Availability Milestone Rev-1 (0007-22).docx
DOCX document 20 KB Posted
- Attached to
- ADMIRAL'S BARGE - REPAIRS AND PRESERVATION
- Solicitation number
- N5523622Q0072
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523622Q0072 (A0002) - AMENDMENT 0002.pdf | ||
| N5523622Q0072 (A0001) - AMENDMENT 0001.pdf | ||
| Availability Milestone (0007-22).docx | DOCX document | |
| Admirals Barge 40PE8501 (SOW).docx | DOCX document | |
| N5523622Q0072 - SF18.pdf | ||
| Attachment-A (0007-22).docx | DOCX document | |
| Attachment-B (0007-22).DOC | DOC document | |
| N5523622Q0072 - RFC.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Availability Milestone Ship/Craft HIN: Admiral Barge (40PE8501) Rev-1 (22Mar22)
Milestones/Key Events: 106 days Availability
| Event |
| Scheduled Date |
| Start Availability (Execution) |
| 06 April 2022 |
| Receive Craft by contractor Not Later Than (NLT) |
| 07 April 2022 |
| Arrival Conference |
| 12 April 2022 |
| Preliminary Inspection NLT. |
| 06-08 April 2022 |
| Submit Production Schedule |
| 15 April 2022 |
Submit Condition Found Reports/Long Lead Time Materials (LLTM) NLT.
Submit Commercially Furnish Materials (CFM) NLT.
Submit Electrical Disconnect report NLT.
27 April 2022
Conduct 25% Conference 25 percent of milestone of craft completion will be recognized when all open and inspect reports and all LLTM has been identified and submitted to SUPERVISOR NLT.
Submit the requirements for paint and preservation to SUPERVISOR NLT.
06 May 2022
Conduct 50% Conference 50 percent of milestone of craft completion will be recognized upon the completion of all structural repairs.
Initial Engine Dyno Testing must be accomplished NLT.
Submit Updated CFM Report NLT.
Commence LAR/Boat Alteration Updates NLT.
27 May 2022
Conduct 75% Conference 75 percent of milestone of craft completion will be recognized upon the completion of all preservation requirements.
Engine Dyno Testing Discrepancies MUST be corrected/completed NLT.
Engine installation onboard the craft MUST commence NLT.
24 June 2022
| Production Completion Date |
| 06 July 2022 |
| Contractor Bay Trials & Correction of Discrepancies NLT. |
| 07 July 2022 |
| Final Inspection & Final Bay Trials |
| 14 July 2022 |
| 100% Availability Complete. Each tasking of the basic specs must be completed and accepted by the government NLT. |
| 20 July 2022 |
| Craft Delivery NLT. |
| 21 July 2022 |