This document contains a pre-solicitation notice and related planned task order for an indefinite delivery indefinite quantity job order contract under NAICS code 236220 for commercial and institutional building construction. The contract will have a base period of two years with one three-year option period for a total potential duration of five years. The task orders will range from $2,000 to $1,000,000 for construction projects such as administration buildings, training facilities, fire stations, laboratories, and other similar facilities at government installations in the Fallon, Nevada area under the Naval Facilities Engineering Command Southwest. The total estimated maximum value is $25 million. The solicitation will be posted on September 25, 2018 with proposals due on or around December 20, 2018 and award based on evaluation of ability to manage projects, experience, past performance, safety, and price related to the sample task order. The acquisition is set aside for small businesses with a size standard of $36.5 million.

View the file

Other files

File Type Posted
N62473-18-R-2284.pdf PDF
COMBINED_JOC_RFP_EXHIBITS.pdf PDF
EXHIBIT_I_Wage_Determinations.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE‐PRICED ITEM DESCRIPTION MEANS ITEM # QTY # QTY UNIT

MATERIAL (MATL)

UNIT COST MATL TOTAL COST LABOR UNIT COST LABOR TOTAL COST

EQUIPMENT (EQUIP)

UNIT COST EQUIP TOTAL COST OTHER COST

OTHER TOTAL

COST

Selective demolition, rubbish handling, dumpster, 40 C.Y., 10 ton capacity, weekly rental, includes one dump per week, cost to be added to demolition cost 024119190840 4 Week Selective demolition, rubbish handling, 0'-100' haul, load, haul, dump and return, wheeled, cost to be added to demolition cost 024119192045 80 C.Y.

Deconstruction material handling, light fixtures for recycling stack and wrap per pallet 024210300350 4 Ea.

Hazardous waste cleanup/pickup/disposal, transportation to disposal site, truckload = 80 drums or 25 C.Y. or 18 tons, maximum 028120101270 35 Mile Bulk asbestos removal, remove cementitious material from flat surface, includes disposable tools & 2 suits & 1 respirator filter/day/worker 028213433000 75 S.F.

Doors, specialty, access, standard, stainless steel, 24" x 24 083113106650 1 Ea.

Flooring demolition, resilient, sheet goods 090505200800 305 S.F.

Vinyl or rubber cove base, for glued and caulked installation, add to labo 090505200800 1 Flooring demolition, vinyl or rubber cove base, straight section 090505200850 87 L.F.

Vinyl or rubber cove base, for glued and caulked installation, add to labo 090505200850 1 Flooring demolition, vinyl or rubber cove base, molded corner 090505200860 4 Ea.

Vinyl or rubber cove base, for glued and caulked installation, add to labo 090505200860 1 Walls and partitions demolition, tile, ceramic, on walls, thin set 090505303760 437 S.F.

Gypsum wallboard, on walls, water resistant, taped & finished (level 4 finish), 5/8" thick 092910302250 437 S.F.

Gypsum wallboard, for finishing corners, inside, add 092910305350 36 L.F.

Wall base, rubber, straight or cove, standard colors, 6" high, 1/8" thick 096513131110 87 L.F.

Surface preparation, interior, walls, sand, gypsum board and plaster, medium 099103400670 786 S.F.

Painting walls, complete, on drywall or plaster, primer and 2 finish coats, with roller, including surface preparation 099123721670 786 S.F.

Wall coating, epoxy coatings, Water based 099656200400 786 S.F.

Toilet accessories, soap dispenser, chrome, surface mounted, liquid 102813134600 2 Ea.

Toilet accessories, towel dispenser, stainless steel, surface mounted 102813136700 2 Ea.

Dental equipment, chair, electric or hydraulic, selective demolition 110505107400 6 Ea.

Selective demolition, casework, metal base cabinets 120505103100 25 L.F.

Selective demolition, countertop, stainless steel or acid proo 120505103120 25 L.F.

Laboratory casework, wall cabinets, metal, open, 12-1/2" deep 123553131300 10 L.F.

Laboratory casework, wall cabinets, with doors, 12" x 31 123553131500 25 L.F.

Casework, base cabinets, hospital, stainless stee 123570131000 25 L.F.

Laboratory casework, counter tops, stainless steel, excl. base cabinet 123653100040 25 S.F.

Sprinkler system component, sprinkler heads, dry, pendent, 1/2" orifice, 3/4" or 1" NPT, 39-1/4" to 42" length, excludes supply piping 211316502790 5 Ea.

Fixture, sink, single compartment, selective demolition 220505101300 2 Ea.

Faucets/fittings, medical, faucet, gooseneck spout, wrist handles, grid drain 224339102900 2 Ea.

Faucets/fittings, medical, mixing valve, knee action, screwdriver stops 224339102940 1 Ea.

Industrial safety fixture, eyewash station, stainless steel, pedestal mounted, excludes rough-in 224516102000 1 Ea.

Ductwork, metal; steel and stainless steel, fabricated, selective demolition 230505101570 100 Lb.

Exhaust system, weld fume hood, selective demolition 230505101770 2 Ea.

Balancing, air conditioning equipment, supply, return, exhaust, registers and diffusers, laboratory fume hood, (Subcontractor's quote including material & labor) 230593103600 1 Ea.

Metal ductwork, fabricated rectangular, galvanized steel, 200 to 500 lb., incl fittings, joints, supports & allow for a flexible connections field sketches, excludes as-built drawings and insulation 233113130520 100 Lb.

Metal ductwork, elevated installation of prefabricated (purchased) ductwork, 10'

to 15' high, add to labor 233113130520 1 Fluorescent fixtures, interior, 2 lamp, 2' x 4', electrical demolition, remove, recessed drop-in, to 15' high, including supports & whips 260505102120 4 Ea.

Outlet boxes, cast, switch cover, 1 gang, FS 260533161510 20 Ea.

Interior LED fixtures, troffer, recess mounted, 6,400 lumens, 2' x 4', replaces four T8 lamp, incl lamps, mounting hardware and connections 265113551020 4 Ea.

TOTALS ‐$ ‐$ ‐$

NON PRE‐PRICED ITEM DESCRIPTION QTY # QTY UNIT

MATERIAL (MATL)

UNIT COST MATL TOTAL COST LABOR UNIT COST LABOR TOTAL COST

EQUIPMENT (EQUIP)

UNIT COST EQUIP TOTAL COST OTHER COST

OTHER TOTAL

COST

OFFICE SYSTEMS FURNITURE 1 LS $ 20,000.00 $ 20,000.00

PREPRICED LINE TOTALS (MATERIALS + LABOR + EQUIPMENT + OTHER

CITY COST INDEX _____ (____________ WEIGHTED AVERAGE)_

SUBTOTAL (PREPRICED LINE TOTALS + CCI)

APPLICABLE SALES TAX ON MATERIALS AND EQUIPMENT _________

SUBTOTAL (PREPRICED LINE ITEMS + CCI + SALES TAX)

PRE‐PRICED COEFFICIENT _______ (FROM EXHIBIT K WORKSHEET)

TOTAL (PRE‐PRICED LINE ITEMS + CCI + SALES TAX, LINE 52) + PRE‐PRICED

COEFFICIENT ADUSTMENT (LINE 52 x LINE 53)

NON PRE‐PRICED LINE TOTALS (MATERIALS + LABOR + EQUIPMENT + OTHER

APPLICABLE SALES TAX ON MATERIALS AND EQUIPMENT __________

SUBTOTAL

NON PRE‐PRICED COEFFICIENT _____ (FROM EXHIBIT K WORKSHEET)

TOTAL (NON PRE‐PRICED LINE ITEMS + SALES TAX, LINE 58) + NON PRE‐PRICED

COEFFICIENT ADJUSTMENT (LINE 58 x LINE 59)

TOTAL TASK ORDER PRICE (LINE 54 + LINE 60)

NOTE: USE OF THIS FORM IS

MANDATORY. ANY MODIFICATION

OF THIS FORM BY THE OFFEROR WILL

RESULT IN THE OFFER BEING

REJECTED AS NON‐RESPONSIVE.