Amnd 0001 20R6010 FINAL.pdf
PDF 652 KB Posted
- Attached to
- FC100 Parking Lot
- Solicitation number
- N6247020R6010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Master PPI Form - FC100 Parking Lot.xls | XLS spreadsheet | |
| RFP 18-0049 - FC100 Parking Lot.pdf | ||
| 18-0049 Appendix D.pdf | ||
| N4008518B0049 Dwgs.pdf | ||
| N4008518B0049 Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
18-0049 FC100 Parking Lot Solicitation N62470-20-R-6010
Marine Corps Base Camp Lejeune, North Carolina Amendment 0001
Block 14. DESCRIPTION OF AMENDMENT (cont.)
A. The following provides the Government’s responses to preaward inquiries:
REFERENCE
Page Section Para.
QUESTION GOVERNMENT RESPONSE
The RFP states this will be a two person project. SSHO/Super and a separate QC is this correct?
This is correct, the SSHO/Super and a separate QC are required.
Does the construction joints indicated on drawing CS-101 have dowels? If so what is the size of dowels / height / spacing?
No, there are no dowels on "CJ" construction joint. See Detail C, Sheet CS501.
Is there a need to drill & epoxy set dowels in existing concrete shown to butt up to? If so what is dowels same size & spacing as CJ if required?
Yes, there is a need. Please provide per Detail C, Sheet CS501
- "EJ".
What strength mix design are you needing 5000 psi or 650Flex?
650 Flex is required.
Thickness of concrete apron 5" or 10"
The thickness of the concrete apron is 10" per Detail B, Sheet
CS501.
A. All other contract terms and conditions remain unchanged.
| Amnd 0001 20R6010 |
| Untitled |
| Untitled |
Pg2 Amnd 0001 20R6010
| IDCode: |
| Page: 1 |
| Pages: 2 |
| AmendNo: AMENDMENT NO. 0001 |
| EffDate: 06/26/20 |
| ReqNo: |
| ProjNo: 1636586 |
| IssCode: ACQ1 |
| IssuedBy: NAVAL FACILITIES ENGINEERING COMMAND, MID-ATLANTIC |
9742 MARYLAND AVENUE
NORFOLK, VA 23511-3095
| AdmCode: |
| AdminBy: See Item 6 |
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolChgYs: Yes |
| SolChgNo: Off |
| SolAmdNo: N6247020R6010 |
| AmendDate: 05/29/20 |
| ModNo: |
| ModDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Off |
| OffrNoEx: No |
| ApprData: |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: |
N6247020R6010 FC100 Parking Lot
The date and the hour for the receipt of proposals remains 09 Jul 2020 no later than 2:00 pm (EDT).
See continuation page(s).
| SignName: |
| SignTitl: |
| ContDate: |
| CoName: |
| CoTitle: |
| CODate: |