Att_D_Questions_Request_Form_2.docx

DOCX document 30 KB Posted

Attached to
Collector - Environmental Intelligence Preparation of the Battlespace (C-EIPB)
Solicitation number
N6230619R0012
Issued by

About this file

Questions and Answers Form 2

View the file

Other files

File Type Posted
Att_D_Questions_Request_Form_1.docx DOCX document
Att_E_DD254_CEIPB.pdf PDF
Att_A_Terms_and_Conditions.pdf PDF
Combined_Synopsis_Solicitation_-_Collector-EIPB.pdf PDF
Att_D_Questions_Request_Form.docx DOCX document
Att_C_Performance_Work_Statement.docx DOCX document
Att_B_Evaluation_Price_Schedule.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Leidos Proprietary Leidos Proprietary N6230619R0012 Attachment D

Questions Request Form

#
SOW/PWS Reference
Question
Answer
1.
Attachment A SF 1449
Should the Offeror assume that the Government will complete the Attachment A SF 1449 schedule at the time of award based on the Attachment B Evaluation Price Schedule?
Yes
2.
Attachment A

FAR 52.212-1 (Page 45) and Addendum to FAR 52.212-1 (Page 64)

The Offeror assumes that FAR 52.212-1 (b) is replaced in its entirety with the Addendum to FAR 52.212-1 that only requires 4 artifacts to be submitted as its proposal response (No exceptions; Reps & Certs; SB S/C Plan; and Attachment B. Is this a correct assumption
Yes. The Addendum to FAR 52.212-1 outlines what is to be submitted in the Instructions for written Proposals Section 2
3.
Instructions for Written Submittals (Page 64) & Section 8 Proposal Organizations
Instructions for written submittals references 4 artifacts to be submitted as a proposal response (see Question #2 list) but Section 8.1 only references 3 artifacts (the SB S/C Plan is not listed). Can you please clarify as to what needs to be submitted with the proposal?
Yes, a Small Business Subcontracting Plan must be submitted.

Section 2 of Addendum 52.212-1, references the documents required to be submitted.

Section 8.1 of Addendum 52.212-1, emphasizes the documents in the proposal organization.

Please refer to Section 2 of Addendum 52.212-1 Instructions to Offerors for submission requirement.