DRAFT- J-27 CDRL Package.pdf

PDF 4 MB Posted

Attached to
Request for Information and Industry Day: MMSC PM Crew
Solicitation number
N61177-27-R-2006
Issued by

About this file

This document is a Contract Data Requirements List (CDRL) for the Professional Mariner Crew contract supporting Multi-Mission Surface Combatant (MMSC) vessels 1-4, under contract N61177-27-R-2006 with PMS 525D (Program Manager).

The CDRL specifies 24 data deliverables across five exhibits (A, B, C, D, and E) covering operational, maintenance, and administrative requirements for the PM crew during ship operations and planned maintenance availabilities (PMAV). Key deliverables include: Heavy Weather Plan (A001, 180 days after contract award); Daily Situational Reports (A002, daily at 1800 Eastern); Monthly Cost Reports in Excel format (A003, 30 days after contract award); PM Crew Familiarization Plan (A004, 60 days after contract award); Damage Control Drill Package and Plan (A005, A010, 180 days); Ready for Sea/Safe to Operate Plan (A006, 30 days prior to sailaway); Watch Quarter & Station Bill/Monthly Roster (A009, monthly); Vessel Security Plan (A013, 180 days); Quality Plan (A014, 30 days); PMS Feedback Report (B001); Condition Found Report (B002); Facilities Maintenance Accomplishment (B003, monthly, 30 days after PMAV); Lube and Fuel Oil Sampling Program (B004, quarterly, 30 days after vessel custody); Environmental Management and Safety Plans (D002-D003); PMAV Work Schedule (E001, 5 days prior), Personnel Access List (E002, 5 days prior), and PMAV Metrics (E003, 30 days after PMAV completion). All deliverables require Distribution Statement D marking and include technical data export control warnings. Documents may be maintained in the Contractor's Integrated Data and Product Model Environment (IDPME) with email notification, with paper copies provided to PMS 525 as indicated. Classified items are excluded from digital repositories.

View the file

Other files

File Type Posted
DRAFT- MMSC PM Crew RFP List of J-Attachments.pdf PDF
PM Crew Draft Solicitation.pdf PDF
PM Crew Attachment C SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROFESSIONAL MARINER CREW CONTRACT DATA REQUIREMENTS LIST

GENERAL DD FORM 1423 GLOSSARY AND DATA DELIVERABLES

TABLE FOR EXHIBITS A, B, C, & D

“Block 1”- See DoD FAR Supplement Subpart 4.71 for proper numbering.

“Block 2”- TITLE- As it appears on data acquisition document cited in Item 4.

“Block 3”- SUBTITLE- Further definition of data item (optional entry).

“Block 4”- DATA ITEM DESCRIPTION (DID)- Number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

“Block 5”- CONTRACT REFERENCE- Reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

“Block 6”- TECHNICAL OFFICE- Responsible for ensuring adequacy of the data item.

“Block 7”-Specify requirement for inspection/acceptance of the data item by the Government.

“Block 8”- APPROVAL CODE- An “A” indicates that advance written approval by a Government Representative is required prior to final acceptance by the Government, or prior to publication and distribution of the final version of the document to addresses listed in Block 14. Approval will be defined as to its content, format, and future actions. If a preliminary draft is required it will be indicated in Block 14.

CODE WHEN USED

A Approval I Info Only R Review

“Block 9”- DISTRIBUTION STATEMENT REQUIRED

“Block 10”- FREQUENCY- The data preparation and submission frequency may be indicated in this block using the codes in the table below. If data are of a recurring type, it is to be submitted at the end of the reporting period established in this block unless otherwise indicated in the data preparation instructions in Block 12, 13, 16.

CODE KEY

DAILY Daily WKLY Weekly

BI-WKLY Every two weeks

DRAFT

MTHLY Monthly BI-MTHLY Every two months

QTRLY Quarterly ANNLY Annually SEMIA Every six months ONE/R One time with revisions R/AR Revisions as required AR As required

CP/RQ Change Pages as required DFDEL Deferred delivery One/P One Time Delivery Preliminary Draft ACA After Contract Award

OTIME One-time submittal 2TIME Two separate submittals XTIME Submit X number of times where X takes on a value of three or more

“Block 11”- AS OF DATE- Date for stopping data collection.

“Block 12”- DATE FOR DIRST SUBMISSION- Due date for initial data submission. This is normally the postage date. Actual due dates by year/month/day or keyed to an event show in the table below.

CODE DEFINITION

NLT Not Later Than X DAC Days after Contract Award X DARC Days after Received Comment(s) X DAIC Days after Identification of Change DFDEL Deferred Delivery X DPT Days Prior To X DACM Days after Contract Modification X DPTDCT Days Prior to Design Certification Test X DARP Days after Reporting Period X DATC Days after Test Completion X DPTT Days Prior to Test DR Design Review CDR Critical Design Review CDD Capabilities Development Document ICD Initial Capabilities Document PRR Production Readiness Reviews PSA Post Shakedown Availability R Review RPCD Reference Previous Contract Delivery MS A Milestone A SSSTRP Software System Safety Technical Review Panel SSWG System Safety Working Group VV & A Verification, Validation, and Accreditation WSESRB Weapons Systems Explosive Safety Review Board

(NOTE: “X” is assigned a value indicating the number of days. Example: 30 DAC)

“Block 13”- DATE SUBSEQUENT SUBMISSION/EVENT IDENTIFICATION- Actual due dates by year/month/day or keyed to an event as shown above.

“Block 14”- DISTRIBUTION AND ADDRESSES- Code of addresses and the number of copies (regular or reproducible) each addressee is to receive. Regular copies required will be to the left of the slash mark and reproducible copies will be to the right. The type of the reproducible copies are explained in Block

16. Codes and symbols of the addressees referenced in Block 14 of the DD Form 1423 are explained in Appendix 2. List of Addresses giving full mailing addresses.

“Block 15”- TOTAL- Summation of the requirements listed in Block 14. Number of regular copies required will be to the left of the slash mark and number of reproducibles to the right.

“Block 16”- REMARKS- Contains all pertinent data information not specified elsewhere on this DD Form 1423 and any amplification of other blocks on this form.

Additional Information

To ensure a common baseline of terminology, the following terms with definitions/examples are provided and shall be used by the Contractor.

Work Item A specific alpha-numeric label for every work item in the form AWI-0234. Trial Cards shall be numbered DK2013,01. EXPs shall be formatted as MMSCX-0123 or

PCW-0123

Work Spec An eight- digit number in the form 123-45-678 representing a “4E Work Specification”

Availability The type and number of the specific availability period covered by the CDRL. PSA or IPDA or Emergent. If multiple events in a category are anticipated, then the several events shall be clearly segregated, for example, PSA1 and the second PSA2

Descriptive Title

A short three-to-ten-word description of the work

PL Planning Letter numbered with hull number and sequential numbering such as PL5- 01 for Planning Letter number 1 for MMSCX

EL Execution Letter numbered with hull number and sequential numbering such as EL6-02 for Execution Letter number 2 for MMSCX

ST Straight Time OT Overtime MAT’L Material NTE Not To Exceed PO Purchase Order CFM Contractor Furnished Material GFM Government Furnished Material NSN National Stock Number IMS Integrated Master Schedule

Notes:

(1) In order to reduce cumbersome reporting procedures, this data may be maintained and delivered in a common digital repository within the Contractor’s Integrated Data and Product Model Environment (IDPME). Contract Letter notification via Email. Email notification shall be made available wen data is posted or modified within the IDPME. Where indicated herein, paper copies shall be provided to PMS 525 in addition to posting on the IPDME. Classified items shall not be posted on the IDPME, but should be handled in accordance with Contract requirements.

(2) All Management Plans identified on subsequent option years should be delivered only if they are different than previous submittals.

(3) The Contractor is encouraged to provide recommendations to streamline for cost efficiency.

(4) Rescheduled submitted requirements are subject to adjustment based on mutual agreement between the Contractor and the Data Manager.

MMSC 1, 2, 3, & 4

CONTRACT DATA REQUIREMENTS LIST INDEX

SEQ.

NO/

CDRL

DATA

DESCRIPTION SUBTITLE CONTRACT

REFERENCE DID FREQUENCY 1st SUBMISSION/

SUBSEQUENT

A001 HEAVY

WEATHER PLAN

SEVERE WEATHER

PLAN/PROCEDURES

CLINS 0001-0004,

TASK 1 DI-MGMT-82069 R/AR 180 DAC/30 DARC

A002

TECHNICAL

REPORT –

STUDY/SERVICES

DAILY SITREP CLINS 0001-0004,

TASK 1 DI-MISC-80508B DAILY AT MOVEBOARD/

DAILY

A003

FUNDS AND

MANHOUR

EXPENDITURE

REPORT

PM CREW MONTHLY

COST REPORT

CLINS 0001-0004,

TASK 1

CLINS 0006-0009

TASK 1

CLINS 0011-0014

TASK 1

CLINS 0016-0019

TASK 4

CLINS 0021-0024

TASK 1

DI-FNCL-80331A

(SEE ATTACHMENT) MONTHLY 30 DAC/30DARC

A004

TECHNICAL

REPORT –

STUDY/SERVICES

PM CREW

FAMILIARIZATION/

ORIENTATION PLAN

CLINS 0001-0004,

TASK 2 DI-MISC-80508B R/AR 60 DAC/30DARC

A005

TECHNICAL

REPORT –

STUDY/SERVICES

DAMAGE CONTROL

DRILL PACKAGE

CLINS 0001-0004,

TASK 1 DI-MISC-80508B R/AR 180DAC/30DARC

A006

TECHNICAL

REPORT –

STUDY/SERVICES

READY FOR SEA/SAFE

TO OPERATE

PLAN/CHECKLIST

CLINS 0001-0004,

TASK 2 DI-MISC-80508B AR

30D PRIOR

SAILAWAY

/30D PRIOR U/W:

PSA, IPDA, CMAV

A007

TECHNICAL

REPORT –

STUDY/SERVICES

PM CREW

TEMPORARY

ALTERATION

CLINS 0001-0004,

TASK 2 DI-MISC-80508B AR AS REQUIRED/

30 DARC

A008

TECHNICAL

REPORT –

STUDY/SERVICES

MMSC TRANSIT PLAN CLINS 0001-0004,

TASK 3 DI-MISC-80508B R/AR 7D PRIOR TO U/W;

2DARC

A009

TECHNICAL

REPORT –

STUDY/SERVICES

WATCH QUARTER &

STATION BILL(WQ &

SB)

/MONTHLY ROSTER

CLINS 0001-0004,

TASK 13 DI-MISC-80508B MONTHLY 30 DAC/30 DARC

A010

TECHNICAL

REPORT –

STUDY/SERVICES

PM CREW DAMAGE

CONTROL PLAN

CLINS 0001-0004,

TASK 14 DI-MISC-80508B R/AR 180DAC/30 DARC

A011

TECHNICAL

REPORT –

STUDY/SERVICES

DAMAGE CONTROL

INVENTORY REPORT

CLINS 0001-0004,

TASK 14 DI-MISC-80508B QUARTERLY

UPON VESSEL

SECURITY

TURNOVER/

30 DARC

A012

TECHNICAL

REPORT –

STUDY/SERVICES

HURRICANE

READINESS REPORT

CLINS 0001-0004,

TASK 10 DI-MISC-80508B AR AR

A013

TECHNICAL

REPORT –

STUDY/SERVICES

VESSEL SECURITY

PLAN

CLINS 0001-0004,

TASK 11 DI-MISC-80508B R/AR 180DAC/30 DARC

OPTION AWARD

A014

TECHNICAL

REPORT –

STUDY/SERVICES

QUALITY PLAN CLINs 0001-0004

TASK 16 DI-MISC-80508B ANNUAL 30 DAC/30 DAC

OPTION AWARD

B001

TECHNICAL

REPORT –

STUDY/SERVICES

PMS FEEDBACK

REPORT

CLINS 0006-0009,

TASK 1

CLINs 0021-0024

TASK 1

DI-MISC-80508B

(SEE ATTACHMENT) AR

UPON VESSEL

SECURITY

TURNOVER/

R/AR

B002 CONDITION

FOUND REPORT

CONDITION FOUND

REPORT

CLINS 0006-0009,

TASK 1

CLINs 0021-0024

TASK 1

DI-MGMT-81648A

(SEE ATTACHMENT) AR

UPON VESSEL

SECURITY

TURNOVER/

R/AR

B003

TECHNICAL

REPORT –

STUDY/SERVICES

FACILITIES

MAINTENANCE

ACCOMPLISHMENT

CLINS 0006-0009,

TASK 2 DI-MISC-80508B MONTHLY 30D AFTER PMAV/

R/AR

B004

TECHNICAL

REPORT –

STUDY/SERVICES

LUBE AND FUEL OIL

SAMPLING PROGRAM

CLINS 0006-0009,

TASK 6 DI-MISC-80508B QUARTERLY

30 DAYS AFTER

VESSEL CUSTODY

/R/AR

D001

TECHNICAL

REPORT –

STUDY/SERVICES

ILLEGAL SUBSTANCE

POLICY

CLINS 0016-0019,

TASK 4 DI-MISC-80508B ANNUAL 30 DAC/30 DAC

OPTION AWARD

D002

TECHNICAL

REPORT –

STUDY/SERVICES

ENVIRONMENTAL

MANAGEMENT PLAN

CLINS 0016-0019,

TASK 6 DI-MISC-80508B ANNUAL 180DAC/30 DAC

OPTION AWARD

D003

TECHNICAL

REPORT –

STUDY/SERVICES

SAFETY PLAN CLINS 0016-0019,

TASK 7 DI-MISC-80508B R/AR 180DAC/30 DARC

OPTION AWARD

E001 WORK

SCHEDULE

PMAV WORK

SCHEDULE

CLINS 0021-0024,

TASK 1 DI-MISC-81382 R/AR 5D PRIOR TO PMAV

E002

CONTRACTOR’S

PERSONNEL

ROSTER

PMAV PERSONNEL

ACCESS LIST

CLINS 0021-0024,

TASK 1 DI-MGMT-81834 R/AR 5D PRIOR TO PMAV

E003

TECHNICAL

REPORT-

STUDY/SERVICES

PMAV METRICS CLINS 0021-0024

TASK 1

DI-MISC-80508B

(SEE ATTACHMENT) 30 DAC PMAV 30 DAC PMAV

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF12. DATE OF 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MGMT-82069

A

DIST D

(BLK 16)

R/AR

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A001 HEAVY WEATHER PLAN

PMS 525DSECTION C CLINs 0001-0004

180 DAC

PagesPage 01 of 01

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING

STATEMENTS: DISTRIBUTION STATEMENT D:

DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF

DEFENSE AND U.S. DOD CONTRACTORS ONLY IN ORDER

TO PROTECT CRITICAL TECHNOLOGY, ADMINISTRATIVE

OR OPERATIONAL USE, AND FOR EXPORT CONTROL, 15

JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO

PROGRAM MANAGER, MULTI-MISSION SURFACE

COMBATANT (PMS 525) FOR ALL.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA

WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT

CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE

EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C.,

APP. 2401 ET SEQ.), AS AMENDED. VIOLATIONS OF THESE

EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL

PENALTIES. DISSEMINATE IN ACCORDANCE WITH

PROVISIONS OF DOD DIRECTIVE 5230.25.

SEVERE WEATHER PLAN/PROCEDURES

LT DRAFT

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

R

DIST D

(BLK 16)

DAILY

(BLK 16)

(BLK 16)

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A002 TECHNICAL REPORT STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004

(BLK 16)

PagesPage 01 of 01

(BLK 4) REPLACE “(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC

EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC RESULTS

WHICH LED TO THE CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

"(2) DAILY SITUATIONAL REPORT (CONTRACTORS' FORMAT) (DD MM YYYY)

- FUEL STATE:

- EQUIPMENT CONDITIONS:

- SIGNIFICANT ISSUES:

- TEMPORARY STANDING ORDERS:

- UPCOMING TRAINING OR MAINTENANCE EVENTS:

- SANITATION SERVICES:

- HOUSEKEEPING EFFORTS:"

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION

STATEMENT D: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND U.S.

DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL TECHNOLOGY,

ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT CONTROL, 15 JULY 2019.

OTHER REQUESTS SHALL BE REFERRED TO PROGRAM MANAGER, MULTI-MISSION

SURFACE COMBATANT (PMS 525) FOR ALL.

(BLK 10) DAILY SUBMITTAL IS TO BE PROVIDED TO PMS 525 GOVERNMENT PROVIDED

DISTRO NLT THAN 1800 EASTERN EACH DAY

(BLK 12,13) FIRST SUBMISSION DUE AT PM CREW MOVE ABOARD AND DAILY THEREAFTER

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS

RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR

THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS

AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL

PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25

DAILY SITREP

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-FNCL-80331A (BLK 16)

R

DIST D

(BLK 16)

MTHLY

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

MMSC 1, 2, 3, 4

A003 FUNDS AND MANHOURS EXPENDITURE REPORT

PMS 525D(BLK 16)

30 DAC

PagesPage 01 of 01

(BLK 4) THE FORMAT SHALL BE IN EXCEL PER ATTACHMENT A (MONTHLY COST

REPORT), 1B (MONTHLY MATERIAL REPORT), and 1C (MONTHLY VARIANCE

ANALYSIS REPORT).

EACH MONTH, THE CONTRACTOR SHALL COMPLETE 1A, 1B, AND 1C FOR EACH CLIN.

EXAMPLE: FOR MMSC-1, EACH MONTH, THE CONTRACTOR SHALL COMPLETE:

- 1A, 1B, AND 1C FOR CLIN 0001 (OPERATIONS)

- 1A, 1B, AND 1C FOR CLIN 0006 (MAINTENANCE)

- 1A, 1B, AND 1C FOR CLIN 0011 (HOTEL SUPPORT)

- 1A, 1B, AND 1C FOR CLIN 0016 (SHORE SUPPORT DETACHMENT)

- 1A, 1B, AND 1C FOR CLIN 0021 (PMAV)

SHALL D

(BLK 5) SECTION C, CLINs 0001-0004, 0006-0009, 0011-0014, 0016-0019

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION

STATEMENT D: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE

AND U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL

TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT

CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM

MANAGER, MULTI-MISSION SURFACE COMBATANT (PMS 525) FOR ALL.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS

RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET

SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET

SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO

SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS

OF DOD DIRECTIVE 5230.25.

3. SUBTIT

NTHLY COST REPORT

CONTRACT:

P0P:

REPORT DATE:

DATA DATE:

CLIN:

WORK AUTHORIZED

Prime Labor Hours ($) Prime Material ($) Sub-Contractor Labor Hours ($) Sub-Contractor Material ($) Overhead G&A Profit

TOTAL AUTHORIZED PRICE

SUMMARY COST STATUS

Total Incurred and Committed Value linked to below cells ETC (For Authorized Distributed Budget) Value linked to below cells EAC (For Authorized Distributed Budget) Value linked to below cells

TOTAL COST + PROFIT

OVERALL SUMMAY VARIANCE

Total EAC Compared with Funding (EAC Total - Contract Funding) Total EAC Compared with Budget (EAC Total - Total Auth Budget)

CONTRACT FUNDING thru MOD XXXXXX TOTAL AUTHORIZED BUDGET (Auth. Base Work + Auth. Base Fee)

Authorized Base Work Authorized Base Fee

INCURRED TO DATE

Direct Labor Hours Overtime Hours Direct Labor Dollars Overtime Dollars Overhead Prime Material (from MMR) Subcontracts (Sub Lab + Sub Marial)

Sub Labor Sub Material (from MMR)

G&A

TOTAL INCURRED

COMMITMENTS

Prime Materials Subcontracts G&A

TOTAL COMMITMENTS 0

TOTAL INCURRED + TOTAL COMMITMENTS 0

ATTACHMENT 1A

CLIN _______ Monthly Cost Report (MCR)

LIMITATION of COST PERCENTAGE (Total cost incurred + committed ) / total funding Total cost incurred / total funding

Estimate To Complete (ETC) Direct Labor Hours Direct Labor Dollars Overhead Prime Material Dollars Subcontract Dollars

Subtotal 0 G&A 0

Total ETC 0

Estimate At Completion (EAC) Direct Labor Hours Direct Labor Dollars Overhead Dollars Prime Material Dollars Subcontract Dollars

Subtotal G&A

Profit

TOTAL EAC 0

REMAINING FUNDS & BURN RATE ANALYSIS:

Funding 0 Total Incurred + Committed 0 Remaining Funding 0

Prior week Total Incurred+Committed Burned Rate - Previous Week 0

REPORT DATE:

DATA DATE:

CLIN: XXXXX

ENTITY DATE ITEM QTY COST NOTE

MATERIAL CONSUMMABLE

FUEL

Prime Total Link to MCR

Sub-Contractor Material

Sub-Contractor #1 TRAVEL

PARTS

Sub-Contractor #2 SPARE PARTS

Sub-Contractor #3 COMMERCIAL PORT SERVICE

SEAWAY TRANSIT

Sub-Contractor #3 OTHER STARLINK MONTHLY BILL

Sub-Contractor Total Link to MCR

ATTACHMENT 1B

CLIN _______ Monthly Material Report (MMR)

REPORT DATE:

DATA DATE:

CLIN: XXXXX

Total Value ($) Current Cost Report XXXX

Prior Cost Report YYYY

WEEK

CHANGE

BAC

ACWP (ACTUALS)

ETC

EAC

VARIANCE

COMPONENT

Current Cost Report XXXX

Prior Cost Report YYYY

WEEK

CHANGE VARINCE ANALYSIS

DIRECT HOURS

DIRECT MATERIAL

SUBCONTRACTOR

HOURS

MATERIAL

OVERHEAD

OTHER

ATTACHMENT 1C

CLIN _______ Monthly Variance Analysis Report (VAR)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

A

DIST D

(BLK 16)

R/AR

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A004 TECHNICAL REPORT - STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004

60 DAC

PagesPage 01 of 01

(BLK 4) THE PM CREW ORIENTATION FAMILIARIZATION PLAN SHALL PROVIDE THE

CONTRACTOR'S APPROACH TO SATISFYING THE REQUIREMENTS IN SECTION C, CLIN

0001-0004 AND SECTION L, VOLUME I, FACTOR 2 MANAGEMENT APPROACH.

REPLACE

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC

EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC

RESULTS WHICH LED TO THE CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUBJECT PLAN DETAILS”

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION

STATEMENT D: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE

AND U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL

TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT

CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM

MANAGER, MULTI-MISSION SURFACE COMBATANT (PMS 525) FOR ALL.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS

RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET

SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401

ET SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO

SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS

OF DOD DIRECTIVE 5230.25.

LT

PM CREW FAMILIARIZATION/

ORIENTATION PLAN

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

A

DIST D

(BLK 16)

R/AR

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A005 TECHNICAL REPORT - STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004

180 DAC

PagesPage 01 of 01

(BLK 4)

REPLACE

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC

EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC

RESULTS WHICH LED TO THE CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUBJECT PLAN DETAILS TO MEET SATISFACTORY PERFORMANCE CRITERIA

(3) OBSERVATIONS IN VIEW OF SATISFACTORY PERFORMANCE

(4) PLANS TO IMPROVE PERFORMANCE

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION

STATEMENT D: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE

AND U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL

TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT

CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM

MANAGER, MULTI-MISSION SURFACE COMBATANT (PMS 525) FOR ALL.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS

RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET

SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET

SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO

SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS

OF DOD DIRECTIVE 5230.25.

3. SUBTITLE

DAMAGE CONTROL DRILL PACKAGE

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

A

DIST D

(BLK 16)

AR

(BLK 16)

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A006 TECHNICAL REPORT STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004, TASK 2

(BLK 16)

PagesPage 01 of 01

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION

STATEMENT D: DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND

U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL TECHNOLOGY,

ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT CONTROL, 15 JULY 2019.

OTHER REQUESTS SHALL BE REFERRED TO PROGRAM MANAGER, MULTI-MISSION

SURFACE COMBATANT (PMS 525) FOR ALL.

(BLK 12) FIRST SUBMISSION DUE 30 DAYS PRIOR TO SAILAWAY FROM BUILD YARD

(BLK 13) SUBSEQUENT SUBMISSIONS PRIOR TO UNDERWAY UPON COMPLETION OF PSA,

IPDA, CMAV

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS

RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.)

OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS

AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL

PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE

5230.25.

3. SUBTITLE

READY FOR SEA/SAFE TO

OPERATE PLAN/CHECKLIST

LT

(BLK 4)

REPLACE

“(C) SECTION I – INCLUDES THE FOLLOWING:“(

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC

EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC

RESULTS WHICH LED TO THE CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

“(C) SECTION I – INCLUDES THE FOLLOWING:“(

(1) INTRODUCTION

(2) SUBJECT PLAN DETAILS

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

A

DIST D

(BLK 16)

AR

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A007 TECHNICAL REPORT - STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004

(BLK 16)

PagesPage 01 of 01

(BLK 4)

REPLACE

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC RESULTS WHICH LED

TO THE CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) PROPOSED TEMPALT CHANGES DEPICTING:

(a) TEMPALT CONFIGURATION

(b) INTERFACES BETWEEN TEMPALT CONFIGURATION AND PERMANENT SHIPBOARD

SYSTEM(S)

(c) SCHEDULE TO INSTALL AND REMOVE TEMPALT CONFIGURATION

(d) SCHEDULE TO RESTORE SHIPBOARD SYSTEM(S) AND DISTURBED SURFACES

(e) TEST PLAN ATTESTING RESTORED SHIP SYSTEM(S)

(2) PLAN TO RESTORE SYSTEM TO ORIGINAL CONFIGURATION

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION STATEMENT D:

DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM MANAGER, MULTI-MISSION SURFACE COMBATANT (PMS 525) FOR ALL.

(BLK 12) CHANGE PROPOSALS FOR PM CREW TEMPALTS SHALL BE SUBMITTED 60 DAYS PRIOR TO

DESIRED IMPLEMENTATION DATE OF THE CHANGE.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF

DOD DIRECTIVE 5230.25.

3. SUBTITLE

TEMPORARY ALTERATION

(TEMPALT)

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

A

DIST D

(BLK 16)

R/AR

(BLK 16)

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A008 TECHNICAL REPORT STUDY/SERVICES

PMS 525SECTION C, CLINs 0001-0004

(BLK 16)

PagesPage 01 of 01

(BLK 4)

REPLACE

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC RESULTS WHICH LED TO

THE CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUBJECT PLAN DETAILS

TRANSIT PLAN SHALL INCLUDE PLANNED PORTS OF CALL WITH ANTICIPATED ARRIVAL AND

DEPARTURE DATES THROUGH ARRIVAL IN NORFOLK OR MAYPORT PENDING SCHEDULE PROVIDED BY PMS 525D. ANTICIPATED SERVICES REQUIRED IN EACH PORT SHALL BE INCLUDED IN THE PLAN. THE

CONTRACTOR SHALL USE THE ATTACHED DAILY PLAN FORMAT TO PROVIDE A 5-DAY ROLLING

SCHEDULE DURING THE SAILAROUND. DAILY PLAN QUADS MAY BE INFORMALLY DELIVERED TO THE

SENIOR PMS 525 RIDER AT THE END OF EACH DAY VICE SUBMITTING THROUGH THE CDRL

WORKFLOW."

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION STATEMENT D:

DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY IN

ORDER TO PROTECT CRITICAL TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR

EXPORT CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM MANAGER, MULTI-MISSION SURFACE COMBATANT (PMS 525) FOR ALL.

(BLK 10, 12) 7 DAYS PRIOR TO EACH UNDERWAY

(BLK 13) 2 DARC

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF

DOD DIRECTIVE 5230.25.

MMSC TRANSIT PLAN

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

R

DIST D

(BLK 16)

MTHLY

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A009 TECHNICAL REPORT - STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004,TASK 013

30 DAC

PagesPage 01 of 01

(BLK 4) REPLACE WITH CONTRACTOR-DEVELOPED WQ&SB FORMAT THAT MEETS REQUIREMENTS

OF CLIN 0001

MONTHLY MANNING REPORT SHALL INCLUDE:

- WQ&SB PERSONNEL

- ALL DIRECT CHARGING PRIME CONTRACT PROGRAM MANAGEMENT

- SHORE SUPPORT PERSONNEL

MONTHLY MANNING REPORT SHALL BE CONSISTENT WITH CDRL A003 AND

INCLUDE AFTER HOURS POINT OF CONTACT INFORMATION

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION STATEMENT D:

DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS

ONLY IN ORDER TO PROTECT CRITICAL TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE,

AND FOR EXPORT CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM

MANAGER, MULTI-MISSION SURFACE COMBATANT (PMS 525) FOR ALL.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT

LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH

PROVISIONS OF DOD DIRECTIVE 5230.25.

3. SUBTITLE

WATCH QUARTER & STATION BILL

(WQ&SB)/ MONTHLY ROSTER

30 DARC

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

A

DIST D

(BLK 16)

R/AR

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A010 TECHNICAL REPORT - STUDY/SERVICES

PMS 525SECTION C, CLINs 0001-0004

180 DAC

PagesPage 01 of 01

(BLK 4)

REPLACE

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUMMARY – A BRIEF STATEMENT OF RESULTS OBTAINED FOR THE ANALYTIC EFFORT.

(3) CONCLUSIONS AND THEIR CONDENSED TECHNICAL SUBSTANTIATION’S.

(D) SECTION II – A COMPLETE AND DETAILED DESCRIPTION OF THE ANALYTIC RESULTS WHICH LED TO THE

CONCLUSIONS STATED IN SECTION I ABOVE.”

WITH

“(C) SECTION I – INCLUDES THE FOLLOWING:

(1) INTRODUCTION

(2) SUBJECT PLAN DETAILS”

THE DAMAGE CONTROL PLAN SHALL PROVIDE THE CONTRACTOR'S APPROACH TO SATISFYING THE REQUIREMENTS OF NSTM 079. THE DOCUMENT AT A MINUMUM SHALL SHOW HOW THE CONTRACTOR

INTENDS TO:

A) TAKE PRELIMINARY ACTION BEFORE DAMAGE OCCURS. THIS INCLUDES MAINTENANCE OF

WATERTIGHT AND AIRTIGHT INTEGRITY, PRESERVATION OF RESERVE BUOYANCY AND STABILITY, REMOVAL OF FIRE AND MISSILE HAZARDS, PREVENTIVE MAINTENANCE AND TEST OF EMERGENCY

EQUIPMENT AND DAMAGE CONTROL FITTINGS.

B) MINIMIZE, CONTAIN AND LOCALIZE CASUALTY DAMAGE BY CONTROLLING FLOODING, DEWATERING, FIREFIGHTING AND CARE TO INJURED AND WOUNDED PERSONNEL.

C) ACCOMPLISH EMERGENCY REPAIRS AND RECOVER AS SOON AS POSSIBLE AFTER DAMAGE OCCURS, BY SEGREGATION, RECONFIGURATION, ESTABLISHING CASUALTY POWER, REGAINING A SAFE MARGIN OF

STABILITY AND BUOYANCY, REINFORCING AND SHORING DAMAGED STRUCTURES AND MANNING

ESSENTIAL EQUIPMENT.

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION STATEMENT D:

DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM MANAGER, MULTI-MISSION

SURFACE COMBATANT (PMS 525) FOR ALL.

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD

DIRECTIVE 5230.25.

PM CREW DAMAGE CONTROL PLAN

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

R

DIST D

(BLK 16)

QTRLY

30 DARC

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A011 TECHNICAL REPORT - STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004

PagesPage 01 of 01

16. REMARKS

(BLK 4) REPLACE WITH GOVERNMENT-PROVIDED DC REPAIR LOCKER INVENTORY SHEETS POSTED IN EACH REPAIR LOCKER. CONTRACTOR SHALL PERFORM A QUARTERLY INSPECTION AND INVENTORY OF THE EQUIPMENT CONTAINED WITHIN THE REPAIR LOCKER. EQUIPMENT SHALL BE INSPECTED FOR

ACCURATE QUANTITY AND STOWAGE LOCATION AS WELL AS FOR USABILITY IN AN EMERGENCY

SITUATION.

CONTRACTOR'S SUBMITTAL SHALL INCLUDE:

(a) COMPARTMENT INSPECTED

(b) DATE INSPECTED

(c) INSPECTOR'S NAME AND POSITION

(d) DESCRIPTION, NSN/PART NUMBER, AND QUANTITY OF ANY EQUIPMENT MISSING OR REQUIRING

REPLACEMENT FOR WEAR/DAMAGE

(e) PHOTOS OF DAMAGED/WORN EQUIPMENT

(f) SIGNATURE OF INSPECTOR

(g) SIGNATURE AND DATE OF WORKCENTER SUPERVISOR

MISSING OR WORN/DAMAGED EQUIPMENT SHALL BE IMMEDIATELY REPORTED TO THE PMS 525 HULL

MANAGER OR HIS/HER REPRESENTATIVE AND DOCUMENTED VIA CONDITION FOUND REPORT.

(BLK 9) SHALL BE MARKED WITH THE FOLLOWING STATEMENTS: DISTRIBUTION STATEMENT D:

DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE AND U.S. DOD CONTRACTORS ONLY IN ORDER TO PROTECT CRITICAL TECHNOLOGY, ADMINISTRATIVE OR OPERATIONAL USE, AND FOR EXPORT CONTROL, 15 JULY 2019. OTHER REQUESTS SHALL BE REFERRED TO PROGRAM MANAGER, MULTI-MISSION SURFACE

COMBATANT (PMS 525) FOR ALL.

(BLK 12) FIRST SUBMISSION DUE 7 DAYS PRIOR TO SAILAWAY FROM FINCANTIERI MARINETTE MARINE

WARNING - THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SEC 2751, ET SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979 (TITLE 50, U.S.C., APP. 2401 ET SEQ.), AS AMENDED. VIOLATIONS OF THESE EXPORT LAWS ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN ACCORDANCE WITH PROVISIONS OF DOD DIRECTIVE 5230.25.

MMSC DAMAGE CONTROL INVENTORY REPORT

UPON VESSEL SECURITY TURNOVERLT DRAFT

Form Approved OMB No. 0704-0188

Public reporting burden for this collection of information is estimated to average 100 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 17. Price Group

7. DD 250 REQ7. DD 250 REQ 9. DIST

STATEMENT

REQUIRED

10. FREQUENCY10. FREQUENCY 12. DATE OF FIRST SUBMISSION12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

18. Estimated Total Price

a. ADDRESSEE

b. COPIES

FINAL

8. APP CODE 11. AS OF DATE 13. DATE OF SUBSEQUENT SUBMISSION

Draft Reg Repro

16. REMARKS

15. Total

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

DD Form 1423-1, JUN 90 Previous editions are obsolete

1007/183 S/N 0102-LF-010-5500

A X

DI-MISC-80508B (BLK 16)

R

DIST D

(BLK 16)

LT

(BLK 16)

PMS 525-COR

PMS 525-DM

SUPSHIP

N61177-27-R-2006MMSC 1, 2, 3, 4

A012 TECHNICAL REPORT STUDY/SERVICES

PMS 525DSECTION C, CLINs 0001-0004

(BL…