PM Crew Attachment C SOW.pdf

PDF 435 KB Posted

Attached to
Request for Information and Industry Day: MMSC PM Crew
Solicitation number
N61177-27-R-2006
Issued by

About this file

This is a Statement of Work (SOW) for the Multi-Mission Surface Combatant (MMSC) Professional Mariner (PM) Crew Contract under solicitation N61177-27-R-2006, issued by the United States Navy for a Foreign Military Sales case supporting the Kingdom of Saudi Arabia's purchase of four MMSC vessels.

The contractor is responsible for operating and maintaining four MMSC ships during the post-delivery period, which spans from September 2028 through June 2031 depending on the vessel. Key operational responsibilities include safe ship operations in-port and underway, crew management of approximately 30 personnel, and coordination across multiple post-delivery phases: Post Delivery Availability (PDA), transit from Marinette, Wisconsin to Naval Station Mayport, Florida, Post Shakedown Availability (PSA), Post Delivery Test & Trials (PDT&T), Industrial Post Delivery Availability (IPDA), Planned Maintenance Availabilities (PMAVs), and Royal Saudi Naval Force (RSNF) Crew Integration. The contractor must comply with USCG regulations, maintain qualified mariners with appropriate licenses and certifications, perform organizational-level maintenance estimated at 240 hours weekly, manage hazardous materials and environmental compliance, and provide hotel and medical support for embarked personnel. Contract line items (CLINs) cover operations (0001-0004), operations data (0005), maintenance (0006-0009), maintenance data (0010), hotel support (0011-0014), hotel data (0015), shore support detachment (0016-0019), shore support data (0020), PMAV support (0021-0024), and PMAV data (0025). Key personnel requirements include a Program Manager with five years' vessel operations experience, Ship's Master with unlimited ocean license, Chief Engineer with gas turbine endorsement, and supporting engineering officers, all with specified desired experience on Navy or Military Sealift Command vessels. All crew must be U.S. citizens, USCG-licensed, hold valid Transportation Worker Identification Credentials, possess current security clearances, and maintain certifications in firefighting and damage control.

View the file

Other files

File Type Posted
DRAFT- J-27 CDRL Package.pdf PDF
DRAFT- MMSC PM Crew RFP List of J-Attachments.pdf PDF
PM Crew Draft Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

STATEMENT OF WORK

MULTI MISSION SURFACE COMBATANT (MMSC)

PROFESSIONAL MARINER (PM) CREW CONTRACT

SOLICITATION N61177-27-R-2006

Attachment C: Statement of Work Solicitation N61177-27-R-2006 MMSC Professional Mariner (PM) Crew Contract

MMSC Professional Mariner (PM) Crew Contract Statement of Work

Program Background In 2017, the United States Navy (USN) and the Kingdom of Saudi Arabia (KSA) Ministry of Defense (MoD) executed a Letter of Offer and Acceptance (LOA), initiating a Foreign Military Sales (FMS) case for the purchase of four (4) Multi-Mission Surface Combatants (MMSC). Lockheed Martin (LM) is the prime contractor responsible for constructing the ships with Fincantieri Marinette Marine (FMM) as the shipbuilder located in Marinette, WI. The scope of the case also includes Royal Saudi Naval Force (RSNF) Crew and Shore Support training and integration.

The MMSC is a variant of the U.S. Navy’s Freedom variant Littoral Combat Ships (LCS). The ship is waterjet-propelled by combined gas turbine/diesel power. It is equipped with a 57mm Gun, Harpoon Missiles, CEROS 200, SeaRAM, ALEX SKWS, and COMBATSS-21. Berthing is available for a ship complement of 101 for an RSNF Crew of 84 with 17 additional sailors embarked for the air detachment.

For the duration of ship operations during the post-delivery period, the air detachment will not be onboard. Berthing for an additional 29 personnel is available via surge berthing with a total of 130 racks being available onboard. Attachment J-1 MMSC Ship Specification Sheet provides additional details but may not reflect all potential ship changes.

Post Delivery Schedule Post-delivery is a critical period in all USN ship acquisition programs. During a typical post-delivery period, the USN will verify operational readiness through extensive, integrated at-sea testing to identify any potential deficiencies through sustained equipment operation and inspections. Through a Post Shakedown Availability (PSA), an Industrial Post Delivery Availability, a Continuous Maintenance Availability (CMAV) and incremental Planned Maintenance Availabilities (PMAV) , a successful post-delivery period will maximize the ship’s material readiness in an at-sea environment.

During the Post Shakedown Availability (PSA), in-line engineering updates are completed, and deficiencies found during ship operations and testing are corrected. In addition to the typical events conducted during a USN post-delivery period, the MMSC Post-Delivery period will also include RSNF Crew integration and training, as well as RSNF Shore Support Team integration.

The contracted Professional Mariner (PM) Crew is expected to operate the MMSC during all phases of post-delivery, to include a Post Delivery Availability (PDA), ship transit, Industrial Post Delivery Availability (IPDA), Post Delivery Test and Trials (PDT&T) and RSNF Crew and Shore Support Integration. During PSA, MMSC will be nonoperational and non-habitable while in a shipyard undergoing ship modernization and repairs. During PSA, the PM Crew will receive alternate tasking.

Attachment J-2, MMSC Post Delivery Timeline, provides the sequence and notional durations for these periods.

Throughout the post-delivery period, there will be numerous stakeholders with competing interests. The schedule will be managed by a Schedule Integration Team (SIT) which will be composed of representatives from the PM Crew, the PDT&T Team, the RSNF Training and Integration Teams as well

Attachment C: Statement of Work Solicitation N61177-27-R-2006 as the PMS 525 Operations and Maintenance Team. The SIT will be responsible for meeting daily to discuss the plan of the day, discuss events that could not be completed and need to be rescheduled, and to deconflict and plan the next day’s operations. The senior PMS 525 PDT&T member will be the sole authority for determining and distributing underway trial and testing schedules and requirements. The PM Crew’s Master or representative shall attend PD SIT daily meetings. The Master is responsible for the safe operation of MMSC and for the performance and safety of the PM Crew. The PM Crew Master will be aware of the daily schedule of events, as well as speed and distance, maneuvering or navigation restrictions.

Post Delivery Availability (PDA)

A number of critical events are accomplished during this period including completion of ship outfitting, crew move aboard (both PM Crew and select RSNF Crew), and crew familiarization to include short underway periods (both PM Crew and RSNF Crew). Industrial production work is minimized and conducted on a non-interference basis.

The PDA period provides the Professional Mariner Crew an opportunity to familiarize themselves with MMSC from the shipyard to PMS 525, key members of the PM Crew will have access to the construction shipyard (FMM) approximately 45-60 days prior to delivery of each ship.

Transit

MMSC will transit from the shipbuilder in Marinette, WI, to Mayport, FL, over approximately 28 days, with scheduled port visits along the route. During this period, the ship will operate independently and conduct limited shipboard testing. The transit will also give the PM Crew additional opportunity to become familiar with ship operations.

Post Shakedown Availability (PSA)

The PSA is a Depot-Level (D-level) repair availability to be performed at a yet-to-be-determined shipyard. The goal of PSA is to correct shipboard deficiencies; incorporate approved engineering changes, and present RSNF a ship in optimal material condition. The PSA also includes drydocking to accomplish underwater hull maintenance/repair.

During PSA, MMSC will be in-port, non-operational and non-habitable. The PM Crew may be expected to perform alternate tasks as-needed which may include organizational-level (O-Level) maintenance, shipyard performance monitoring, fire marshal duties, equipment tag-out approvals, and quality assurance oversight.

Test & Trials

The PDT&T period will verify and validate the MMSC’s operational capabilities in its respective warfare mission areas. These warfare mission areas including, but not limited to air, surface, and electronic warfare - will be exercised during tracking and live fire test events conducted by Naval Surface Warfare Centers (NSWCs).

The PM Crew will operate the ship’s hull, mechanical, and electrical (HM&E) systems in port and, while at sea, will operate navigation and small boat systems to ensure the ship arrives on station in time for all

Attachment C: Statement of Work Solicitation N61177-27-R-2006 test and trial events. The PM Crew will not operate combat systems or weapon systems during tracking, live-fire, or test and trial events. NSWC Port Hueneme Division (PHD) is responsible for staffing all combat system and weapon system operator positions during these events.

Planned Maintenance Availability (PMAV)

PMAVs are notionally 5-day long maintenance availabilities that will be scheduled and performed monthly. During the PMAV, shore support teams will come onboard to perform O-Level planned maintenance on systems and equipment throughout the ship. The PM Crew will be responsible for ensuring safe access to the equipment. PMAVs are performed in-port, and the ship will not be expected to get underway within 72-hour notice.

Industrial Post Delivery Availability (IPDA)

After PDT&T, an IPDA will occur to accomplish repairs and upgrades identified during the PDT&T period. This availability will occur at a yet-to-be-determined shipyard. The PM Crew may be expected to perform alternate tasks, which may include O-Level Maintenance, fire marshal responsibility, equipment tag-out approvals, and quality assurance oversight.

RSNF Crew Integration Period

A dedicated RSNF Crew Integration Period will be scheduled. Its objective is to transition operational control of the ship from the PM Crew to the RSNF Crew in a controlled manner. RSNF Crew “shadowing” of PM Crew in-port and underway duties and responsibilities with conduct of daily drills and scenarios that will be evaluated and graded by PMS 525 training team. As RSNF Crew competency increases, the PM Crew will gradually assume an observational role during ship operations. However, the PM Crew will always remain responsible for safe operation of the ship.

Continuous Maintenance Availability (CMAV)

Prior to MMSC Sail Away from Mayport, a CMAV repair availability will be conducted pier-side to accomplish deferred equipment repairs and facilities maintenance. A concurrent PMAV will also be performed during this window.

Anticipated ship delivery dates for the class are in Table 1 below. These delivery dates are subject to change.

MMSC 1 Delivery to USN September 2028 MMSC 1 Delivery to RSNF January 2030 MMSC 2 Delivery to USN February 2029 MMSC 2 Delivery to RSNF June 2030 MMSC 3 Delivery to USN July 2029 MMSC 3 Delivery to RSNF November 2030 MMSC 4 Delivery to USN February 2030 MMSC 4 Delivery to RSNF June 2031

Table 1: Anticipated Ship Delivery Dates

Attachment C: Statement of Work Solicitation N61177-27-R-2006

Key Personnel This section provides a general overview of the responsibilities of key PMS 525 PD personnel and organizations involved in MMSC PD Support. Attachment J-3, PMS 525D Organization lists personnel, who support the PD Principal Assistant to the Program Manager (PAPM).

Post Delivery PAPM

The PD PAPM has overall responsibility for the successful accomplishment of MMSC during PD and reports directly to the PMS 525 Program Manager.

Post Delivery Test & Trials (PDT&T) Assistant Program Manager (APM)

The PDT&T APM is responsible to the PD PAPM for providing management and execution of all test events during the PDT&T period while working closely with stakeholders from various government activities and supporting contractors.

Post Delivery RSNF Crew Integration APM

The RSNF Crew Integration APM is responsible to the PMS 525 PD PAPM for the planning, management, and execution of all RSNF Crew training events during the PD period.

Post Delivery Operations and Maintenance (O&M) APM

The PD O&M APM is responsible for the PD PAPM for providing overarching management and execution of PD operations, planned maintenance and logistics support during the PD period.

Hull Manager (HM)

The HM is the onsite PD team lead and serves as the primary representative for planning and execution of all industrial availabilities.

Hull Support Manager (HSM)

The HSM is the primary support contractor for the PD HM and is the focal point for all PSA planning and execution efforts.

Maintenance Coordinator/RSNF Shore Support Integrator

The Maintenance Coordinator/RSNF Shore Support Integrator provides support typically performed by Navy Ship Crews, fleet organizations and organizations providing O-Level Maintenance.

3M Coordinator

The 3M Coordinator is responsible for the implementation and management of the Planned Maintenance System (PMS) Program for the ship.

Planned Maintenance Availability (PMAV) Coordinator

PMAV Coordinator is primarily responsible for developing the PMS Work Package (WP) and managing the resources required to accomplish the PMAVs.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

Detailed descriptions for all PMS 525 PD positions can be found in the PMS 525 PD Manual which will be provided upon request.

CLINs 0001-0004: Operations The following tasks apply to:

• CLIN 0001 (MMSC-1)

• CLIN 0002 (MMSC-2)

• CLIN 0003 (MMSC-3)

• CLIN 0004 (MMSC-4)

MMSC shall remain in operating status throughout PD, and capable of getting underway within 72 hours after receipt of sailing orders. Except for PSA and IPDA, ships are anticipated to be underway approximately 65% of the PD window. Underway periods are defined as the ship operating outside of a port, which includes but is not limited to independent steaming, test & trials, training operations, and transits to and from selected ports.

Ship Riders

In addition to the PM Crew, ship riders to be embarked include PMS 525, Original Equipment Manufacturer (OEM), Lockheed Martin (LM), Shipyard (SY), Government Test Team, RSNF Crew and Crew Training Team (CTT) as notionally shown in Table 2.

The CTT is a PMS 525 team dedicated to training the RSNF Crew and will consist of approximately 10- 15 members familiar with U.S. Navy training methods and standards. PMS 525 personnel will have overall responsibility of managing post-delivery activities, developing, and executing a daily ship schedule, and RSNF Crew Integration.

The OEM authorized representative performs equipment maintenance, diagnostics, and repairs as required. Industry riders from Lockheed Martin (LM) will assist with PDT&T and perform maintenance and repairs as needed. A dedicated rider from LM will coordinate all guaranteed work. Riders from the shipyard, Fincantieri Marinette Marine (FMM), will be available to troubleshoot systems and assist with ship problems.

The Government will staff Test Team members consisting of combat systems operators, command control communication and computers and information personnel. The test team will manage and oversee the PDT&T period while the equipment operators will perform weapons firings. Additionally, up to 84 members of the RSNF Crew will ride the ship during all underway phases of post-delivery.

MMSC Riders PDA Transit Testing PSA RSNF Crew Integration

PMS 525 CTT 0 0 10 0 13

PM Crew ~30 ~30 ~30 ~30 ~30

PMS 525D Personnel 5 3 3 10 3

OEM, LM, SY 5 5 10 10 5

Government Test Team 0 0 20 5 5

Attachment C: Statement of Work Solicitation N61177-27-R-2006

RNSF Crew 0 2 TBD TBD 84 Table 2: Projected MMSC Ridership during PD

Note 1: The numbers provided in Table 2 are estimates and are subject to change Note 2: All remaining available berthing will be allocated to RSNF Crew

Task 1: General Operations

1. The Contractor shall be responsible for the safe and efficient maintenance and operations – in-port and underway. The crew will operate all main, auxiliary, and emergency shipboard equipment and systems, while in-port and at-sea per terms of this contract, engineering operating sequencing system (EOSS) procedures and equipment manufacturer requirements.

See Attachment J-4, MMSC EOSS Procedures.

2. The Contractor shall operate the MMSC ships in accordance with the United States Coast Guard (USCG) Navigation Rules and Regulations, other applicable US National, State Statutes & Regulations, and international laws and regulations.

3. The Contractor shall plan to operate the ships in the following areas: Great Lakes, St.

Lawrence Seaway, Atlantic Seaboard, Gulf of America and Bahamas. The Contractor shall maintain electronic charts for each ship’s region of operation.

4. The Contractor shall provide mariners who meet all current standards of training, certification and watchkeeping requirements for their rating and ship’s horsepower and tonnage requirements.

5. The Contractor shall be aware that personal emergencies which arise while onboard an operationally employed ship are not be considered automatic justification for aborting a mission or making a port call to accommodate the emergency.

6. While pier-side at NAVSTA Mayport, the Contractor shall consider a normal workday as 0700–1630 Monday through Friday. The Contractor shall provide a minimum of two (2) personnel on the ship 24 hours a day, seven (7) days a week to include all holidays to support watch standing.

7. While pier-side at a port other than NAVSTA Mayport, the Contractor shall provide an onboard crew 24 hours a day, seven days a week, to support pier side normal, emergent shipboard operations and security.

8. The Contractor shall develop, maintain, and implement severe weather procedures for all ships. In accordance with Attachment J-5, MANUAL OF THE SENIOR OFFICER PRESENT AFLOAT (SOPA) MAYPORT, FLA, 5440.3H 9 May 2017.

a. The instruction shall be reviewed annually and applicable PM Crew Contract Instructions updated accordingly.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

b. The Contractor shall deliver a Heavy Weather Plan (Severe Weather Plan/Procedures) per Attachment J-27 Contract Data Requirements List.

9. The Government may authorize additional manning to support underway sorties. When a hurricane condition is set in the area of operations (AOR), and any ship is in-port or underway within the storm-related area, the Contractor shall submit an initial hurricane status report for all ships within one hour of notification of the condition being sent to PMS 525 Hull Manager IAW J-5. Ships unable to sortie shall take all available extra precautions to prepare for severe weather. PMS 525 will assist with contracts for support (such as standby tugs or cranes) as appropriate.

10. Prior to each underway period from Sail around through delivery to the RSNF, the Contractor shall ensure that all requisite (redlines and/or mission required) equipment is safe to operate (STO). The Contractor shall develop and provide a process and/or procedures that will ensure MMSC is materially safe and ready to get underway. Equipment and systems shall be aligned and operated in accordance with Engineering Operational Sequencing System (EOSS) and, if applicable, planned maintenance procedures. Equipment defects or conditions that prevent the ship or a piece of equipment from being declared as STO shall be reported to PMS 525 immediately.

11. The Contractor shall submit a Daily Situation Report (SITREP) to the PMS Hull Manager, per Attachment J-27 Contract Data Requirements List.

a. This report shall include the fuel state, equipment conditions, significant issues, temporary standing orders, upcoming training or maintenance events, sanitation services and housekeeping efforts.

12. In case of emergency, nothing in this contract shall be construed as preventing the Master from taking the most effective action to safeguard life, property, and the ship. The Master shall have authority to abort operations temporarily in light of clear and present danger to life at sea.

13. The Contractor shall designate a member of the crew as a Schedule Integration Team (SIT) Representative. This representative shall attend daily SIT meetings where PMS 525 will review the schedule for the day/week and make changes as appropriate.

14. The Contractor shall manage a Work Authorization Form (WAF)/Tag-Out Program in accordance with Attachment J-6.

15. Per Attachment J-27 Contract Data Requirements List, the Contractor shall develop a Damage Control Drill Package, in accordance with Table 4, to include grading criteria that determines satisfactory drill performance.

16. The Contractor shall document costs in a monthly Funds and Manhour Expenditure Report (PM Crew Monthly Cost Report) per Attachment J-27 Contract Data Requirements List.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

Task 2: Post Delivery Availability (PDA)/Pre-Transit Prior to departure from FMM, the Contractor shall be afforded a PDA familiarization period of approximately 30 days to acquaint personnel with the layout and operation of the ship.

1. Per Attachment J-27 Contract Data Requirements List, the Contractor shall develop a PM Crew Familiarization/Orientation Plan of actions and milestones defining key events, training, and shipbuilder/OEM support required during the PDA period which shall be maintained and updated after contract award. The Contractor shall identify areas where Government support is required.

2. The Contractor shall make key personnel available for the familiarization period.

3. The Contractor shall allot billets for riders to observe the builder’s sea trials. If billets are provided, the Contractor shall assign personnel to ride the ship.

4. The Contractor shall provide the Government with a request for OEM training support 90 days in advance of the familiarization period.

5. The Contractor shall schedule/attend Quebec Pilot School at the Maritime Simulation & Resource Center in Quebec.

6. The Contractor shall participate in (2) underway periods prior to transit. The two periods will comprise of:

a. PM Crew to “shadow” the Shipbuilder Operating Crew during in port and underway operations. The Shipbuilder Operating Crew Master is responsible for the safe operation of the ship.

b. PM Crew to prepare for and perform in-port and underway operations under the supervision of the Shipbuilder Operating Crew. The Shipbuilder Operating Crew Master is responsible for the safe operation of the ship

7. The Contractor shall perform Transit Load-Out.

8. The Contractor shall conduct a Safe to Sail Review in accordance with Attachment J-7, MMSC Operational Readiness Instruction, and submit a Ready for Sea/Safe to Operate Plan/Checklist per Attachment J-27 Contract Data Requirements List. The Contractor shall incorporate the following requirements into their plan:

a. Equipment Red Line Instruction in accordance with Attachment J-8 MMSC Equipment

Red Line Instruction.

b. Temporary Standing Orders (TSO) in accordance with Attachment J-9 MMSC TSO

Instruction.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

9. The Contractor shall be allowed to install temporary alterations to the ship to promote crew morale or to assist with operation of the ship (Wi-Fi, commercial navigation radars, GPS, etc.). Prior to installation, the Contractor shall submit, per Attachment J-27 Contract Data Requirements List, PM Crew Temporary Alterations for Government approval. Temporary Alterations include equipment to be installed, location(s), and ship systems of equipment to be modified.

Task 3: Transit

1. The Contractor shall sail/transit MMSC from sail from the FMM Shipyard in Marinette, WI through the Great Lakes and St. Lawrence Seaway and down the Eastern Seaboard to Naval Station Mayport, the MMSC homeport during the PD period.

a. The Contractor shall navigate the ship during transit in accordance with all local rules and regulations.

b. The Contractor shall hire a licensed pilot to assist the ship with maneuvering through restricted zones throughout the Great Lakes and St. Lawrence Seaway.

2. The Government will provide (post award) the Contractor with a notional transit plan. The Contractor shall arrange for all required port visits and associated support including but not limited to line handlers and tugs, food procurement, trash and oily waste offload, and fuel onload during the sail around.

a. The Contractor shall provide a final MMSC Transit Plan prior to getting underway per

Attachment J-27 Contract Data.

b. The transit plan shall include underway durations, planned port calls and durations, and planned support for each port call.

3. Prior to entry of the Welland Canal, the ship will be outfitted with protective fendering to assist with the transit of the canal and seaway locks. This evolution may be completed at the build yard or at a stop prior to the Welland Canal. Prior to departure from the St Lawrence Seaway, the Contractor shall be required to stop and have the protective fendering removed.

4. The Contractor shall provide meals, berthing, washroom linens and cleaning services to support embarked crew and Government riders.

5. The Contractor shall procure, service, and dispose of portable toilets to accommodate ship crew and riders during the sail around due to regulations on the Great Lakes and in the St.

Lawrence Seaway. The toilets will be disposed of at the final port stop prior to the Atlantic Ocean.

Task 4: Post Shakedown Availability (PSA) During post-delivery, the ship will undergo a planned 21-week PSA at a yet-to-be-determined shipyard.

During PSA, ship alterations and corrective repairs will be conducted. The table below lists the notional PSA schedules.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

Ship PSA Start PSA Complete

MMSC 1 JAN 2029 JUNE 2029

MMSC 2 JULY 2029 DEC 2029

MMSC 3 JAN 2030 JUNE 2030

MMSC 4 JULY 2030 DEC 2030

Table 3: Notional MMSC PSA Schedules

1. The Contractor shall retain responsibility for the safe operation of ship’s equipment, systems and provide access to ship’s spaces during PSA. The Contractor shall coordinate operations and access with the Post Delivery Execution Yard (PDEY) and other PSA activities.

a. The Contractor shall attend and participate in PSA advance planning and PSA daily/weekly execution related meetings.

b. The Contractor shall turnover the ships Work Authorization Form (WAF) and Tag-out

Program to the PDEY for the duration of the PSA.

c. The Contractor shall assist PMS 525 with regular audits to include PDEY’s management of the WAF/Tag-Out Program.

d. The Contractor will assist the Hull Manager with providing quality oversight and status of ongoing ship repair work.

e. The Contractor shall assist PMS 525 with verification of work item completion to include attending government responsible check points and witnessing equipment and system testing.

f. The Contractor will operate equipment during light-off and testing,

g. The Contractor shall assist PMS 525 with compartment closeout activities.

2. The Contractor shall perform assigned planned and facility maintenance.

3. Upon conclusion of PSA, the Contractor shall transition WAF Tag-Out Program responsibility from the PDEY.

Task 5: Post Repair Trials Upon successful completion of the PSA and restoration of the ship, the ship will get underway to conduct a Post Repair Trial (PRT) to verify performance of PSA-impacted systems.

1. The Contractor shall verify propulsion, auxiliary and navigation system integrity.

2. The Contractor shall perform STO analysis/RFS review.

3. The Contractor shall conduct a fast cruise prior to getting underway.

4. The Contractor shall execute the PRT Agenda and Schedule.

Task 6: Post Delivery Test and Trials (PDT&T) Upon completion of PSA, the ships will commence the Post Delivery Test and Trials (PDT&T) Period.

During this time, the ship’s Combat and Mission Systems capabilities will be exercised to include radar tracking and missile firings, utilizing manned air and surface targets, or radio-controlled targets.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

A Government provided detachment will be responsible for operation, maintenance and logistics support of all combat and mission systems equipment. Government representatives will be responsible for preparation, weapons release, and subsequent actions surrounding all firing and test events. In support of this effort, the Contractor shall perform the following tasks:

1. The Contractor shall operate the vessel in a manner compliant with the Marine Mammal Protection Act.

2. The Contractor shall designate a representative to attend PDT&T planning and execution meetings - virtually or in person, to include Mission Control Panels (MCPs) and Mission Readiness Reviews (MMRs).

Task 7: Industrial Post Delivery Availability (IPDA)

1. During the IPDA, the Contractor shall coordinate with various IPDA executing organizations conducting repairs, upgrades and testing.

2. The Contractor shall maintain systems integrity and assist the executing yard with and continue to administer the WAF/Tagout Program.

3. The Contractor shall operate equipment as required to support shipyard testing.

4. The Contractor shall assist PMS 525 with verification of work item completion to include attending government responsible check points and witnessing equipment and system testing.

5. The Contractor shall assist PMS 525 with accomplishing various planned audits.

6. The Contractor shall assist PMS 525 with compartment closeout activities.

7. The Contractor shall perform planned maintenance as required.

Task 8: RSNF Crew Integration RSNF Crew Integration onboard MMSC will be divided into two phases. Each phase will be defined in the RSNF Crew Training Plan provided at Contract Award.

During the first phase of RSNF Crew Integration, the crew will conduct events on MMSC under the guidance of the PMS 525 Training Team (525M). The RSNF Crew will participate in training including tracing of systems, starting/stopping equipment, drawing lube oil/fuel oil samples for testing and conducting emergency evolutions like fire and flooding drills. Pending adequate progression, the RSNF Crew may stand under instruction watches under the supervision of the PMS 525 Training Team.

Training events will be briefed to the Contractor as part of the SIT plan for the day. While the primary responsibility for training lies with the PMS 525 Training Team, the Contractor may be asked to provide limited training to the RSNF Crew including details regarding standing of watches, equipment alignment for operation as part of normal ship operations, or emergency actions in case of an equipment casualty or malfunction.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

Training events during the second phase are similar to those in the first phase. However, the objective of this phase is to transition operational control of the ship from the PM Crew to the RSNF Crew in a safe and controlled manner; regardless of the phase or timing, the Contractor shall remain responsible for the safe operation of the ship.

The PMS 525 Training Team will also remain onboard and will supervise the RSNF Crew’s performance of the execution of drills and evolutions to ensure all safety measures are strictly enforced.

1. The PM Crew Ship Master shall designate a member of the PM Crew as a SIT Representative, who shall attend daily SIT meetings, review the training schedule and recommend changes, as appropriate.

2. The Contractor shall provide RSNF watch standing training and PMS support, as directed.

3. During an emergent situation, the Contractor and Government shall cease RSNF training support immediately and the Contractor shall take immediate actions to remedy the emergent situation.

Task 9: Corrective Maintenance Availability (CMAV) Prior to vessel delivery to RSNF, PMS 525 will accomplish a CMAV pier side at NSA Mayport to complete outstanding planned maintenance or repair work by the PDEY. The ship will remain fully operational and capable of getting underway. In support of this effort, the Contractor shall perform the following tasks:

1. The Contractor shall ensure tag outs are accomplished in accordance with the PMS 525 WAF/Tag Out process and prepare the program for transfer to RSNF

2. The Contractor shall maintain systems integrity and assist the executing yard with access to equipment and spaces.

3. The Contractor shall assist PMS 525 with verification of work item completion to include attending check points and witnessing test events.

4. The Contractor shall perform additional planned maintenance, as directed.

5. The Contractor shall support final load-out and provisioning of the ship.

6. The Contractor shall support PMS 525 in the transfer of the ship to RSNF.

Task 10: Communications

1. The Contractor shall operate appropriate shipboard communication equipment in support of the safe operation of the vessel. Records of such communications shall be maintained and submitted. See Task 15.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

2. The Contractor shall communicate logistics requirements and receive other necessary information via a Contractor furnished Starlink System, which is to be a temporary, standalone system – not to be connected to, nor integrated with shipboard systems and networks.

3. The Contractor shall coordinate logistic port services (tugs, line handlers, etc.), repair parts and services, fuel, food, and other consumables.

4. Tactical communications in support of accomplishing Post Delivery Test & Trial events will be performed by a government detachment.

Task 11: Shipboard Security

1. The Contractor shall implement shipboard security measures against terrorism, hostage situations, demonstrations, sabotage, piracy or hostile acts at all times and with increased situational awareness while sailing in high threat areas in accordance with Attachment J-10, MMSC Vessel Security Plan (VSP). The Contractor shall develop a Vessel Security Plan per

2. The Government may implement additional security measures in response to heightened force protection conditions. Additional measures will be directed via task order.

Task 12: Foreign Port Visits

1. During the transit from the construction yard in Marinette, WI, the Contractor may pull into foreign ports to offload and resupply, if necessary and required.

2. The Contractor shall comply with applicable U.S. and host nation agreements that specify procedures for port visits in that country.

3. While performing ship operations, the Contractor shall advise foreign authorities and husbanding agents that MMSC is a sovereign immune vessel of the United States. The Contractor shall operate in accordance with Attachment J-11, NAVADMIN 158/16 Sovereign Immunity Policy. If the Contractor encounters a request contrary to this guidance, the Contractor shall immediately contact PMS 525 for further guidance.

Task 13: Manning

1. The Contractor’s entire crew shall:

a. Be U.S. citizens and literate in English

b. Be United States Coast Guard (USCG) licensed for their billet

c. Meet standards of training, certification and watchkeeping for seafarers (STCW) for their billet

d. Possess a valid Transportation Worker Identification Credential (TWIC), and other USCG documents required by applicable law and regulations

Attachment C: Statement of Work Solicitation N61177-27-R-2006

2. The Contractor shall provide the ship with a trained, medical person to support the ship’s mission., to provide medical first aid onboard. As a minimum, personnel need to be proficient in CPR and automatic external defibrillator (AED) procedures and provide calibration and operation of the breathalyzer, or any other USCG-approved device for determining blood alcohol/drug content

a. During the contract period, the contractor shall maintain ashore, on an as-needed basis, at least one licensed physician to review, approve and certify that members of the crew are fit for duty

b. The Contractor will provide a Medical Kit containing any required equipment and consumable pharmaceuticals to provide medical services to the crew

3. Crew members responsible for operating and maintaining the ship’s firefighting and fire detection system shall comply with U.S. Navy or USCG certified shipboard firefighting/damage control course to include shipboard aircraft firefighting. Certifications shall be current for the duration of the contract.

4. The Contractor shall follow the following policies in regards to Key Personnel:

c. Offerors shall propose Key Personnel at the time of proposal submission, in which a good faith expectation exists of providing such Key Personnel at contract award.

d. For proposed contingent Key Personnel, a Letter of Intent is required and considered to be material to the proposal since these Letters of Intent demonstrate the Offeror’s ability to hire personnel with the qualifications.

e. Key Resumes shall be provided in accordance with Section L.

f. The Government required Key Personnel are as follows:

(1) Program Manager (PM) shall: possess a Bachelor's Degree in Engineering or Business from an accredited college or university. The PM shall have ten

(5) years of experience in vessel operations, maintenance and repairs to include: ship maintenance availability planning, estimating, budgeting, scheduling and sub-contracting management. Desired: Program Management Professional Certification and experience in Navy Maintenance Programs.

(2) Ship’s Master shall: possess a license as a Master Mariner, unlimited oceans, unlimited tonnage. Desired: Have a minimum of 5 years’ experience operating aboard USN or MSC vessels and experience operating waterjet and combined diesel and gas turbine (CODAG) propelled vessels.

(3) Chief Mate shall: possess a license as Chief Mate, unlimited oceans, unlimited tonnage. Desired: Have a minimum of 3 years’ operational experience with USN or MSC vessels.

(4) Chief Engineer shall: possess a license as Chief Engineer, unlimited oceans, of any horsepower with a USCG gas turbine endorsement and five

(5) years documented experience in that position. Desired: Have a

Attachment C: Statement of Work Solicitation N61177-27-R-2006 minimum of 5 years operational experience with USN or MSC vessels and experience operating waterjet and CODAG propelled vessels.

(5) 1st Assistant Engineer shall: possess a license as 1st Assistant Engineer, unlimited oceans, of any horsepower with a USCG gas turbine endorsement and three (3) years documented experience in that position.

Desired: Have minimum 3 years’ operational experience with USN or MSC vessels and experience operating waterjet propelled vessels.

4. The Contractor shall man MMSC in accordance with 46 CFR 15.705, while proposing a tailored PM Crew Watch, Quarter & Station Bill to safely and efficiently meet:

a. Conditions of Readiness: General Quarters, Special Threats, , Peacetime Sailing, In-Port

Readiness

b. Special Evolutions: Piloting/Restricted Maneuvering, Anchorage

c. Emergency Evolutions: Onboard Fire/Flooding, Collision, Small Boat Operations, Abandon Ship, Personnel Evacuation

The Contractor shall submit their WQ&SB/Monthly Roster per Attachment J-27 Contract Data Requirements List.

5. The Contractor shall minimize the frequency and volume of ship’s crew turnover and to the maximum extent possible comply with the following recommendations:

a. There shall be at least thirty days between the rotation of:

i. Ship’s Master and Chief Mate

ii. Chief Engineer and 1st Assistant Engineer

iii. Ship’s Master and Chief Engineer

b. No more than 25% of the crew shall be changed or rotated in any single rotation.

c. The maximum crew rotation per billet is four times per year.

6. The contractor shall make efforts to ensure continuity of employment to the greatest practicable extent among licensed and unlicensed mariners and follow a Hiring and Retention Plan submitted with proposal.

7. The Contractor shall prepare a monthly personnel roster to include after hours, points of contact, per Attachment J-27 Contract Data Requirements List.

8. U.S. Passports: All Contractor crew shall hold valid U.S. passports. Fees associated with obtaining passports shall be at the mariner’s or contractor's expense.

9. In accordance with SECNAV M-5510.30, the Navy Personnel Security Program Manual (Chapter 6, Section 6-6, Paragraphs 2b and 2c), Executive Order 13467 of June 30, 2008, as well as Homeland Security Presidential Directive 12 (HSPD-12) and United States Office of Personnel Management Memorandum, Final Credentialing Standards for Issuing Personal Identify Verification Cards under HSPD-12 dated 31 July 2008, the Contractor shall ensure that all individuals performing work on behalf of the government have a current, favorably adjudicated background investigation of the appropriate type to determine fitness to perform

Attachment C: Statement of Work Solicitation N61177-27-R-2006 work on behalf of the Government as a contractor employee, perform sensitive national security duties, or have access to classified information. A background investigation equivalent to the current Tier requirement and which is still in scope is acceptable. Fees associated with obtaining background checks shall be at the contractor's expense.

10. For personnel accessing U.S. Naval Stations, the Contractor shall submit all personnel for DBIDS identification to facilitate base access. Fees associated with obtaining DBIDs shall be at the contractor's expense.

11. For Key Personnel, the Contractor shall submit issuance Common Access Cards (CACs) in accordance with DoD Instruction/Manual 1000.13. CACs enable positive identification to access various controlled Government websites. Additional requests for CACs will be vetted by the Contracting Officer’s Representative (COR) for approval. Associated fees shall be at the contractor's expense.

12. The Contractor shall meet the training requirements and standards of 46 CFR Part 15.1105 and 46 CFR Part 199.180 (b) and (g). The Contractor shall ensure ship mariners are trained and demonstrate competence in performance of their duties in support of the ship’s emergency and station bills. The Contractor shall maintain the ship’s training materials in accordance with 46 CFR 199.180 (a). All drills, musters, and training shall be logged in the ship’s official logbook.

13. The drills listed below shall be performed in a safe and practicable manner to simulate actual emergencies. Drills shall be conducted to verify procedures and crew preparedness. The crew’s performance shall be critiqued by the Ship’s Master or representative. Findings and recommendations for improvement shall be reported in Damage Control Drill Package, per attachment J-27 Contract Data Requirements List.

Drill Periodicity Requirement Fire Drill Monthly 46 CFR 199.180c (2) Abandon Ship Drill Every Underway 46 CFR 199.80c (2) Damage Control Flooding Drill Quarterly NSTM 079 Lifeboats Waterborne Drill Quarterly 46 CFR 199.180 Line Throwing Appliance Drill Quarterly 46 CFR 199-.80e Man Overboard Drill – Daytime Each Deck Watch Quarterly COMSCINST 3121.9 Man Overboard Drill – Nighttime Each Deck Watch – Every 6 mos. COMSCINST 3121.9 Physical Security Drill As Dictated by PMS 525 and/or

NAVSTA Mayport

33 CFR 104.230

Oil Spill Drill Quarterly 33 CFR 155.1060 (1)/

OPNAVINST 5090.1

Table 4: PM Crew Drill Plan

a. Additional requirements to above periodicities:

i. Every crew member must participate in at least one abandon-ship drill and one fire drill every month.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

ii. If more than 25 percent of the crew have not participated in an Abandon Ship and Fire Drills onboard that vessel in the previous month, then the drills must take place within 24 hours of the vessel leaving a port.

Task 14: Damage Control

1. The Contractor shall submit a PM Crew Damage Control Plan, per Attachment J-27 Contract Data Requirements List. The Plan should be written in accordance with:

a. Attachment J-12, NSTM 079, Vol II

b. Attachment J-13, NSTM 555

c. Attachment J-14, NAVAIR 00-80T-122

d. Attachment J-15, CNSL Standard Repair Party Manual

e. Commercial Best Practices

2. The Contractor shall inspect and inventory onboard DC equipment quarterly and upon turnover of assigned DC Officer. The Contractor shall:

a. Post the inventory record, interior to each DC locker within three days of completing the inventory

b. Using the posted initial DC Repair Locker Inventory Sheets posted in each Repair

Locker, the Contractor shall submit a quarterly Damage Control Inventory Report and make recommendations for the correction of noted discrepancies, per Attachment J-27 Contract Data Requirements List

3. The Contractor shall operate and maintain ship’s firefighting and damage control equipment in accordance with U.S. Navy and manufacturer requirements.

4. When in port, the Contractor shall contain fires and coordinate firefighting efforts with the local fire department. The Contractor shall remain on station to provide direction and access to affected areas.

Task 15: Ship Logs

1. The Contractor shall maintain logs as required by relevant regulations and statutes and at a minimum, maintain the Ship’s Deck and Engineering Logs in which are documented occurrences and events of importance pertaining to ship operations and safety. The Contractor shall:

a. Maintain logs for the period of performance of the contract

b. Make all logs available for review as requested by PMS 525

Task 16: Quality

1. Using commercial best practices (CBP) and industry guidelines, the Contractor shall develop and administer a Quality Program reflective of the statement of work. In addition to CBP, the following areas will be incorporated into the Quality Program:

a. Pre Underway Check List; Readiness for Sea Determination/Safe to Sail Evaluation and

Processes

b. Equipment Operational Red-Line Management

Attachment C: Statement of Work Solicitation N61177-27-R-2006

c. Temporary, Nighttime and Normal Standing Orders

d. Operational Risk Management

e. Initiatives to improve Quality to include means to optimize Government involvement and support

2. The Contractor shall submit a PM Crew Quality Plan, per Attachment J-27 Contract Data Requirements List.

CLIN 0005: Data for CLINs 0001-0004 The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) A, attached hereto.

CLINs 0006-0009: Maintenance The following tasks apply to:

• CLIN 0006 (MMSC-1)

• CLIN 0007 (MMSC-2)

• CLIN 0008 (MMSC-3)

• CLIN 0009 (MMSC-4)

Throughout the PD period, planned maintenance for shipboard equipment and systems will be managed by the PMS 525D 3M Coordinator. When tasked, the Contractor shall be responsible for: organizational

(O) level planned maintenance; facilities maintenance; minimal corrective and emergent repairs; and services support of government responsible intermediate (I) and depot (D) level maintenance performed on and off the ship.

Task 1: Operational-Level (O-Level) Planned Maintenance

The anticipated weekly assigned O-level maintenance is notionally 240 hours, broken down as follows:

• Damage Control: 81 hours

• Deck: 24 hours

• Electrical: 25 hours

• Mechanical:110 hours

1. The Contractor shall be responsible for completing assigned O-level maintenance in accordance with J-16 Attachment, MMSC Maintenance and Material Management (3M) Manual.

2. The Contractor shall provide technical and craftsman manpower, materials, tools, and support to accomplish assigned maintenance requirement cards (MRC) in accordance with Attachment J-17, MMSC PM Crew MRC Deck to include material and verification that tag outs have been properly installed.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

3. The Contractor shall develop PMS Feedback Reports (PFBR), per Attachment J-27 Contract

Data Requirements List, to document problems or deficiencies regarding PMS documentation.

4. The Contractor shall prepare Condition Found Reports (CFRs), per Attachment J-27 Contract Data Requirements List, to identify deficiencies with equipment or systems discovered during conduct of PMS or equipment inspections or operations.

5. The Contractor shall complete work in compliance with Attachment J-6, PMS 525 WAF/Tagout User Manual Instruction.

6. The Contractor shall document costs in a monthly Funds and Manhour Expenditure Report

Task 2: PM Crew Facilities Maintenance

1. The Contractor shall complete facilities maintenance in accordance with Attachment J-18, MMSC Compartment Cleaning Schedule.

2. The PM Crew Master or representative shall support a daily habitability cleanliness walkthrough with the PMS 525 senior rider or representative.

3. The Contractor shall maintain all areas of the ship in a neat, swept, dry, and sanitary condition, with all gear, equipment, and tools stowed in a safe, secure, and orderly fashion.

4. The Contractor shall perform or contract for pest management services to keep the ship free from insects and rodents.

5. The Contractor shall ensure all machinery spaces and cargo holds are maintained in a condition that is: rust-free, painted, and with dry, oil-free bilges.

6. The Contractor shall ensure all interior spaces and furnishings are clean, painted and repaired when damaged.

7. The Contractor shall develop a Facilities Maintenance Accomplishment Report per

Task 3: Services Support of On & Off Ship Maintenance and Repairs The Government will routinely contract third parties to complete maintenance and repairs. In support of this effort:

1. The Contractor shall manage access and tag-out program in support of the third party.

Attachment C: Statement of Work Solicitation N61177-27-R-2006

2. The Contractor shall provide for gas-free engineering services to certify spaces as safe to enter and hot work

3. The Contractor shall maintain an accurate inventory of equipment removed from the vessel.

4. Upon completion of maintenance and/or repairs by the third party, the Contractor shall restore system integrity and ensure operational effectiveness.

Task 4: Corrective Maintenance/Emergent Repairs

1. The Contractor may be tasked to perform corrective maintenance or emergent repairs:

a. Corrective maintenance required to complete planned maintenance/MRC.

b. Infrequent, Temporary, emergent repairs conducted in accordance with commercial best practices and equipment manufacturer guidelines.

Task 5: Casualty Reporting

1. In the event of a casualty, the Contractor shall take appropriate actions and notify the appropriate PMS 525 rider or Lockheed Martin Warranty Rider - immediately. The Contractor shall work with the onboard PMS 525 representative or Lockheed Martin warranty rider to determine corrective actions.

Task 6: Lube Oil, Fuel Oil, Potable Water Sampling and Testing

1. The Contractor shall implement fuel oil, lube oil and potable water sampling and testing programs in accordance with:

a. Attachment J-19, MMSC Lube Oil Quality Management Plan (LOQMP)

b. Attachment J-20, MMSC Fuel Oil Quality Management Plan (FOQMP)

c. Attachment J-21, NAVMED P- 5010, CH 6, Potable Water Quality Management Plan

(PWQMP)

2. The Contractor shall submit a Lube and Fuel Oil Sampling Program per attachment J-27 Contract Data Requirements List.

CLIN 0010: Data for CLINs 0006-0009 The data to be furnished hereunder shall be prepared in accordance with the Contract Data Requirements List, DD Form 1423, Exhibit(s) B, attached hereto.

CLINs 0011-0014 Hotel Support The following tasks apply to:

• CLIN 0011 (MMSC-1)

• CLIN 0012 (MMSC-2)

• CLIN 0013 (MMSC-3)

• CLIN 0014 (MMSC-4)

Attachment C: Statement of Work Solicitation N61177-27-R-2006

Task 1: Hotel Support During PD, the Contractor shall be responsible for providing hotel and medical support for all riders.

MMSC is equipped to berth a maximum of 130 personnel. Table 5 contains the spaces available for crew berthing during underway periods. The remainder of spaces will be reserved for PMS 525 riders.

Space Space Nomenclature # Bunks

01-25-3-L OFFICER SR (2) 2

01-25-8-L COMMANDING OFFICER (SR) 1

01-37-1-L OFFICER SR (2) 2

01-37-2-L OFFICER SR (2) 2

01-38-3-L OFFICER SR (2) 2

01-38-4-L OFFICER SR (2) 2

2-48-4-L OFFICER BUNKROOM (4) 4

2-49-6-L CPO BUNKROOM (6) 6

3-11-0-L CREW LIVING SPACE (18) 18

TOTAL 39

Table 5: MMSC Berthing Plan