Availability Milestone (0007-22).docx

DOCX document 20 KB Posted

Attached to
ADMIRAL'S BARGE - REPAIRS AND PRESERVATION
Solicitation number
N5523622Q0072
Issued by

View the file

Other files

File Type Posted
Availability Milestone Rev-1 (0007-22).docx DOCX document
N5523622Q0072 (A0002) - AMENDMENT 0002.pdf PDF
N5523622Q0072 (A0001) - AMENDMENT 0001.pdf PDF
Admirals Barge 40PE8501 (SOW).docx DOCX document
N5523622Q0072 - SF18.pdf PDF
Attachment-A (0007-22).docx DOCX document
Attachment-B (0007-22).DOC DOC document
N5523622Q0072 - RFC.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Availability Milestone Ship/Craft HIN: Admiral Barge (40PE8501)

Milestones/Key Events: 106 days Availability

Event
Scheduled Date
Start Availability (Execution)
06 April 2022
Receive Craft by contractor Not Later Than (NLT)
07 April 2022
Arrival Conference
12 April 2022
Preliminary Inspection NLT.
06-08 April 2022
Submit Production Schedule
15 April 2022

Submit Condition Found Reports/Long Lead Time Materials (LLTM) NLT.

Submit Commercially Furnish Materials (CFM) NLT.

Submit Electrical Disconnect report NLT.

27 April 2022

Conduct 25% Conference 25 percent of milestone of craft completion will be recognized when all open and inspect reports and all LLTM has been identified and submitted to SUPERVISOR NLT.

Submit the requirements for paint and preservation to SUPERVISOR NLT.

06 May 2022

Conduct 50% Conference 50 percent of milestone of craft completion will be recognized upon the completion of all structural repairs.

Initial Engine Dyno Testing must be accomplished NLT.

Submit Updated CFM Report NLT.

Commence LAR/Boat Alteration Updates NLT.

27 May 2022

Conduct 75% Conference 75 percent of milestone of craft completion will be recognized upon the completion of all preservation requirements.

Engine Dyno Testing Discrepancies MUST be corrected/completed NLT.

Engine installation onboard the craft MUST commence NLT.

24 June 2022

Production Completion Date
06 July 2022
Contractor Bay Trials & Correction of Discrepancies NLT.
07 July 2022
Final Inspection & Final Bay Trials
14 July 2022
100% Availability Complete. Each tasking of the basic specs must be completed and accepted by the government NLT.
20 July 2022
Craft Delivery NLT.
21 July 2022