Att_D_Questions_Request_Form_1.docx

DOCX document 29 KB Posted

Attached to
Collector - Environmental Intelligence Preparation of the Battlespace (C-EIPB)
Solicitation number
N6230619R0012
Issued by

About this file

Questions and Answers Form 1

View the file

Other files

File Type Posted
Att_D_Questions_Request_Form_2.docx DOCX document
Att_E_DD254_CEIPB.pdf PDF
Att_A_Terms_and_Conditions.pdf PDF
Combined_Synopsis_Solicitation_-_Collector-EIPB.pdf PDF
Att_D_Questions_Request_Form.docx DOCX document
Att_C_Performance_Work_Statement.docx DOCX document
Att_B_Evaluation_Price_Schedule.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Leidos Proprietary Leidos Proprietary N6230619R0012 Attachment D

Questions Request Form

#
SOW/PWS Reference
Question
Answer
1.
Attachment A & B, Combined Synopsis
Attachment A (pages 3 through 41) and Attachment B reference Base period plus five one-year options. Attachment A Page 70 –Contract Award section and the Combined Synopsis references Base with four one-year options. Which is correct?
The fifth year CLIN is to capture prices for FAR 51.217-8 Option to Extend Services as annotated in the CLIN description for CLINS 5001-5013 in Att A.
2.
Attachment A & B
CLINs 0001, 0002, 0009 and 0010 reference more than 12 months for the base year of performance. This is also true for each option year. Shouldn’t the number of months for each of these CLINs be 12 or less?
As annotated in Att C PWS Section 2.2 “All tasks outlined in below sections shall be completed per month with a possibility of multiple customers, simultaneously.” For example: This means 60 months equates: five customers can order 12 month services, which would total 60 months for CLIN 0001.
3.
Attachment A,

Section 8.1 & Addendum to 52.212-2 Para 1.2 & 1.3 (Pages 66- 67)

Lowest Price Technically Acceptable (LPTA) – Para 1.2 & 1.3 refers to “technical requirements”. Is a technical response to be included as part of the proposal submission in addition to the artifacts listed in Section 8.1?
No. The technical requirements is referring to what is outlined in the PWS. As stated in the Request for Proposal, the signature provided by the contractor, is confirming that the contractor does not take exception to the technical requirements of the solicitation.
4.
General
What is the anticipated Award Date and Contract Start Date?
The anticipated award date is on or about 4 Sep 2019, with a contract start date of NLT 23 Sep 2019.