This document contains questions and answers regarding a solicitation for multi-discipline architect-engineer services. The solicitation seeks an indefinite delivery/indefinite quantity contract to provide renovation, repair, or new construction design services for facilities under the Naval Facilities Engineering Systems Command Southwest. Services include preparation of design-bid-build construction packages, design-build packages, cost estimates, studies, and technical reviews. Project types may include facilities such as commercial, institutional, industrial, operational, training, research and development, medical, and quality of life structures. The contract will support installations in Arizona, California, Colorado, Nevada, New Mexico, Utah, and other approved locations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS & ANSWERS
February 4, 2021
Synopsis: N62473-21-R-1018 Synopsis Issuance Date: January 6, 2021 CS/Email: Eley DeCuba, eley.decuba@navy.mil
Subject: MULTI-DISCIPLINE ARCHITECT-ENGINEER SERVICES INDEFINITE
DELIVERY/INDEFINITE QUANTITY CONTRACT, UNRESTRICTED, FOR
RENOVATION/REPAIR OR NEW CONSTRUCTION OF FACILITIES AT
SUPPORTED INSTALLATIONS UNDER NAVAL FACILITIES ENGINEERING
SYTEMS COMMAND SOUTHWEST AREA OF RESPONSIBILITY IN ARIZONA,
CALIFORNIA, COLORADO, NEVADA, NEW MEXICO, UTAH, AND AS
OTHERWISE APPROVED.
Question 26: The RFP requires the Program Manager, Design Quality Control Manager (DQCM) and
Project (Task Order) Managers be Registered Architects. Since this IDIQ is to support multi-discipline AE services for a variety of facility types, and considering the expected Program Manager responsibilities please allow that the Program Manager to be a Registered Architect or a Registered/Professional Engineer
Answer 26: As stated in the Synopsis, the Program Manager shall be a professionally registered Architect and be an employee of the prime A-E firm.
Question 27: Under Criterion 2, the RFQ indicates, “All projects provided in the SF330 must be completed by the actual office/branch/regional office/individual team member proposed to manage and perform work under this contract…” Please confirm that a project completed by a team member that is proposed as a key subconsultant will be evaluated and given the same consideration.
Answer 27: Confirmed.
Question 28: Is a Veterans Administration facility considered a military installation as it supports military programs.
Answer 28: A Veterans Administration facility is not considered a Navy, Marine Corps, or Air Force military installation in regards to this Synopsis. Please reference response to RFI #8 for more information.
Question 29: The SF330 Part I Form Block 7 requires us to include our office fax number. If we don’t have a fax number for that office, is it acceptable to put “N/A” in that block?
Answer 29: Yes, it is acceptable to put "N/A" in Block 7 if your office does not have a fax number.