south area tie-in locations. For bidding purposes, we expect that the lengthy areas away from public access do not require to be fenced.

A36. Provide Fencing in accordance with Section 01 50 00.05 20 - TEMPORARY

FACILITIES AND CONTROLS FOR DESIGN-BUILD.

Q37. Section 01 57 19, Page 17, paragraph 3.1 PROTECTION OF NATURAL RESOURCES includes a list of species that may be encountered during the construction of the project. Please identify the locations and any restrictions on the following: Nene, Shearwater, Moorhen, Coot, Stilt, and the Hawaiian Duck. Also, it is identified that the project maybe located adjacent to critical habitat for "Panicum niihauensis." What is the action required by the contractors if this is encountered?

A37. See DB RFP Part 3 sections 2.5 and 3.2 for direction and point of contact regarding natural resources.

Q38. Section 01 57 19 Page 18, paragraph 3.2.1. Construction General Permit. Please advise what is expected to be required from the contractor to provide a Construction General Permit as required by 40 CFR 122.26 or the State of Hawaii General Permit.

A38. See DB RFP Section 01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS paragraph 1.7. It is the Contractor’s responsibility to obtain any necessary licenses and permits.

Q39. Due to the extensive quantity of concrete required for the duct bank encasement and the remote location of the project from a commercial concrete plant, will the contractor be allowed to set up a batch plant onsite to service this project’s need for concrete materials?

A39. Without any concept of the batch plant, it is very difficult to determine whether a concrete batch plant will be allowed on site. In the past, a batch plant was constructed for the runway resurfacing project. The location of that particular plant is away and to the north of the project site. There is no available cleared site and within the project limits that could accommodate a batch plant. If the successful bidder proposes a concept during the design phase, this question can be reviewed again.

Q40. Part 6 - G403010 lists for us to provide IEDs, including a real time automation controller and remote terminal unit in the power plant control room and at each switch.

Are the number of units correct on SK-E604? Are there any qualifications necessary for person programming and designing? Do they only need to perform the actions on SK- E603?

A40. As indicated in Part 6 – G40 General Requirements, DB Contractor and his designer of record shall provide an Electrical System complete in place, tested and approved, and in accordance with Part 2, Section 2.3.1 as needed for a complete, usable and proper installation.

Q41. Part 6 - G401002 Transformers calls for biodegradable less flammable liquid-insulated. The NAVFAC Hawaii design guide section 2.3.1.7 says that transformers shall be insulated with mineral oil due to recycling and disposal issues. Please provide direction as to which applies.

A41. Provide mineral oil as required by the NAVFAC Hawaii design guide.

Q42. Part 6 - G401002 Transformers. Does the asymmetrical fault current, when connected to the utility and the generation is present, exceed 10,000 amps symmetrical? If it does, is a deadfront transformer still acceptable?

A42. DB Contactor and his designer of record shall calculate fault currents as part of the DB contract document. Utility power and generation will not operate in parallel as indicated on Drawing SK-E604, Switchgear Sequence of Operations.

Q43. Part 6 - Section G401003 Switches controls and devices requires SF6 insulated pad-mounted switchgear. However, the NAVFAC design guide (section 2.3.2.9) for pad-mounted switches tells us not to use SF6 type gas switches due to an unknown white chemical developed in switch. Please provide instruction as to which applies.

A43. Provide bid documents based on SF6 type gas switches. Request variance to NAVFAC Design Standard to allow SF6 type switches after contract is awarded.

Q44. Part 6 - G401003 Switches controls and devices. Can a building or non-stainless enclosure be provided instead of 316 stainless equipment?

A44. Provide bid for type 316 stainless steel in accordance with G40 SITE ELECTRICAL UTILITIES. Coordinate with Contracting Officer any desired alternatives.

Q45. Section 2.3.3.6 of NAVFAC utility design guide states: “If solid state relays are specified… programmable software, and test instruments shall be furnished as part of the project.” Does this apply to this project? Does it require a software license?

A45. Yes, this applies to this project and includes software requirements.

Q46. Part 6 - Does NCTAMS have jurisdiction over the Fiber optic cable?

A46. PMRF currently has jurisdiction over the fiber optic cables. Jurisdiction may change in the future.

Q47. Part 6 - Can the Fiberoptic cable required be routed in the same ductbank and manhole system, or must they be separate?

A47. As indicated in Part 3 Chapter 2 paragraph 2.4 and NAVFAC Hawaii PUBLIC WORKS UTILITIES CRITERIA PW6 600-01, 10 April 2006, section 2.7, DB Contractor shall comply with UFC-3-550-01 for underground electrical system requirements

Q48. Part 6 - Can the SKM model and system be provided to contractor?

A48. There is no current information available.

Q49. Part 6 - Cyber Security. Are there any requirements for the capability of the cyber security team?

A49. Provide Cyber Security requirements in accordance with specification section 01 31 19.05 20 – 1.5.1; DB RFP Part 3 chapter 2 2.3.1; and PTS Section 25 50 00.00 20 (p.838).

Q50. Part 6 - Cyber security Hygiene Checklist number 23 requires Configuration management, and HBS host intrusion prevention system. Is a typical RTAC capable of performing this? Is a separate Switch required to detect?

A50. DB Contractor and his designer of record shall determine hardware capability and requirements as part of the DB contract documents. See DB RFP Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q51. Drawing SK-E603 sequence of operations states there is to be a “workstation” for all switchgear control and monitoring for control of local equipment at each switchgear.

Please define “workstation.”

A51. The statement on SK-E603 should be read in its entirety with attention to the individual sentences: CONTROL INTERLOCKS BETWEEN THE SWITCHGEAR

SHALL RESIDE IN THE AUTOMATION CONTROLLER AT B112. MONITORING

SHALL BE AVAILABLE AT THE MASTER STATION OPERATOR WORKSTATION

FOR ALL SWITCHGEAR. CONTROL AND MONITORING OF LOCAL EQUIPMENT

SHALL BE AVAILABLE AT EACH SWITCHGEAR.

Q52. On the site visit it was noticed in the existing manholes that the fiber may be run in the same conduit as the 15kV. There is only one spare conduit available. When we utilize the existing, can the Fiberoptic cable required be routed in the same conduit and manhole system or must they be separate?

A52. As indicated in Part 3 Chapter 2 paragraph 2.4 and NAVFAC Hawaii PUBLIC WORKS UTILITIES CRITERIA PW6 600-01, 10 April 2006, section 2.7, DB Contractor shall comply with UFC-3-550-01 for underground electrical system requirements

Q53. UFC 3-550-01 section 3-11.5.1 states: “provide separate power and communication manholes.” Are the fiber and power cabling in separate ductbank and manhole systems? Is this true on the existing ductbank to be utilized? What is the requirement on the new ductbank to be installed?

A53. As indicated in Part 3 Chapter 2 paragraph 2.4 and NAVFAC Hawaii PUBLIC WORKS UTILITIES CRITERIA PW6 600-01, 10 April 2006, section 2.7, DB Contractor shall comply with UFC-3-550-01 for underground electrical system requirements

Q54. SK-E501 Typical Utility Duct Section separation – Is this intended to show a typical Comm and Power separation, or just power?

A54. Typical Utility Duct Section Separation detail is intended to show communications and power separation.

Q.55 NAFAC Standard section 2.3.7.3 calls for extension of a 2-inch conduit to nearest manhole for SCADA requirements. Does this apply? Can we use this for fiber requirements?

A55. Referenced NAVFAC Design Standard does apply. Section 2.3.7.3 is requirement for conduits to be installed in new construction for future use and therefore cannot be used for the new fiber installation but must be left for future.

Q56. NAVFAC Hawaii Standards 2.3.9.2 b. states to provide an octagonal type manhole with a minimum size of 8x8x8 unless otherwise specified. Is this the standard manhole PMRF desires?

A56. Provide bid based on UFC 3-550-01 section 3-11.5.6 design standards in addition with complying with transportation rating. DB Contractor and his designer of record shall verify manhole configuration with NAVFAC Hawaii during design development.

Q57. For long power runs, is a handhole acceptable if no facilities are near for connection?

A57. Provide manholes with manhole spacing as required in UFC 3-550-01 section 3- 11.6.

Q58. UFC 3-550-01 section 3-11.2.2 requires plastic spacers in ductbank, but they are not shown in detail. Are spacers required?

A58. Provide spacers as required to comply with referenced UFC.

Q59. UFC 3-550-01 requires fire proofing of cables in manhole. Is this required?

A59. Provide fire proofing for cables in manholes as required to comply with referenced

UFC.

Q60. Can information on power factor correction be provided for sizing of capacitor and step settings? Is there any worry about inrush of capacitance because of the change to more underground feeder?

A60. DB Contractor and his designer of record shall provide power factor correction calculations and capacitor bank sizing as part of the DB Contract documents. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q61. Will rebar cages for manhole crossings be required?

A61. Prescriptive Specification UFGS Section 33 71 02 requires rebar for electrical ductbank crossing under roadways and is the DB Contractor’s designer of record responsibility to prepare. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements.

Q62. Confirm what scope KIUC will provide for demolition of existing utility poles and cables

A62. DB Contractor and his designer of record shall coordinate with KIUC regarding specific requirements for demolition of existing KIUC poles and equipment.

Q63. Please confirm that handholes will be acceptable means for straight through pull points.

A63. See response to RFI #57.

Q64. Are there specific areas of the base that will require temp power during construction and tie-in to utility outages?

A64. Yes, certain areas will require temporary power. DB Contractor and his designer of record shall coordinate specific temporary power requirements, scheduling and duration with the government DM and in accordance with specification section 01 14

00.05 20 – 1.3.5.1

Q65. Please provide an overall expected construction duration and completion date.

A65. See Document 00700 FAR clause 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

Q66. Please confirm precast handholes & manholes are acceptable.

A66. See NAVFAC Hawaii design standard section 3.2.12.4. DB Contractor and his designer of record shall confirm acceptable manhole materials, construction and configuration as part of the DB document preparation.

Q67. How much water per day can be used from the existing water system?

A67. The successful Contractor will be allowed to use water from the PMRF system. A water meter to record usage will be installed, at the Contractor’s expense. The exact amount of water the Contractor can utilize per day has not been calculated. If for any reason PMRF is placed on water use restriction, the Contractor will need to provide the water required for the project from an outside source.

Q68. Will there be an area to stockpile and screen rock out of the dirt?

A68. See DB RFP Section 01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS

Q69. Can excess spoils be spread on site or do will be required to be hauled offsite?

A69. See DB RFP Section 01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS

Q70. Please provide profiles for the duct bank. In particular, we would like to see where and how the duct bank will be routed over or under existing utilities where the two cross each other.

A70. DB Contractor and his designer of record shall provide ductbank plan and profile details as part of the DB contract documents. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q71. Please provide us with details for the concrete transformer and switchgear pads.

A71. DB Contractor and his designer of record shall provide equipment pad details as part of the DB contract documents. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q72. We understand that there is at least one location where the duct bank is to be installed under the road via a bored casing. Please provide the boring requirements, including the diameters of the bored hole and casing and any grouting requirements.

A72. DB Contractor and his designer of record shall provide boring details and requirements as part of the DB contract documents and in accordance with the DB RFP references. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q73. Please provide prescriptive specifications.

A73. DB Contractor and his designer of record shall provide all required specifications as part of the DB contract documents. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q74. Please confirm unforeseen site conditions is not in scope of work for contractor.

A74. As referenced in DB RFP Parts 2 and 3, unforeseen site conditions may arise during design and construction. The DB Contractor and his designer of record shall anticipate unforeseen conditions.

Q75. Please confirm fiber wiring requirements or if a prescriptive telecommunication cabling specification will be made available.

A75. Fiber wiring requirements and specifications shall be provided by the DB contractor and his designer of record during design development. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q76. Please provide utility fault current calculations and X/R ratios for the incoming services.

A76. Requested information will be provided to the DB contractor and his designer of record after contract is awarded. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q77. Please provide existing load calculations that will be required to tie into new underground circuits.

A77. There is no current information available.

Q78. Please provide existing short circuit analysis and protective coordination study for affected electrical systems.

A78. There is no current information available.

Q79. Although Part 3 Chapter 1 states, “The drawings provided in Part 6 of the RFP documents indicate the work required”, this statement seems to apply to attachments 1 to 3, with other background information given in attachments 4 to 9 . Please verify that the work shown in Part 6 attachment 4 Reference Drawings for “Replace Switchgear Bldg 112 Main Base Power Plant, PMRF” was completed and are now existing construction and the drawings were furnished for coordination purposes, but that is not in the scope of work of the PMRF Power Grid Consolidation at the Pacific Missile Range Facility.

A79. The work shown in Part 6 attachment 4 Reference Drawings for “Replace Switchgear Bldg 112 Main Base Power Plant, PMRF” has been completed and is now existing construction. The drawings are provided for coordination purposes and are not required scope of work for this contract.

Q80. What are the limitations in time to cutover the existing electrical services to new?

A80. See DB RFP 01 14 00.05 20 - WORK RESTRICTIONS FOR DESIGN-BUILD and DB RFP Part 3 section 2.5. DB contractor shall coordinate limits on main power outages with the government during design and construction.

Q81. Are there going to be limits on the main power outages?

A81. See DB RFP 01 14 00.05 20 - WORK RESTRICTIONS FOR DESIGN-BUILD and DB RFP Part 3 section 2.5. DB contractor shall coordinate limits on main power outages with the government during design and construction.

Q82. Currently the access on this road is limited to 34 tons by the bridge limitations on Highway 50. There is a limited river crossing that is upstream. Much of the equipment and materials needed for this project will be excess of 34 tons. Will it be allowed that we can pour in place the new man holes?

A82. See NAVFAC Hawaii design standard section 3.2.12.4. DB Contractor and his designer of record shall confirm acceptable manhole materials, construction and configuration as part of the DB document preparation.

Q83. What limitations of work hours and work days within any work week will their be on this project?

A83. See DB RFP 01 14 00.05 20 - WORK RESTRICTIONS FOR DESIGN-BUILD

Q84. Is sloping of the conduit banks to drain water required?

A85. Sloping of the conduit ductbanks for water drainage is not indicated in the DB RFB or referenced design documents and is not required.

Q85. How many of the pairs of fiber will be required to be spliced in the existing control building?

A86. DB Contractor and his designer of record shall determine fiber optic cable quantities and requirements as part of the DB document design process. Refer to Section SECTION 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES for General Design Requirements

Q87. Per PART 3 Section 1: "The drawings shall be considered as project requirements to be verified with NAVFAC Hawaii personnel during design build process." Previously in the section it is stated "that this is a design build contract."

Please explain what is meant by "the drawings shall be considered as project requirements to be verified by NAVFAC Hawaii personnel during the design build process"?

A87. The drawings and RFP documents are intended to show the overall schematic level scope of work including but not limited to; suggested equipment locations, suggested duct bank routing, and identification of some of the more salient complexities like ditch crossings and utility interconnection points. The DB Contractor and his designer of record are required to provide fully developed, complete construction documents and are expected to coordinate final project requirements with KIUC and NAVFAC HI during the design process.

Q88. Is the drawing SK-E602 to be adhered to exactly, or does it convey design intent that can be adapted by the design-build contractor?

A88. Drawing SK-E602 is intended to convey design intent and functionality that can be adapted by the DB Contractor and his designer of record. Equipment features functionality, and materials shall comply with the DB-RFP documents.

Q89. May the ductbank routing alignment be adjusted in the design-build process?

Note 3 on SK E-101 to E-113 indicates rerouting to avoid obstructions. Is contractor rerouting allowed that meets the intent of the design?

A89. Yes, the ductbank routing alignment may be adjusted in the design build process in close collaboration with NAVFAC HI and base activities.

Q90. Per SK-E602 conduit and cable schedule, some cables are listed as having both a neutral and ground 15kV conductor. Please verify both are required.

A90. Existing PMRF drawings show incoming KIUC feeders as 12.47KV, 4-wire.

Provide bid based on feeder schedule as shown on RFP documents.

Q91. Drawing SK E-106, Note 8 indicates Option 4 (CLIN 0005) description of converting the overhead lines to underground ductbank from Majors Bay to the Beach Cottages. Please provide a sketch of the work required. In particular, what are the power and equipment requirements at the connection to each cottage? Please provide details. What size and where are the existing transformers located and how are they fed?

A91. Specific requirements for the OH to UG conversion as described should be provided as part of the DB Contractor scope of work.

Q92. Drawing SK E-112, Note 8 indicates Option 4 (CLIN 0005) description of converting the overhead lines to underground ductbank WWVH road. How far is the ductbank to be routed on this road and what facilities are connected? Please provide a sketch of the work required. In particular, what are the power and equipment requirements at the connection to each facility? Please provide details. What size and where are the existing transformers located and how are they fed?

A92. Specific requirements for the OH to UG conversion as described should be provided as part of the DB Contractor scope of work.

Q93. Please clarify the requirements below. Does the value of $10 million need to be solely (or primarily) electrical work or can the projects also contain significant portions of general construction in addition to electrical portions of work that meet the scope of work of this proposed project?

Submit a minimum of one (1) and a maximum of three (3) relevant construction projects in which the Offeror was the Prime Contractor that best demonstrates the Offeror’s experience or relevant projects that are similar in size, scope, and complexity to the Request for Proposal (RFP). The Offeror must have been a Prime Contractor for the projects and each project shall be $10M or more in dollar value and be completed within the past ten (10) years of the date of issuance of this RFP. For purposes of this evaluation, a relevant project is further defined as work which includes underground electrical distribution systems. Offeror must demonstrate experience with replacing existing medium voltage electrical distribution systems which service multiple facilities.

A93. Please follow the RFP.

Q94. In Section 00110, Paragraph 2.2 (Page 5 of 15), it is stated that Attachment A shall be written in a minimum of Arial 11-point. However, the text that is on the provided Attachment A is all in Times New Roman. In light of this, may we provide our answers in a minimum of 11-point, Times New Roman?

A94. Yes.

No. PRINTED NAME COMPANY NAME

1 Alshukri, Zaid T-Makki Nan, Inc

2 Bothof, John Burns & McDonnell

3 Buchholz, Kevin Rosendin Electric, Inc.

4 Chun, Ryan Rosendin Electric, Inc.

5 Fischer, Brian Hensel Phelps Construction Co.

6 Gay, Charles Nova Group

7 King, Robert Niking Corporation

8 Lindley, James Helix Electric, Inc.

9 Miyasaki, Steve Nan, Inc

10 Shaw, Kevin Nova Group

11 Stoddard, Kristina Louis Berger Power

12 Techmanski, Andrew Whitefish Energy Holdings, LLC

13 Telthorst, Scott Helix Electric, Inc.

14 Tomomitsu, Harold TOMCO Corp.

15 Tyker, Clark TOMCO Corp.

16 Uyehara, Jon Henkels and MCCoy Inc

17 Venezia, Michael Hensel Phelps Construction Co.

18 Nonaka, Christine NAVFAC Hawaii

19 Sano, Derrick NAVFAC Hawaii

20 Takamine, Jan NAVFAC Hawaii

21 Morita, Lynne NAVFAC Hawaii

22 Nakashima, Kris NAVFAC Hawaii

PROPOSAL DUE DATE: 5/30/18 TIME: 2:00 PM, HST

SITE VISIT ATTENDEE LIST

SOLICITATION/CONTRACT/TASK ORDER NO. N62478-18-R-4035

PROJECT TITLE: FY16 MCON PROJECT P-416 ENERGY – PMRF POWER GRID CONSOLIDATION

AT THE PACIFIC MISSILE RANGE FACILITY, KEKAHA, KAUAI, HAWAII

AREAS TO BE VISITED: PMRF SITE VISIT DATE: 5/9/18 TIME: 1000 AM, HST

DOCUMENT 00900

APPENDIX E

Amendment 0003

Amendment 0003
Document 00900 Appendix D
Document 00900 Appendix E