Section H - Special Contract Requirements Summary

This document is Section H of a federal construction contract, establishing special contract requirements for Department of War (DoW) facilities in the Mediterranean area. The section contains 25 subsections addressing comprehensive operational, safety, environmental, and administrative requirements applicable to prime contractors and subcontractors performing work at military installations in Greece.

Key operational requirements include quality control procedures with mandatory contractor QC plans, QC manager involvement, and three-phase inspection processes (preparatory, initial, and follow-up). The contractor must maintain personnel contact lists, obtain identification badges, comply with base access procedures differentiated by Greek citizen, EU citizen, and non-EU national status (requiring documentation submissions 45 days prior for new personnel and 30 days for renewals). Safety obligations are extensive, encompassing compliance with USACE EM 385-1-1 standards, monthly safety self-evaluation checklists scoring minimum 90 percent, accident reporting within four hours for recordable injuries or property damage exceeding $2,000, weight handling equipment certificates of compliance, fall protection programs, confined space entry procedures, and hot work permits. Environmental responsibilities include hazardous material screening (prohibiting asbestos, lead-based paint, PCBs, and other specified substances requiring minimum 10 working days approval), archaeological site protection with mandatory work stoppage upon discovery, and waste disposal compliance. Additional requirements address utilities verification prior to excavation using private locating services and hand digging within two feet of known utilities, electrical safety per UFC 3-560-01, water supply systems compliance with Navy drinking water standards, building access coordination, contractor vehicle identification, and underground utility location surveys. The contractor bears costs for quality control management, final cleanup, keys replacement if lost, and all hazardous material disposal.

View the file

Other files

File Type Posted
Souda Bay JOC Statement of Work.pdf PDF
Solicitation - N6247026R0041.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section H - Special Contract Requirements

TABLE OF CONTENTS

PARAGRAPH TITLE

H.1 DEFINITIONS

H.2 DIRECTIVES

H.3 UFGS 00 73 04 SUPPLEMENTARY CONDITIONS FOR PROJECTS IF

MEDITERRANEAN AREA

H.4 INSTALLATION REGULATIONS

H.5 BASE ACCESS REQUIREMENTS

H.6 QUALITY CONTROL

H.7 FIRE PREVENTION

H.8 ENERGY & WATER CONSERVATION

H.9 ENVIRONMENTAL PROTECTION

H.10 DISPOSITION OF WASTE MATERIAL

H.11 HEALTH AND SAFETY

H.12 ACCESS TO BUILDINGS

H.13 UNDERGROUND UTILITIES

H.14 IDENTIFICATION OF CONTRACTOR VEHICLES

H.15 PERMITS

H.16 EQUIPMENT WARRANTY TAG

H.17 RECORDING AND PRESERVING HISTORICAL AND

ARCHEOLOGICAL FINDS

H.18 CONDUCTING CONTRACT BUSINESS

H.19 FINAL CLEAN UP COSTS

H.20 ELEVATORS

H.21 PHOTOGRAPHY

H.22 TEMPORARY FACILITIES AFD CONTROLS

H.23 DISCLOSURE OF INFORMATION

H.24 CONTRACTOR USE OF RADIOACTIVE MATERIAL

H.25 NOTICE TO CONTRACTOR OF DRUG DETECTION

H.1 DEFINITIONS

As used throughout the contract, the following terms shall have the meaning set forth below:

Contracting Officer (KO): The individual designated to administer the contract. Throughout this contract this individual will be responsible and possess the authority to act on behalf of the Government with respect to the specific contract.

Contracting Officer Representative (COR): The individual designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature.

Contractor (KTR): The term Contractor refers to both the prime Contractor and subcontractors, including the Designer of Record.

Designer of Record (DOR): Individual working as a subcontractor to or partner with prime Contractor who provides drawings/designs for this contract.

Quality Control (QC): Contractor’s system to control the quality of design, material, equipment and construction.

Quality Assurance (QA) Program: Government’s program to evaluate the effectiveness of the Contractor’s quality control. The Government’s QA Program is not a substitute for the Contractor’s QC Program.

Federal Holidays: New Year’s Day, Martin Luther King Jr. Day, President’s Day, Memorial Day, Independence Day; Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.

Contract: Contract or task order.

Certified Construction Health & Safety Technician (CHST): An individual who is currently certified as a CHST by the Board of Certified Safety Professionals.

Certified Industrial Hygienist (CIH): An individual who is currently certified as a CIH by the American Board of Industrial Hygiene.

Certified Safety Professional (CSP): An individual who is currently certified as a CSP by the Board of Certified Safety Professionals.

Certified Safety Trained Supervisor (STS): An individual who is currently certified as an STS by the Board of Certified Safety Professionals.

Competent Person: A person who is capable of identifying or predicting hazards or hazardous conditions and has the authority to take prompt corrective measures to eliminate them. The competent person assists writing the AHA and signs it if the phase of work requires a particular competent person (e.g., fall protection, excavation/trenching, scaffolding).

Competent Person for Fall Protection: A person designated in writing by the employer to be responsible for the immediate supervision, implementation and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating, and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

Qualified Person: One who, by possession of a recognized degree, certificate, or professional standing and has extensive knowledge, training, and experience and has successfully demonstrated his/her ability to solve or resolve problems related to the subject matter, work, or the project.

High Visibility Accident: Any mishap which may generate publicity and/or high visibility.

Medical Treatment: Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

Operating Envelope: The area surrounding any crane. Inside this "envelope" is the crane, the operator, riggers and crane walkers, rigging gear between the hook and the load, the load and the crane's supporting structure (ground, rail, etc.).

Qualified Person for Fall Protection: A person with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, evaluating and specifying fall protection and rescue systems.

Excavation Work: Digging, saw-cutting, or core drilling of all vertical and horizontal surfaces to include building interiors.

H.2 DIRECTIVES

The contractor shall be knowledgeable of all applicable Department of War (DoW) Secretary of the Navy (SECNAV), Chief of Naval operations (OPNAV), Naval Engineering Command (NAVFAC), and all other directives and instructions as cited in Section J.

The Contractor shall become acquainted with the applicable sections of the regulations and other publications set forth herein. The Contractor is only obligated to follow those coded as mandatory and only to the extent stated in this specification when a specific part of this document is referenced herein.

The Contractor and all employees of the Contractor shall be acquainted with and obey all Government and Installation regulations as posted, or as requested by the Contracting Officer and or a designated representative.

Government and Installation regulations become binding on the contractor upon posting or issuance by Contracting Officer and/or a designated representative.

H.3 SUPPLEMENTARY CONDITIONS FOR PROJECTS IN MEDITERRANEAN AREA

DOCUMENT 00 73 04

SUPPLEMENTARY CONDITIONS FOR PROJECTS IF MEDITERRANEAN AREA

08/08

PART 1 GENERAL

PUBLIC RELEASE OF INFORMATION

Prohibition

There shall be no public release of information or photographs concerning any aspect of the materials or services relating to this bid, contract, or purchase order or other documents resulting therefrom without the prior written approval of the Contracting Officer.

Subcontracts and Purchase Orders

The Contractor agrees to insert the substance of above paragraph "Prohibition" in each subcontract and purchase order generated for this contract.

ENGLISH SPEAKING REPRESENTATIVE

At all times when any performance of the work at the site is being conducted by any employee of the Contractor or his subcontractors, the Contractor shall have a representative present on the site who is capable of explaining the work operations and receiving instructions in the English language. The Contracting Officer shall have the right to determine without appeal of such decision, whether the proposed representative has sufficient technical and lingual capabilities and the Contractor shall immediately replace any individual not acceptable to the Contracting Officer.

The Construction Contractor's qualified Project Manager, on-site Superintendent, Quality Control Manager, and Quality Control Specialist shall be fluent (can read, speak, and write) in English.

NORMS AND LAWS

In case of differences between project specifications or the accompanying drawings and referenced norms and laws, norms and laws shall govern. In case of differences between project specifications and the accompanying drawings, the specifications shall govern.

INDUSTRY STANDARDS

When both U.S. and European, or Greek Industry Standards are applicable to this project and the standards are in conflict with each other, the most stringent of the industry shall govern.

PROHIBITED ITEMS

Use of the following items in this construction project is prohibited:

a. Use of aluminum for electrical conductors.

b. Embedding aluminum conduit in concrete.

c. Use of fluorescent light ballasts and other products containing PCB's.

d. Use of urea-formaldehyde foam insulation products.

e. Use of any paint/coatings having a lead content of over 0.06 percent by weight of non-volatile content. The use of ozone depleting chemicals is prohibited. The use of zinc-chromate is prohibited.

f. The use of materials containing asbestos is prohibited.

PROPRIETARY NAMES

Manufacturer's proprietary names indicated for colors, textures and patterns of materials are for the purpose of color, texture and pattern selection only. Other manufacturers’ materials are acceptable and provided they closely approximate colors, textures and patterns indicated and provided they conform to all other requirements subject to Contracting Officer's approval.

SUBMITTAL OF PROOF OF QUALIFICATIONS AND EXPERIENCE

Where qualifications or experience requirements are set forth in the specifications with respect to equipment and equipment installers, written proof of such qualifications or experience must be provided within thirty (30) calendar days after Contract award, and before placing any order for such equipment or before dispatching equipment installers to the project site.

ORAL MODIFICATION

No oral statement of any person other than the Contracting Officer as provided in the clause in this Contract entitled FAR 52.243-4 "Changes" (AUG 1987), shall in any manner or degree modify or otherwise affect the terms of this Contract.

NO WAIVER BY GOVERNMENT

The failure of the Government, in any one or more instances, to insist upon the strict performance of any of the terms of this Contract or to exercise any option herein conferred shall not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.

FINAL GOVERNING STANDARDS (FGS)

Final Governing Standards (FGS) for environmental protection at DoW installations and facilities in Greece went into effect June 1994. These standards were developed by comparing and adopting the more protective requirements of the Overseas Environmental Baseline Guidance Document (OEBGD), European Union and national, regional, and local environmental laws and regulations. The FGS are applicable to work under this contract. The FGS (both English and local language versions) may be reviewed at the PWD Office during normal business hours.

H.4 INSTALLATION REGULATIONS

H.4.1. Contract Personnel

The Contractor shall furnish a list of contact personnel for the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

H.4.2. Identification Badges

Identification badges, if required, will be furnished based on the individual installation security procedures. The application for and use of badges will be as directed. Contactor is responsible for all costs associated with obtaining proper credentials. Contractor shall immediately report instances of lost or stolen badges to the Contracting Officer. All Contractor and subcontractor personnel shall be required to possess and wear identification badges at all times when working within the confines of the individual military bases or other job site location under this contract.

H.4.3 Contractor Personnel Requirements

Failure to obtain entry approval will not affect the contract price or time of completion. All Contractor personnel shall become familiar with and obey all Government regulations including fire, traffic, and security regulations. Refer to individual Task Order or Installation requirements provided at the preconstruction conference.

H.5 BASE ACCESS REQUIREMENTS

Base Access procedures are stated in OPNAVINST 5530.14 and NAVSUPPACTSOUDABAYINST

5512.1. The Contractor shall submit Base Access requests through PWD. The access requirements are subject to change at any time. The Contractor shall comply with the most recent DoW, Navy, and base access requirements as well as any supplemental documents related to base access requirements, as applicable. Any additional costs for changed requirements will not be reimbursed to the Contractor. The current requirements are below:

1. Greek Citizens

a. Documentation to include with Base Access Form

(1) Greek ID number

b. Documentation to bring when picking up Base Access Pass

(1) Greek ID

(2) Local police record check (must be the original and not a copy) conducted within the past 30 days. The police record check is valid for 6 months.

2. EU Citizens (Non-Greek)

(1) Legible, color copy of passport and EU ID card. EU citizens without a passport will be considered on a case by case basis.

b. Documentation to bring when picking up Base Access Pass

(1) Passport and EU ID card (must be the original and not a copy for passport and ID). One form of identification will be collected by Hellenic Air Force personnel at the Greek gate and returned upon exit. Second form of ID will serve as identification at the US gate. For personnel without a passport, they will need to provide another form of photo identification.

3. Non-EU Third Country Nationals

(1) Legible, color copy of passport and Greek residence card. Documentation must show at least two years of residency in Greece.

b. Documentation to bring when picking up Base Access Pass

(1) Passport and Greek residence card (must be the original and not a copy for passport and residence card). One form of identification will be collected by Hellenic Air Force personnel at the Greek gate and returned upon exit.

Second form of ID will serve as identification at the US gate.

4. The Contractor shall not include more than 15 names on each Base Access Request Form.

(Multiple forms may be submitted.)

5. On the 15th of each month, the Contractor shall provide their most current roster of personnel highlighting any names that need to be removed from the Base Access List.

6. Base Access Requests for Few Personnel (Personnel requiring access for the first time) need to be submitted 45 days prior to the day he/she needs access to the base (e.g. if the person is expected to start work at the beginning of May, the base access request needs to be submitted by 15 March).

7. Base Access Renewal Requests for Current Personnel (Those that have access currently) need to be submitted 30 days prior (e.g. if the person is expected to start work at the beginning of May, the base access request needs to be submitted by 01 April).

H.6 QUALITY CONTROL

The Quality Control (QC) program is a concerted effort of the Contractor and Government personnel to ensure that quality standards are met under contract terms. Quality Management consists of two parts:

Quality Control (QC), established and directed by the Contractor, and Quality Assurance (QA), the Government’s program to maximize project quality elements. The Contractor’s QC organization for each Task Order shall include a QC Manager and any QC Specialists that are specified in the Task Order RFP.

Costs for the QC Manager shall be included in the Contractor’s Coefficient.

The Contractor shall establish and maintain an inspection system in accordance with the FAR Clause 52.246-12, INSPECTION OF CONSTRUCTION, to ensure that the work performed conforms to the contract requirements.

H.6.1 QC Plan

Submit a QC plan for Government review and acceptance. Submittal requirements for this deliverable are posted in Section F – Deliveries or Performance.

The Contractor shall maintain a file of all scheduled and performed QC inspections, inspection results, and dates and details of corrective and preventive actions. The file shall be the property of the Government and made available during the Government’s regular working hours. The QC plan shall be submitted in a 3-ring binder with one electronic copy that covers the overarching QC procedures that are instituted for all Task Orders under this contract. The General QC plan shall include the following:

1) NAMES, QUALIFICATIONS and RESPONSIBILITIES: For each person in the QC organization (design and construction).

2) OUTSIDE ORGANIZATIONS: Outside organizations, including architectural and consulting engineering firms and a description of the services these firms will provide.

3) INITIAL SUBMITTAL REGISTER (DESIGN & CONSTRUCTION): Include submittal reviewer, estimated date of delivery, and identify which design submittals require Government approval prior to construction, and which construction submittals require DOR or Government approval prior to construction.

4) TESTING LABORATORIES: Accredited laboratories as applicable.

5) TESTING PLAN AND LOG: Tests required, referenced by specification paragraph number

Requiring the test, frequency, and person responsible for each test.

6) LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task, which is separate and distinct from other tasks, and has the same control requirements and work crews.

7) COMMUNICATION PLAN: Provide a plan for key decisions and possible problems the Contractor and Government may encounter during the design phase of the project.

Communication Plan shall indicate the frequency of design meetings and what information is covered in those meetings, key design decision points tied to the Network Analysis Schedule and how the DOR plans to include the Government in those decisions, peer review procedures, interdisciplinary coordination, design review procedures, and comment resolution.

H.6.2 QC Manager Responsibilities:

1. Participate in the Project Kick-off, Partnering, Coordination Meetings and Production Meetings.

2. Ensure that no construction begins before required submittals are approved. Submit Material

Safety Data Sheets (MSDS) to the Government as applicable. Immediately stop any work that does not comply with the Task Order scope of work, and direct the removal and replacement of any defective work.

3. Immediately stop any work that does not comply with contract plans and specifications, and direct the removal and replacement of any defective work.

4. Prepare QC Reports.

5. Prepare daily Contractor Production Reports.

6. Hold biweekly Task Order QC meetings with Superintendent and Government team;

participation shall be suitable for the phase of work.

7. Consult SSHO to ensure that safety inspections are performed.

8. Maintain submittal log.

9. Maintain updated as-built drawings on site.

10. Maintain testing plan and log (if required by Task Order). Ensure that all testing is performed per contract.

11. Maintain deficiency log on site, noting dates deficiency identified, and date corrected.

12. Certify and sign each invoice stating that all work to be paid under the invoice has been completed in accordance with contract requirements.

13. Perform Punch-out and Pre-final inspections and participate in Final Inspections. Establish list of deficiencies; correct prior to the Final inspection.

14. Ensure that all required keys, operation and maintenance manuals, and warranty certificates are submitted to the Contracting Officer.

QC Manager Uses the Three Phases of Control process for construction QC:

1. Preparatory Phase: Review all applicable documents for compliance with all applicable laws, codes, regulations, and the requirements of the contract, including contract drawings and specifications. Determine requirements for testing and certification. Review submittal approvals for materials, equipment, shop drawings, and applicable methods of construction and installation.

Include all Preparatory Phase items in the QC Report.

2. Initial Phase: Observe and inspect the initial portion of the work performed under a definable feature of work to establish the quality of the workmanship, resolve conflicts in construction, ensure that testing is done and certified as required, and to check all work procedures to ascertain the work is in conformance with required safety requirements. Record and report nonconforming work and work not of acceptable quality and requiring correction or rework. Include all Initial Phase items, along with initial phase checklist and, in the QC Report.

3. Follow-Up Phase: Occurs at the completion of each Definable Feature of Work (DFOW). Ensure the work is in compliance with contract requirements, quality of workmanship for all work is maintained, and all work performed meets safety requirements. Include all Follow-Up Phase items, including date, in the QC Report.

The QC Manager must possess a current certificate showing successful completion of the NAVFAC Contractor Quality Management (CQM) Training.

Contractor Daily Quality Control Report: Other requirements of this deliverable are posted in Section F - Deliveries or Performance. Contractor Quality Control Reports are to be prepared, signed and dated by the Project QC Manager and shall contain the following information:

1. Date of report, report number, contract number

2. Identify by Task Order number and project title where Preparatory Phase work was performed today.

3. Identify by Task Order number and project title where Initial Phase work was performed today.

4. Results of the Follow-up Phase inspections held today.

5. Include a “Remarks” section in this report which will contain pertinent information including direction received, quality control problem areas, deviations from the QC plan, construction deficiencies encountered, QC meetings held, and corrective action taken by the Contractor.

6. Contractor Quality Control Report certification, signature and date.

H.7 FIRE PREVENTION

The Contractor shall ensure that his employees shall know how to activate a fire alarm or otherwise notify the local Fire Department in the event of an emergency. The Contractor shall observe all requirements for handling and storage of combustible supplies, materials, waste and trash. Contractor employees shall be trained to properly respond to a fire alarm or fire in accordance with activity instructions.

H.8 ENERGY & WATER CONSERVATION

The Contractor shall participate actively in the activity’s energy & water conservation program. The Contractor shall comply with the base energy conservation program as defined in local base regulations.

Use of high energy consuming tools or equipment shall be approved by the Contracting Officer and/or a designated representative prior to use.

The Contractor shall observe the most recent version of the Energy and Water Management Program, NAVSUPPACTSOUDABAYINST 4100.1G. It is mandatory that the Contractor obtain a copy of this instruction and post it in a conspicuous location for the Contractor's employees to read. Copies of the instructions are available from the PWD office. Ensure that employees comply with these regulations at all times. It is suggested that an employee be appointed as energy monitor by the Contractor for buildings under the jurisdiction of the Contractor.

H.9 ENVIRONMENTAL PROTECTION

The Contractor shall provide and maintain, during the life of the contract, environmental protection as defined herein and on individual Task Order(s). Plan for and provide environmental protective measures to control pollution that develops during normal construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with U.S., Host Nation, DoW, USN, and installation regulations and requirements pertaining to the environment, including but not limited to water, land, air, and noise pollution.

The Contractor is responsible for understanding and properly performing all requirements under federal, state, and local environmental laws, regulations and ordinances that are applicable to the work being performed under this contract. This responsibility extends to securing all permits required by such laws, regulations, and ordinances.

The Contractor is responsible for advising its agents, employees, subcontractors, and other personnel who will perform operations, activities, or services under this contract of these requirements.

The Contractor is responsible for the following:

1. Notifying the Government promptly upon receipt of regulatory notices, orders, or requests for information, and promptly supplying copies to the Government.

2. Complying with environmental regulatory notices or orders to the extent attributable to the Contractor.

3. Correcting conditions of environmental noncompliance identified by the Government in the absence of regulatory non-compliance notices. This includes cleaning up any contamination released from Contractor operations, whether such contamination is on or off Government property.

4. The Contractor is responsible, upon Government request, for providing the Government and/or any regulatory agency with any information that may be required regarding the actual or potential. environmental impacts of Contractor’s operations. The information shall be timely and complete and in a form acceptable to the Government and/or the regulatory agency.

5. Soil disturbance in known or suspected contaminated or otherwise environmentally regulated sites will only be permitted after approval of an Environmental Plan.

H.9.1 Archeological Sites

The Request for Proposal for individual Task Order will identify when work shall be conducted on properties that are designated as historic places or areas of sensitive archeological or protected nature. The Contractor shall understand and comply with all applicable protection standards for such sites.

Comply with installation Natural and Cultural Resources Management User's Guide and/or Installation Natural Resources Management Plan and Cultural Resources Management Plan as applicable. If any construction work uncovers any cultural resource or potential cultural resource, the Contractor must stop that work and notify the KO immediately. Within 14 days the Government will coordinate with local authorities to determine how to proceed. If the resource is determined to be not of exploitable archaeological value, the Government will direct the Contractor to proceed without change. If the resource is determined to be of exploitable archaeological value, the Government will make a determination regarding how to proceed and notify the Contractor of impact to project via Task Order modification pursuant to FAR 52.243-4, Changes, or FAR 52.236-2, Differing Site Conditions.

H.9.2 Drinking water pipes

If the Contractor is required to work on any potable water pipes or appurtenances, the Contractor shall not use lead-based solder.

H.10 DISPOSITION OF WASTE MATERIAL

All debris, rubbish, hazardous waste, and non-usable material resulting from the work under this contract shall be disposed of by the contractor at his expense off Government property, as specified in section J, specification 01 74 19, "Construction Demolition and Waste Management". The Contractor shall make every effort to recycle, refer to specification section 01 62 35, “Recycled / Recovered Materials”.

H.10.1 Salvage

All non-usable surplus material and debris resulting from work under these specifications shall be removed from the site by the Contractor at their expense. The Government retains salvage rights to any material of archaeological or historical value as determined by the Contracting Officer.

The Contractor shall remove all material not claimed for salvage by the Government and disposed of off base bi-weekly or as specifically agreed to in a specific delivery order. The contractor shall dispose of hazardous waste in accordance with the Resource Conservation and Recovery Act and associated state and local regulations.

Except where indicated and/or specified otherwise in other sections, all material and equipment removed, but not reused, shall become the property of the Contractor and shall be removed from Government Property. Title to all material resulting from demolition, and all material and equipment to be removed, is vested to the Contractor upon approval by the Contracting Officer of the Contractor’s demolition and removal procedures, and authorization by the Contracting Officer to begin demolition. The Government will not be responsible for the condition or loss of, or damage to such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.

Salvaged Materials and Equipment: Carefully remove materials and equipment that are specified to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site, as directed.

H.10.2 Reuse of Material and Equipment

Carefully remove and store materials and equipment specified to be reused or relocated to prevent damage and reinstall as the work progresses.

H.10.3 Waste-Transporting Vehicles

All vehicles transporting waste and debris from the job site shall be suitable for the task, properly loaded, and covered to prevent spillage during transport.

H.11 HEALTH AND SAFETY

In addition to references and standards given in this section, the Contractor is responsible for understanding and complying with all Greece safety standards that govern work in the areas under any Task Order awarded. The publications listed below form a part of this contract to the extent referenced.

For the life of the contract, the publication versions that are current at the time of contract award will be used. The publications are referred to within the text by the basic designation only.

H.11.1 References

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z359.1, Safety Requirements for Personal Fall Arrest System, Subsystems and Components ANSI A10.32, Fall Protection Systems for Construction and Demolition Operations ANSI A10.6, Demolition Operations ANSI A10.34, Protection of the Public on or Adjacent to Construction Sites ANSI Z9.2, Fundamentals Governing the Design and Operation of Local Exhaust Systems ANSI Z88.2, Respiratory Protection ANSI Z358.1, Emergency Eyewash and Shower Equipment

AMERICAN WATER WORK ASSOCIATION

AWWA Standard C600 series, Testing Appendix C, Procedures for Pressure and Leakage Testing of Water Mains AWWA Standard C605, Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water

AWWA Standard C511, Reduce-Pressure Principle Backflow Prevention Assembly AWWA Standard C651, Disinfecting Water Mains AWWA Standard C652, Disinfection of Water-Storage Facilities AWWA Standard C653, Disinfection of Water Treatment Plants AWWA Standard C800, Underground Service Line Valves & Fittings AWWA Standard M14, Backflow Prevention and Cross-Connection Control

ASME INTERNATIONAL (ASME)

ASME B30.22, Articulating Boom Cranes ASME B30.3, Construction Tower Cranes ASME B30.5, Mobile and Locomotive Cranes ASME B30.8, Floating Cranes and Floating Derricks

AMERICAN SOCIETY OF TESTING AND MATERIALS (ASTM)

ASTM Standards on Lead-Based Paint Abatement in Buildings ASTM E 1368, Visual Inspection of Asbestos Abatement Projects

DEPARTMENT OF WAR (DoW) MIL-STD-1472F, Military Standard, Human Engineering Design Criteria for Military Systems, Equipment and Facilities DoW-HDBK 743A, Anthropometry of US Military Personnel

DEFENSE LOGISTICS AGENCY (DLA)

DLA 4145.25, Storage and Handling of Compressed Gases and Liquids in Cylinders

EPA Standards and Documents – General 15 U.S.C. 2601 – Toxic Substances Control Act EPA Title X – The Residential Lead Based Paint Hazard Reduction Act EPA & HUD – Lead Safe Work Practices HUD Guidelines, Guidelines for the Evaluation and Control of Lead Based Paint Hazards in Housing

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241, Safeguarding Construction, Alteration, and Demolition Operations NFPA 51B, Fire Prevention During Welding, Cutting, and Other Hot Work NFPA 70, National Electrical Code NFPA 70E, Electrical Safety in the Workplace

NAVFAC

NAVFAC P-307, Management of Weight Handling Equipment

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1, Safety -- Safety and Health Requirements

UNITED FACILITIES CRITERIA (UFC)

UFC 3-560-01, Electrical Safety, O&M UFC 3-230-01, Water Storage, Distribution, and Transmission

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910, Occupational Safety and Health Standards 29 CFR 1910.146, Permit-required Confined Spaces

29 CFR 1915, Occupational Safety and Health Standards for Shipyard Employment 29 CFR 1926, Safety and Health Regulations for Construction

H.11.2 Submittals

A "G" following a submittal indicates that Government approval action is required.

1) Contractor Accident Prevention Plan (APP), comply with EM 385-1-1, Appendix A; G

2) Contractor Safety Self-Evaluation Checklist; G

3) Monthly Work-Hour Reports

4) Crane Critical Lift Plan; G

5) Accident Reports – submit if incidence occurs.

6) Activity Hazard Analyses, as applicable

H.11.3 Weight Handling Equipment (WHE) Accident

A WHE accident occurs when any one or more of the six elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking; overload; or collision, including unplanned contact between the load, crane, or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents, even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over).

H.11.4 Contractor Safety Self-Evaluation Checklist

Contracting Officer will provide a "Contractor Safety Self-Evaluation checklist" to the Contractor at the pre-construction conference. Complete the checklist monthly and submit with each request for payment. A score of 90 or greater is required. Failure to submit the completed safety self-evaluation checklist or achieve a score of at least 90 will result in retention of up to ten (10) percent of the voucher.

H.11.5 Regulatory Requirements

In addition to the detailed requirements included in this contract, work performed shall comply with USACE EM 385-1-1, and the laws, ordinances, criteria, rules and regulations included in attachments of this Solicitation. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall apply. UFC 3-560-01 takes precedence over all other guidance for electrical safety.

H.11.6 Accident Notification and Reports

H.11.6.1 Recordable injuries and illnesses

For recordable injuries and illnesses, and property damage accidents resulting in at least $2,000 in damages, the Prime Contractor shall conduct an accident investigation to establish the root cause(s) of the accident, fill out the Contractor Incident Report (CIR) electronically and submit via the NAVFAC Enterprise Safety Applications Management System (ESAMS) within 5 calendar days of incident. The Contracting Officer will provide copies of any required or special forms.

H.11.6.2 Weight handling equipment accident (including rigging gear accidents)

The Prime Contractor shall conduct an accident investigation to establish the root cause(s) of the accident, complete the WHE Accident Report (Crane and Rigging Gear) form and provide the report to the Contracting Officer within 30 calendar days of the accident. Crane operations shall not proceed until cause is determined and corrective actions have been implemented to the satisfaction of the contracting officer. The Contracting Officer will provide a blank copy of the accident report form.

H.11.6.3 Notifying the Contracting Officer

The Contractor shall notify the Contracting Officer as soon as practical, but not later than four hours, after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $2,000, or any weight handling equipment accident. Include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (e.g., type of construction equipment used, PPE used). Preserve the conditions and evidence on accident site until the Government investigation team arrives and Government investigation is conducted.

H.11.6.4 Monthly Work-Hour Reports

Monthly work-hour reporting to the Contracting Officer is required to be attached to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The Contracting Officer will provide copies of any special forms.

H.11.7 Hot Work

Prior to performing "Hot Work" (e.g., welding, cutting) or operating other flame producing/ spark producing devices, request a written permit from the Fire Division. CONTRACTORS ARE REQUIRED

TO MEET ALL CRITERIA BEFORE A PERMIT IS ISSUED.

Criteria shall be defined as that meeting industry standard for the work being performed.

It is mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site as required after completion of the task or as specified on the hot work permit.

D.11.8 Hazardous Material Use

Each hazardous material must receive approval prior to being brought onto the job site or prior to any other use in connection with this contract. Allow a minimum of 10 working days for processing of the request for use of a Hazardous Material (HazMat).

The Contractor shall provide a Safety Data Sheet(s) for all HazMat brought on base and to all jobsite locations.

All HazMat drivers shall hold a Greek ADR license (European Union hazardous material transport course). Hazardous material will be screened for the following prohibited constituents:

• Asbestos

• Acrylonitrile

• Arsenic

• Benzene

• Beryllium

• Cadmium

• Chrome VI (hexavalent chromium)

• Formaldehyde

• Isocyanates

• Mercury

• Methylene chloride

• Lead

• Polychlorinated biphenyls (PCBs)

• Vinyl chloride

• Carcinogens in amounts greater than 0.1%

• Chemical substances or mixtures subject to an order under 15 U.S.§ 2606.

• Toxic water pollutants defined in 33 U.S.C. § 502 (13) and regulated under 33 U.S.C. § 1317.

• Hazardous air pollutants regulated under 42 U.S.C. § 112.

• Extremely hazardous substances described in 42 U.S.C. § 11002(a)(2).

If flammable liquids (flashpoint 200 F or above) are to be stored on site, provide a flammable liquid storage cabinet in compliance with specifications of NFPA 30, Chapter 14. The Contractor may be required to Register hazardous material storage units (e.g. provide a Point of Contact) and allow the temporary application of additional provided signs or forms if required by local instructions.

Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, or lead-based paint are prohibited. The Contracting Officer, upon written request may consider exceptions to the use of any of the above excluded materials.

The Request for Proposal should have identified materials such as PCB, lead paint, and friable and nonfriable asbestos. If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous.

If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to FAR 52.243-4, Changes, and FAR 52.236-2, Differing Site Conditions.

H.11.9 Pre-outage Coordination Meeting (Utilities)

Apply for utility outages at least 15 days in advance. As a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

H.11.10 Fall Hazard Protection and Prevention Program

Establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. Include company policy; identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures.

H.11.10.1 Fall Protection for Roofing Work

Implement all protection controls based on the type of roof being constructed and work being performed. Evaluate the roof area to be accessed for its structural integrity including weightbearing capabilities for the projected loading.

1) A safety monitoring system is not adequate fall protection for low sloped roofs and is not authorized.

2) Work on steep-sloped roofs, including residential or housing type construction, requires a personal fall arrest system, guardrails with toe-boards, or safety nets.

H.11.10.2 Fall Prevention and Design

During design, consider and eliminate fall hazards encountered at the facility during maintenance evolutions whenever possible. If it is not feasible to eliminate or prevent the need to work at heights with its subsequent exposure to fall hazards, include control measures in the design to protect personnel conducting maintenance work after completion of the project. In addition to the detailed requirements included in the provisions of this contract, incorporate the requirements of 29 CFR 1910 Standards in the design (29 CFR 1915 applies for work in Shipyards).

H.11.11 Weight Handling Equipment H.11.11.1 Certificate of Compliance (Cranes)

Provide a Certificate of Compliance for each crane and Multi-Purpose Machine, Material Handling Equipment (Forklifts), and construction equipment when used as cranes to lift suspended loads entering an activity under this contract (see Contracting Officer for a blank certificate).

Certificate shall state that the WHE and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., WHE used in construction, demolition, or maintenance shall comply with 29 CFR 1926, Occupational Safety and Health Standards for Construction, and USACE EM 385-1-1, Safety and Health Requirements Manual, section 16 and NAVFAC P-307. The Certificate of Compliance shall state that the WHE operator(s) is qualified and trained in the operation of the WHE to be used. Also certify that all of its WHE operators working on the DoW activity have been trained in the proper use of all safety devices (e.g., anti-two block devices). Post these certifications on the cranes.

H.11.11.3 Notification

Notify the Contracting Officer 15 days in advance of any cranes entering the activity so that necessary quality assurance spot checks can be coordinated. Contractor's operator shall remain with the crane during the spot check.

H.11.11.4 Requirements

1.) Comply with the crane manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work. Perform erection under the supervision of a designated person (as defined in ASME B30.5). Perform all testing in accordance with the manufacturer's recommended procedures.

2.) Comply with ASME B30.5 for mobile and locomotive cranes, ASME B30.22 for articulating boom cranes, ASME B30.3 for construction tower cranes, and ASME B30.8 for floating cranes and floating derricks.

3.) Under no circumstance make a lift at or above 90% of the crane’s rated capacity in any configuration.

4.) When operating in the vicinity of overhead transmission lines, operators and riggers shall be alert to this special hazard and shall follow the requirements of USACE EM 385-1-1 section 11 and ASME B30.5 or ASME B30.22 as applicable.

5.) Use cribbing when performing lifts on outriggers.

6.) Position the crane hook/block directly over the load. Side loading of the crane is prohibited.

7.) Certification records which include the date of inspection, signature of the person performing the inspection, and the serial number or other identifier of the crane that was inspected shall be available for review by Contracting Officer personnel.

8.) Written reports listing the load test procedures used along with any repairs or alterations performed on the crane shall be available for review by Contracting Officer personnel.

9.) Certify that all crane operators have been trained in proper use of all safety devices (e.g. anti-two block devices).

10.) Take steps to ensure that wind speed does not contribute to loss of control of the load during lifting operations. Prior to conducting lifting operations, set a maximum wind speed at which a crane can be safely operated based on the equipment being used, the load being lifted, experience of operators and riggers, and hazards on the work site. Include this maximum wind speed determination in the activity hazard analysis plan for that operation.

H.11.12 Utility Locations and Verification Prior to Excavation

The Contractor shall obtain appropriate digging permit from Base personnel through Administrative Contracting Officer’s Technical Representative prior to digging. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any Installation locating service and coordinated with the Installation utility department. Maintain all markings during utility investigation throughout the contract.

Physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system.

Use hand digging within 0.61 m (2 feet) of a known utility. If construction is parallel to an existing utility, expose the utility by hand digging every 30.5 m (100 feet) if parallel within 1.5 m (5 feet) of the excavation.

a.) Excavation: All excavation works shall be in accordance with PWD’s SOP for Excavation, PWD-EXCAVATION-01. All excavation requests shall be submitted to the Contracting Officer Technical Representative on PWD’s Excavation Request Form, included in Attachment J.

H.11.13 Utilities within Concrete Slabs

Utilities located within concrete slabs are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with Installation utility departments in addition to a private locating service. Outages to isolate utility systems shall be used in circumstances where utilities are unable to be positively identified. The use of historical drawings does not alleviate the contractor from meeting this requirement.

H.11.14 Conduct of Electrical Work

Follow electrical safety criteria specified in UFC 3-560-01, USACE EM 385-1-1, Safety and Health Requirements Manual, and NFPA 70E, Standard for Electrical Safety in the Workplace, during the conduct of all work.

OSHA Approved Certification – The equipment installation and its component parts shall be in compliance with the applicable OSHA regulations in accordance with CFR Title 29, Chapter XVII, Part 1910 and installed in accordance with FEC/NFPA requirements. Approval shall be as specified under the “Approval” and “Acceptance” criteria in the OSHA regulations Subpart “O”, Machinery and Machine Guarding paragraph 1910.212 and Subpart “S” Electrical, paragraph 1910.303 and paragraph 1910.399.

After equipment delivery and installation, and prior to testing, the Contractor shall provide an OSHA Certification Report. Failure to provide this certification report will delay acceptance of the equipment and could result in rejection for failure to comply with the terms of the contract. This report documents the results of all tests performed, provides an assessment of the equipment performance for compliance with the contract requirements, and forms a basis for recommending a safety certification. The report, test and evaluation shall be a composite of those inspection requirements specified in the contract. The report shall be prepared in an orderly manner to clearly and accurately set forth the collected data and conclusion resulting from these inspection requirements, opinions and subjective conclusions shall be clearly identified. The report shall include, but is not limited to, the following:

1. List of all tests performed and by whom witnessed.

2. List of data used for evaluation.

3. Tabulation of all discrepancies related to specification performance requirements.

4. Description of limitations revealed by data utilized.

5. Actions taken to mitigate each discrepancy and limitation.

6. Recommendations for subsequent actions.

7. Summary conclusions.

Manufacturer Certification that equipment has been manufactured and installed to OSHA CFR

1910.399 (per definition of “acceptable”).

H.11.15 Work in Confined Spaces

In addition to the requirements of Section 06.I of USACE EM 385-1-1, Safety and Health…