Exhibit_A_-_Specification_Package_No._BOST-515-16.pdf
PDF 286 KB Posted
- Attached to
- LCAC 80 FY-16 Fleet Modernization Program Federal contract opportunity
- Solicitation number
- N55236-16-R-0002
About this file
Exhibit A - Specification Package No. BOST-515-16
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N55236-16-R-0002-0002.pdf | ||
| N55236-16-R-0002-0001.pdf | ||
| Attachment_1_-_Reference_Information_Sheet.doc | DOC document | |
| Attachment_2_-_Request_for_Specification_Clarification_Form.docx | DOCX document | |
| N55236-16-R-0002.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVSEA BOSTON
LCAC 80 (LCAC 80)
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
SPECIFICATION NUMBER: BOST-515-16
SHIP CHARACTERISTICS
LENGTH OVERALL
MAX. BEAM AT DESIGN WATERLINE
91 FEET
47 FEET
10 INCHES
10 INCHES
EXTREME BEAM INCLUDING APPENDAGES 49 FEET 2 INCHES
DRAFT (MAX. NAVIGABLE) (FWD.)
DRAFT (MAX. NAVIGABLE) (AFT.)
3 FEET
3 FEET
2 INCHES
2 INCHES
LIGHT DISPLACEMENT 89 LONG TON
FULL LOAD DISPLACEMENT 166 LONG TON
HEIGHT OF MAST ABOVE DESIGN WATERLINE 18 FEET 6 INCHES
INDEX
SHIP: LCAC 80 (ACU 45411) BOST-515-16
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-16 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM_NO. TITLE DATE
009-01 General Criteria; accomplish 01/02/2015
009-02 Environmental Compliance Reports for Material Usage at Naval Facilities; provide 01/02/2015
009-03 Toxic and Hazardous Substances; control 01/02/2015
009-04 Quality Management System; provide 01/02/2015
009-05 Temporary Accesses; provide 01/02/2015
009-06 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
01/02/2015
009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish 01/02/2015
009-08 Fire Protection at Contractor's Facility; accomplish 01/02/2015
009-10 Shipboard Asbestos-Containing Material (ACM); control 01/02/2015
009-18 Magnetic Material; control 01/02/2015
009-19 Provisioning Technical Documentation (PTD); provide 01/02/2015
009-20 Government Property; control 01/02/2015
009-21 Logistics and Technical Data; provide 01/02/2015
009-23 Interferences; remove and install 01/02/2015
009-24 Authorization, Control, Isolation, Blanking, and Tagging Requirements; accomplish 01/02/2015
009-28 Fire Prevention Requirements; accomplish 01/02/2015
009-29 Asbestos-Free Pipe Hanger Liner Material; install 01/02/2015
009-34 Fire Protection of Unmanned Vessels at Contractor's Facility; provide 01/02/2015
009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish
01/02/2015
009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for
Commercial Equipment/ Component; provide
01/02/2015
009-40 Requirements for Contractor Cranes, Multi-Purpose Machines and Material Handling Equipment at Naval Facilities; accomplish
01/02/2015
009-59 Organotin Antifouling Material; control 01/02/2015
009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;
provide and manage
01/02/2015
009-61 Shipboard Use of Fluorocarbons; control 01/02/2015
009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 01/02/2015
009-65 Polychlorinated Biphenyls (PCBs); control 01/02/2015
009-67 Integrated Total Ship Testing; manage 01/02/2015
009-69 Heavy Weather/Mooring Plan; provide 01/02/2015
009-70 Confined Space Entry, Certification, Fire Prevention and Housekeeping for Unmanned Vessels; accomplish
01/02/2015
009-72 Physical Security at Private Contractor's Facility; accomplish 01/02/2015 bbessette Cross-Out 009-07 Confined Space Entry, Certification, Fire Prevention and Housekeeping; accomplish 01/02/2015 bbessette Cross-Out 009-08 Fire Protection at Contractor's Facility; accomplish 01/02/2015 bbessette Cross-Out 009-10 Shipboard Asbestos-Containing Material (ACM); control 01/02/2015 bbessette Cross-Out 009-29 Asbestos-Free Pipe Hanger Liner Material; install 01/02/2015 bbessette Cross-Out 009-34 Fire Protection of Unmanned Vessels at Contractor's Facility; provide 01/02/2015 bbessette Cross-Out 009-35 Confined Space Entry, Certification, Fire Prevention Utilizing Military Fire Watches, and Housekeeping; accomplish 01/02/2015 bbessette Cross-Out 009-39 Technical Manual Contract Requirement (TMCR) for New Technical Manuals for Commercial Equipment/ Component; provide 01/02/2015 bbessette Cross-Out 009-59 Organotin Antifouling Material; control 01/02/2015 bbessette Cross-Out 009-60 Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration;
provide and manage 01/02/2015 bbessette Cross-Out 009-64 Synthetic Fire-Resistant Hydraulic Fluid; control 01/02/2015 bbessette Cross-Out 009-65 Polychlorinated Biphenyls (PCBs); control 01/02/2015 bbessette Cross-Out 009-72 Physical Security at Private Contractor's Facility; accomplish 01/02/2015 bbessette Cross-Out 009-18 Magnetic Material; control 01/02/2015 bbessette Cross-Out 009-28 Fire Prevention Requirements; accomplish 01/02/2015
ITEM_NO. TITLE DATE
009-73 Shipboard Electrical/Electronic/Fiber Optic Cable; remove, relocate, repair, and install
01/02/2015
009-74 Occupational, Safety and Health Requirements; accomplish 01/02/2015
009-77 Cofferdam Requirements; accomplish 01/02/2015
009-79 Government Owned Material (GOM); status reporting 01/02/2015
009-80 Ship's Facilities; provide 01/02/2015
009-81 Compartment Closeout; accomplish 01/02/2015
009-82 Data Requirements When Installing an Equal Component Vice Specified Component; provide
01/02/2015
009-83 Wire Rope Fitting Verfication; provide 02/19/2015
009-84 Accountability of Temporary Fasteners; provide 02/13/2015
009-86 Recovery of Chlorofluorocarbon (CFC) Refrigerants and Fire Suppressant Halon (H) Materials; accomplish
02/13/2015
009-87 Chemical disinfection Procedures; accomplish 02/13/2015
009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify
01/02/2015
009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes;
accomplish
01/02/2015
009-93 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution Prevention Act (PPA) Information; provide
01/02/2015
009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish 01/02/2015
009-95 Mechanically Attached Fittings (MAF's) for Piping Systems; install 01/02/2015
009-97 Shipbuilding and Ship Repair Operations National Emission Standard for Hazardous Air Pollutants (NESHAPS) for Surface Coating Information; provide
01/02/2015
009-99 Ship Departure Report; provide 01/02/2015
009-100 Ship's Stability Process Control Procedure (PCP); maintain 01/02/2015
009-101 Requirements for Entry to and Departure from Contractor's Facility; accomplish 01/02/2015
009-102 Alteration Verification; provide 01/02/2015
009-103 Weight and Moment Change Data; provide 01/02/2015
009-106 Work Authorization Form Coordinator (WAFCOR); provide 01/02/2015
009-108 Aircraft Carrier Requirements for Entry to, Movement within, and Departure from Contractor's Facility; accomplish
01/02/2015
009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels;
accomplish
01/02/2015
009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels; accomplish 01/02/2015
009-111 Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration;
provide and manage
01/02/2015
009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish 01/02/2015
009-118 CG Deck Loading; accomplish 01/02/2015
009-120 Fact Finding and Critique of Unplanned Events; manage 01/02/2015
009-121 Ship Assessment/Inspection Requirements; provide 01/02/2015 bbessette Cross-Out 009-77 Cofferdam Requirements; accomplish 01/02/2015 bbessette Cross-Out 009-80 Ship's Facilities; provide 01/02/2015 bbessette Cross-Out 009-83 Wire Rope Fitting Verfication; provide 02/19/2015 bbessette Cross-Out 009-87 Chemical disinfection Procedures; accomplish 02/13/2015 bbessette Cross-Out 009-88 Collection, Holding and Transfer (CHT) and Mogas Tanks, Spaces, and Piping, including Sewage or Mogas-Contaminated Tanks, Spaces, and Piping; certify 01/02/2015 bbessette Cross-Out 009-94 General Environmental Requirements for Work at Contractor's Facility; accomplish 01/02/2015 bbessette Cross-Out 009-100 Ship's Stability Process Control Procedure (PCP); maintain 01/02/2015 bbessette Cross-Out 009-109 Special Requirements for Non-SUBSAFE Work on SUBSAFE-Certified Vessels;
accomplish 01/02/2015 bbessette Cross-Out 009-110 Special Requirements for Non-Nuclear Work on Nuclear Vessels; accomplish 01/02/2015 bbessette Cross-Out 009-112 Prevention of Radiographic-Inspection Ionizing-Radiation Hazards; accomplish 01/02/2015 bbessette Cross-Out 009-118 CG Deck Loading; accomplish 01/02/2015 bbessette Cross-Out 009-121 Ship Assessment/Inspection Requirements; provide 01/02/2015 bbessette Cross-Out 009-89 Purchase and Inspection Requirements for Contractor Furnished Anodes;
accomplish 01/02/2015 bbessette Cross-Out 009-95 Mechanically Attached Fittings (MAF's) for Piping Systems; install 01/02/2015 bbessette Cross-Out 009-103 Weight and Moment Change Data; provide 01/02/2015 bbessette Cross-Out 009-106 Work Authorization Form Coordinator (WAFCOR); provide 01/02/2015 bbessette Cross-Out 009-108 Aircraft Carrier Requirements for Entry to, Movement within, and Departure from Contractor's Facility; accomplish 01/02/2015 bbessette Cross-Out 009-101 Requirements for Entry to and Departure from Contractor's Facility; accomplish 01/02/2015
DATETITLEITEM NO.
CATEGORY II. FY-16 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER
009-11 Insulation and Lagging Requirements; accomplish 17-Jan-13
009-12 Welding, Fabrication, and Inspection Requirements;
accomplish
07-Nov-13
009-25 Structural Boundary Test; accomplish 17-Jan-13
009-32 Cleaning and Painting Requirements; accomplish 07-Nov-13
009-71 Testing Requirements for Piping Systems; accomplish 17-Jan-13
ITEM NO. TITLE
Hazardous Waste Produced on Naval Vessels; control077-01-001
Cushion Vane Assembly; repair248-11-002
LCAC Craft Change Document CCD-553 Rev 00, Cushion Vane Fitting Modification; accomplish
248-90-001
LCAC Craft Change Document CCD-165 Rev 02, Oily Waste Drain Modification; accomplish
261-90-001
LCAC Craft Change Document 445 Rev 01, Incr 01, Limited Compartment Painting; accomplish
631-90-002
LCAC Craft Change Document CCD-571 Rev 00, LCAC Weapon Stowage Modification; accomplish
713-85-001
Cleaning and Pumping; accomplish992-31-001
PRELIMINARY SPECIFICATION
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 077-01-001
COAR: 16 PCN: LC80-B078
CMP: NONE
PLANNER: DEMERS, RAY
SSP: BOST-515-16 1 of 5 ITEM NO: 077-01-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Hazardous Waste Produced on Naval Vessels; control
1.2 Location of Work:
1.2.1 Throughout the Ship
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Resource Conservation and Recovery Act (RCRA)
2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act
2.3 Applicable Hazardous Waste Manifest Form
2.4 10 U.S.C. 7311
3. REQUIREMENTS:
3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with 2.1 and 2.2.
3.1.1 When a Navy generator number is required by this Work Item, submit the original of 2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.
3.1.2 Manage and transport for Navy disposal, Navy-generated
hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.
Report: Hazardous Waste Manifest Date: + 2
3.1.3 Submit one legible copy, in hard copy or approved
transferrable media, of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.
3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.
3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's Force or Navy employees (termed Navy- Generated Hazardous Waste) on board the vessel shall only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor shall obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411)
SSP: BOST-515-16 2 of 5 ITEM NO: 077-01-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor- Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law.
Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste shall only bear a generator number issued to the contractor.
3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) shall bear a generator identification number issued to the contractor pursuant to applicable law and shall also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste shall bear a generator identification number issued to the contractor and shall also cite in the remarks block a generator identification number issued to the Navy. The contractor shall sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the manifest is required for disposal. The contractor shall obtain SUPERVISOR's concurrence with the categorization of the wastes as co-generated before completion of the manifest. Manifests prepared shall be presented to the SUPERVISOR for completion after the hazardous waste has been identified.
3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor shall notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.
3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy shall notify the contractor within three business days of receipt of notification by the state. The contractor shall dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.
3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:
AMOUNT
TYPE NAVY CO-GENERATED CONTRACTOR
Acid Solutions (may include __________ ____________ __________
SSP: BOST-515-16 3 of 5 ITEM NO: 077-01-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
spent sulfamic, citric, chromic, nitric, sulfuric, hydrochloric, etc.)
Ethylene Glycol (Antifreeze) __________ ____________ __________
Sodium Hydroxide __________ ____________ __________
Cleaning Solvents __________ 5 Gallons __________
Sodium Phosphates (Tri, Bi, __________ ____________ __________ or Mono)
Fluorocarbons __________ ____________ __________
Morpholine __________ ____________ __________
Sodium Chromates __________ ____________ __________
Hydrazine __________ ____________ __________
Carbohydrazide __________ ____________ __________
Methyl Ethyl Ketone __________ ____________ __________
Spent Abrasive Blast Material __________ One Ton __________
(contaminated with a known hazardous waste)
Trichloroethane __________ 5 Gallon __________
Miscellaneous Chemicals __________ 5 Gallon 10 Gallon
(Ignitable)
Miscellaneous Chemicals __________ 5 Gallon __________
(Corrosive)
Miscellaneous Chemicals __________ ____________ __________
(TCLP Toxic)
Miscellaneous Chemicals __________ 10 Gallon __________
(Reactive)
Oil (Synthetic) __________ 5 Gallon __________
Paints (Enamel, Latex, __________ 10 Gallon __________
Epoxy, thinners, oil based, rubber paint, nonskid, lacquer, remover, varnishes)
Paints (May include lead, __________ 5 Pounds __________ cadmium, or chrome)
Paint Strippers (phenols, __________ ____________ __________ lead, chromium)
SSP: BOST-515-16 4 of 5 ITEM NO: 077-01-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Sludge (Contaminated with __________ 25 Gallon _________ a known hazardous waste)
Wool Felt (contaminated __________ ____________ _________ with chromium and PCB's)
Ventilation Debris/Residue
(heavy metals, e.g., cadmium, chromium) __________ ____________ _________
Insulation (May contain lead) __________ 40 Square Feet _________
Oily Rags __________ 30 Pounds _________
3.6 Notify the SUPERVISOR at least one working day prior to shipment of hazardous waste for disposal.
Report: Hazardous waste listing Date: + 2
3.7 Submit one legible copy, in hard copy or approved transferrable media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the SUPERVISOR.
3.7.1 The report shall include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.
3.7.1.1 Chemical analysis shall be accomplished by laboratories with state or EPA approved quality assurance programs.
3.7.2 The contractor shall make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.
3.8 Nothing contained in this Work Item shall relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.
4. NOTES:
4.1 The waste listed in 3.5 is based on the best information available at the time of preparation of the solicitation. Hazardous waste generated during the actual performance of the work may vary in type or amount from waste listed in 3.5 which may result in renegotiation for credit or increase pursuant to Paragraph (b) of 2.4. The contractor is expected to use best management practice to identify and dispose of all hazardous waste. Some of the substances listed in 3.5 may be neutralized, recycled, or otherwise removed from the requirements of Subtitle C of 2.1. Inclusion of these substances in the waste listed in
3.5 does not preclude the contractor from taking action consistent with
2.1 to reduce or eliminate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2.
Processes that add hazardous constituents to the bilges may require that
SSP: BOST-515-16 5 of 5 ITEM NO: 077-01-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
bilge water be disposed of as a hazardous waste.
4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.4. They are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.
4.2 Hazardous wastes are determined by one or more of the following methods:
4.2.1 Chemical analysis which shows that the material
characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.
4.2.2 Reference to a Material Safety Data Sheet (MSDS).
4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.
4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 248-11-002
COAR: 16 PCN: LC80-B248
CMP: NONE
PLANNER: DEMERS, RAY
SSP: BOST-515-16 1 of 6 ITEM NO: 248-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Cushion Vane Assembly; repair
1.2 Location of Work:
1.2.1 Frames 6-10, Underwater Hull, Port
1.2.2 Frames 6-10, Underwater Hull, Starboard
1.3 Identification:
1.3.1 Quantity (8 EA), Cushion Vane Assembly, 56 inch X 13 inch, 6061 Aluminum, Port, (4 Each Forward and 4 Each Aft)
1.3.2 Quantity (8 EA), Cushion Vane Assembly, 56 inch X 13 inch, 6061 Aluminum, Starboard, (4 Each Forward and 4 Each Aft)
2. REFERENCES:
2.1 Standard Items
2.2 568-5749819 Rev K, LCAC Mechanical Installation Vane Control
2.3 S9248-AA-TMM-080, Operation and Maintenance Manual for (SLEP) Landing Craft, Air Cushion (LCAC) Lift System Fans and Ducting (LCAC 80)
2.4 248-5749558 Rev I, LCAC Vane Assy and Installation
2.5 248-5749597 Rev W, LCAC Vane Details
2.6 101-5749137 Rev AK, LCAC Flotation Compt Assembly
2.7 101-5749968 Rev M, LCAC Details-Flotation Compt
2.8 111-5749144 Rev M, LCAC Plating Installation, Wet Deck
2.9 111-5749145 Rev P, LCAC Plating Details, Wet Deck
2.10 122-5749177 Rev K, LCAC Frame 6A, Assembly
2.11 122-5749183 Rev L, LCAC Frame 10, Assembly
2.12 101-5749137 Rev PF, SLEP Flotation Compartment Assembly
2.13 111-5749144 Rev PB, SLEP Plating Installation Wet Deck
2.14 122-5749183 Rev P-, SLEP Frame 10 Assembly
2.15 7614-947918 Rev LD, Landing Craft Air Cushion Process Specification for Polyurethane (Erosion) Protection
3. REQUIREMENTS:
(V)(G) "JOINT VISUAL INSPECTION"
3.1 Accomplish a joint visual inspection with the SUPERVISOR of the equipment listed in 1.3 and located in 1.2 for proper operation and alignment in both fully opened and fully closed positions using 2.2 and
SSP: BOST-515-16 2 of 6 ITEM NO: 248-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
2.3 for guidance.
Report: Inspection Results Date: + 3
3.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.1 to the SUPERVISOR.
3.2 Disassemble each cushion vane assembly listed in 1.3 and located in 1.2, including bearings, flanges and linkage using Paragraphs 3-4.2, 6-
5.29 and 6-5.30 of 2.3, 2.4 and 2.5 for guidance.
3.3 Clean the exterior surfaces of the equipment listed in 1.3 and located in 1.2, by low pressure clean fresh water wash method. Surfaces shall be cleaned free of salt, sand and foreign matter.
3.3.1 Accomplish a visual inspection of each cushion vane assembly for structural integrity, deterioration, pitting, cracks, weld repairs and areas of damage or distortion.
Report: Inspection Results Date: + 3
3.3.1.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.3.1 to the SUPERVISOR.
3.4 Machine areas of each cushion vane assembly listed in 1.3 and located in 1.2 as designated by the SUPERVISOR resulting from 3.3.1.1, to original dimensions and contours in accordance with 2.5.
3.4.1 Remove existing and install new a total of 40 square feet of deteriorated, warped or unserviceable plating in way of repairs as designated by the SUPERVISOR in accordance with 2.6 through 2.11, as modified by 2.12 through 2.14.
3.4.1.1 Minimum size of inserts, shall be one square foot.
3.4.2 Accomplish the requirements of 009-12 of 2.1, including Table 4, Column C, Lines One through 7.
3.4.3 Install new polyurethane tape to the leading edge of each cushion vane in accordance with Note 14 of 2.5, and 2.15.
3.5 Assemble and install each cushion vane assembly listed in 1.3 and located in 1.2, in accordance with Paragraphs 6-5.29 and 6-5.30 of 2.3,
2.4 and 2.5, using Fig.8-19 of 2.3 for guidance. Remove existing, fit, and install new the following parts:
TOTAL
QUANTITY NAME INDEX REF. FIGURE PART
REQUIRED OF PART NO. NO. NO. NO.
32 EA Nut, Self-locking 5 2.3 8-19 MS21044C4
8 EA Shim Pack 6 2.3 8-19 5749597-121
8 EA O-Ring 8 2.3 8-19 MS28775-326
SSP: BOST-515-16 3 of 6 ITEM NO: 248-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
8 EA PIN Torque Tube 9 2.3 8-19 5749597-047
8 EA Washer, Thrust 13 2.3 8-19 5749597-113
8 EA Gasket, rubber 14 2.3 8-19 5749597-053
32 EA Washer, Flat 18 2.3 8-19 AN960C416
32 EA Washer, Flat 19 2.3 8-19 75775CY-4
32 EA Nut, Self-locking 20 2.3 8-19 MS21044C4
0 EA Rivet, Blind 47 2.3 8-19 NAS1399C8-5 (Not required. See 4.1)
48 EA Shim Pack 72 2.3 8-19 5749597-117
16 EA O-Ring 73 2.3 8-19 MS28775-120
48 EA Shim Pack 74 2.3 8-19 5749597-119
16 EA Washer, Thrust 75 2.3 8-19 5749597-115
32 EA Washer, Flat 81 2.3 8-19 75775CY-4
32 EA Washer, Flat 82 2.3 8-19 AN960C416
32 EA Nut, Self-locking 83 2.3 8-19 MS21044C4
32 EA Washer, Flat 91 2.3 8-19 75775CY-4
32 EA Washer, Flat 92 2.3 8-19 AN960C416
32 EA Nut, Self-locking 93 2.3 8-19 MS21044C4
8 EA Gasket, Rubber 94 2.3 8-19 5749597-053
8 EA PIN Torque Tube 98 2.3 8-19 5749597-047
8 EA Washer, Thrust 99 2.3 8-19 5749597-113
8 EA O-Ring 101 2.3 8-19 MS28775-326
80 EA Screw 44 2.4 N/A MS24694-C100
80 EA Nut 45 2.4 N/A MS21044C4
80 EA Washer 48 2.4 N/A AN960C416
3.5.1 Remove existing, fit, and install new the following parts provided as Government Furnished Material (GFM) and listed in 5.1:
TOTAL
QUANTITY NAME INDEX REF. FIGURE PART
REQUIRED OF PART NO. NO. NO. NO.
8 EA Torque Tube Ext. One 2.3 8-19 5749597-123
8 EA Coupling 2 2.3 8-19 5749597-107
8 EA Washer, Teflon 7 2.3 8-19 5749597-111
8 AY Torque Tube Assy 10 2.3 8-19 5749597-005 (Incl Index Nos. 11 & 12)
8 EA Vane Attach Fitting 15 2.3 8-19 5749597-049
SSP: BOST-515-16 4 of 6 ITEM NO: 248-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
32 EA Bolt, Machine 16 2.3 8-19 NAS6704L18
32 EA Bolt, Machine 17 2.3 8-19 NAS6704L15
16 EA Bolt, Machine 77 2.3 8-19 NAS6704L18
16 EA Bolt, Machine 78 2.3 8-19 NAS6704L21
16 EA Bolt, Machine 79 2.3 8-19 NAS6704L15
16 EA Bolt, Machine 80 2.3 8-19 NAS6704L20
16 EA Bearing, Spherical 84 2.3 8-19 KSC171216V
8 EA Vane Attach Fitting 86 2.3 8-19 5749597-049
16 EA Bolt, Machine 87 2.3 8-19 NAS6704L18
16 EA Bolt, Machine 88 2.3 8-19 NAS6704L21
16 EA Bolt, Machine 89 2.3 8-19 NAS6704L15
16 EA Bolt, Machine 90 2.3 8-19 NAS6704L20
8 AY Torque Tube Assy 95 2.3 8-19 5749597-003 (Incl Index Nos. 96 & 97)
8 EA Washer, Teflon 100 2.3 8-19 5749597-111
3.5.2 Template exact size, configuration, and location from existing landing craft conditions.
3.5.3 Turnover unused parts and fasteners to the SUPERVISOR for disposition.
3.6 Install, lubricate and align each cushion vane assembly listed in
1.3 and located in 1.2, and associated linkage in accordance with 2.2, Paragraph 6-4 of 2.3, 2.4 and 2.5.
(V)(G) "OPERATIONAL TEST"
3.7 Accomplish an operational test of the equipment listed in 1.3 and located in 1.2, to verify proper operation and alignment in accordance with Paragraph 2-3 of 2.3.
3.7.1 Accomplish adjustments in accordance with Paragraph 6-4 of 2.3.
Report: Operational Test Results Date: + 3
3.7.2 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.7 to the SUPERVISOR.
4. NOTES:
4.1 LCAC Craft Change Document-553 Rev 00, Cushion Vane Fitting Modification; accomplish is covered by Work Item 248-90-001.
4.2 Weld repairs required for Cushion Vane Assemblies listed in 1.3 shall be accomplished by the Assault Craft Unit.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
SSP: BOST-515-16 5 of 6 ITEM NO: 248-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART PIECE NO. REF NO.
NATIONAL
STOCK NO.
REQ
PARA NO.
1. 8 EA
Torque Tube Ext, 5749597-123 One 2.3
2030-01- 235-7648 3.5.1
2. 8 EA
Coupling, 5749597-107 2 2.3
2030-01- 236-7230 3.5.1
3. 8 EA
Washer, Teflon, 5749597-111 7 2.3
5365-01- 226-9220 3.5.1
4. 8 AY
Torque Tube Assy, 5749597- 005 10 2.3
4710-01- 219-5480 3.5.1
5. 8 EA
Vane Attachment Fitting, 5749597-049 15 2.3
2040-01- 327-3159 3.5.1
6. 32 EA
Bolt, Machine
NAS6704L18 16 2.3
5306-01- 492-1063 3.5.1
7. 32 EA
Bolt, Machine
NAS6704L15 17 2.3
5306-01- 492-1013 3.5.1
8. 16 EA
Bolt, Machine
NAS6704L18 77 2.3
5306-01- 492-1063 3.5.1
9. 16 EA
Bolt, Machine
NAS6704L21 78 2.3
5306-01- 492-1511 3.5.1
10. 16 EA
Bolt, Machine
NAS6704L15 79 2.3
5306-01- 492-1013 3.5.1
11. 16 EA
Bolt, Machine
NAS6704L20 80 2.3
5306-01- 492-1485 3.5.1
12. 16 EA
Bearing, Spherical, KSC171216V 84 2.3
3120-01- 218-1305 3.5.1
13. 8 EA
Vane Attachment Fitting, 5749597-049 86 2.3
2040-01- 327-3159 3.5.1
14. 16 EA
Bolt, Machine
NAS6704L18 87 2.3
5306-01- 492-1063 3.5.1
15. 16 EA
Bolt, Machine
NAS6704L21 88 2.3
5306-01- 492-1511 3.5.1
16. 16 EA
Bolt, Machine
NAS6704L15 89 2.3
5306-01- 492-1013 3.5.1
17. 16 EA
Bolt, Machine
NAS6704L20 90 2.3
5306-01- 492-1485 3.5.1
18. 8 AY
Torque Tube Assy, 5749597- 003 95 2.3
2040-01- 219-2406 3.5.1
19. 8 EA
Washer, Teflon, 5749597-111 100 2.3
5365-01- 226-9220 3.5.1
5.2 PUSH MATERIAL:
SSP: BOST-515-16 6 of 6 ITEM NO: 248-11-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 248-90-001
COAR: 16 PCN: LC80-B553
CMP: NONE
PLANNER: DEMERS, RAY
SSP: BOST-515-16 1 of 2 ITEM NO: 248-90-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: LCAC Craft Change Document CCD-553 Rev 00, Cushion Vane Fitting Modification; accomplish
1.2 Location of Work:
1.2.1 Frames 6-10, Underwater Hull, Port
1.2.2 Frames 6-10, Underwater Hull, Starboard
1.3 Identification:
1.3.1 Quantity (16 EA), Vane Pin Support Fitting Assembly, (Part No.
5749597-029 of 2.1)
2. REFERENCES:
2.1 248-5749597 Rev W, LCAC Vane Details
2.2 LCAC Craft Change Document CCD-553 Rev 00, Cushion Vane Fitting Modification
2.3 S9248-AA-TMM-080, Operation and Maintenance Manual for (SLEP) Landing Craft, Air Cushion (LCAC) Lift System Fans and Ducting (LCAC 80)
2.4 248-5749558 Rev I, LCAC Vane Assy and Installation
3. REQUIREMENTS:
3.1 Accomplish removals, modifications and installations for LCAC Craft Change Document CCD-553 Rev 00, Cushion Vane Fitting Modification for the equipment listed in 1.3 and located in 1.2 in accordance with 2.2, using 2.1, 2.3 and 2.4 for guidance.
3.1.1 Template exact size, configuration, and location from existing landing craft conditions.
3.1.2 Assemble and install each cushion vane assembly disassembled in 3.1 in accordance with 2.1 and 2.4, using Paragraphs 6-5.29, 6-
5.30 and Figure 8-19 of 2.3 for guidance.
3.1.3 Remove existing, fit, and install new the following parts:
TOTAL
QUANTITY NAME PIECE REF. FIGURE PART
REQUIRED OF PART NO. NO. DRAWING NO. NO.
16 EA Vane Pin Ftg N/A 2.2 N/A 5749597-029
80 EA Screw 44 2.4 N/A MS24694-C100
80 EA Nut, Self-Lkg 45 2.4 N/A MS21044C4
80 EA Washer 48 2.4 N/A AN960C416
(V)(G) "OPERATIONAL TEST"
SSP: BOST-515-16 2 of 2 ITEM NO: 248-90-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.2 Accomplish an operational test of the equipment listed in 1.3 and located in 1.2 to verify proper operation and alignment in accordance with Paragraph 2-3 of 2.3.
3.2.1 Accomplish adjustments in accordance with Paragraph 6-4.5 of 2.3.
Report: Test Results Date: + 3
3.2.2 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.2 to the SUPERVISOR.
4. NOTES:
4.1 Known source for manufacturing materials (Part No. 2889K156), for Cushion Vane Pin Support Fitting Assembly listed in 1.3.1:
McMaster-Carr Supply Co.
600 N. County Line Rd.
Elmhurst, Il. 60126-2081
Tel: (330)995-5500
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 261-90-001
COAR: 16 PCN: LC80-B165
CMP: NONE
PLANNER: DEMERS, RAY
SSP: BOST-515-16 1 of 3 ITEM NO: 261-90-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: LCAC Craft Change Document CCD-165 Rev 02, Oily Waste Drain Modification; accomplish
1.2 Location of Work:
1.2.1 Throughout The Craft
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 LCAC Craft Change Document CCD-165 Rev 02, Oily Waste Drain
2.3 261-6905672 Rev P, CraftAlt 165D LCAC Drain System Drain Modification Incidental to Oily Waste System
2.4 261-6386473 Rev PE, SLEP Main Fuel Feed & Crossover Instl
2.5 261-6386377 Rev PA, SLEP APU Fuel Feed and Stripping Instl
2.6 151-5749264 Rev P, LCAC Shelf Assembly - Engine Compartment
2.7 505-6800352 Rev B, LCAC Non-Conductive Insert for CRES Fittings Thru Alum. Decks Bulkheads & Brackets
2.8 S6240-A9-MAN-010 Rev 05, Landing Craft, Air Cushion (LCAC) Welding and Inspection Manual
3. REQUIREMENTS:
3.1 Accomplish removals, modifications and installations for LCAC Craft Change Document CCD-165 Rev 02, Oily Waste Drain Modification, at locations listed in 1.2 in accordance with 2.2 and 2.3, using 2.4 through
2.7 for guidance.
3.1.1 Template exact size, configuration, and location from existing landing craft conditions.
3.1.2 Accomplish the requirements of 009-12 of 2.1, including Table One, Column A, Lines One through 10.
3.1.2.1 Accomplish the requirements of Paragraph 13-8 of 2.8 for approved Weld Procedure Number GT-A52 for GTAW Aluminum Tube and Pipe.
3.1.3 Remove unused hangers, clips, brackets, and supports resulting from piping removals in 3.1.
3.1.4 Chip and grind surfaces flush and smooth in way of removals.
3.1.5 Install new supports for piping installed in 3.1 to prevent vibration, in accordance with 2.3.
3.1.6 Install deck plating and bulkhead inserts in way of removals
SSP: BOST-515-16 2 of 3 ITEM NO: 261-90-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
which no longer services piping in accordance with 2.3, using new aluminum material conforming to 5456-H116.
3.1.6.1 Fair-in existing plating adjoining each new insert.
3.1.7 Accomplish the requirements of 009-12 of 2.1, including Table 4, Column C, Lines One through 7.
3.1.7.1 Accomplish nondestructive testing in accordance with
Line 10.
3.1.8 Accomplish the requirements of 009-25 of 2.1 for the local air hose test of each new deck and bulkhead insert, and each new attachment weld to watertight structure. Allowable leakage: None.
3.2 Accomplish the requirements of 009-71 of 2.1 for new and disturbed piping.
3.2.1 Accomplish a static head pressure test of new and disturbed oily waste drain piping in accordance with Test Note T-1 of 2.3.
3.2.1.1 Test pressure shall be 2 PSIG, using clean, fresh water, when the hydrostatic test option is selected.
3.2.1.2 Allowable leakage at new and disturbed joints: None.
3.2.2 Remove test fluid upon completion of hydrostatic pressure test. Allowable residual fluid: None.
3.2.3 Verify oily waste system unobstructive flow in accordance with Test Note T-3 of 2.3.
4. NOTES:
4.1 Known sources for P-2 Tubing listed in 2.3:
Specialized Metals
3701 NW 126th Ave. Coral Springs, FL 33065
Tel: 954-340-9225 Fax: 954-340-9570
POC: Jason Maloney ext. 308
Tech Steel & Materials
1180 Lincoln Ave
Holbrook, NY 11741
Tel: 631-218-0013 Fax: 631-218-0141
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SSP: BOST-515-16 3 of 3 ITEM NO: 261-90-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 631-90-002
COAR: 16 PCN: LC80-B445
CMP: NONE
PLANNER: ROBERTS, JEARLD
DEMERS, RAY
SSP: BOST-515-16 1 of 3 ITEM NO: 631-90-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: LCAC Craft Change Document 445 Rev 01, Incr 01, Limited Compartment Painting; accomplish
1.2 Location of Work:
1.2.1 Void (2-6-3-Q)
1.2.2 Void (2-6-4-Q)
1.2.3 Flotation Void (2-7-1-V)
1.2.4 Flotation Void (2-7-2-V)
1.2.5 Flotation Void (2-8-1-V)
1.2.6 Flotation Void (2-8-2-V)
1.2.7 Stowage and Electronic Equipment Space (1-2-1-Q)
1.2.8 Troop/Passenger Seating (1-4-1-C)
1.2.9 Troop/Passenger Seating (1-2-4-C)
1.2.10 Ammunition Space (1-2-6-M)
1.2.11 Command Module, Exterior Bulkheads
1.2.12 P & E Module, Exterior Bulkheads
1.3 Identification:
1.3.1 Not Applicable
2. REFERENCES:
2.1 Standard Items
2.2 LCAC Craft Change Document 445 Rev 01, Incr 01, Limited Compartment Painting
2.3 631-6266706 Rev P, LCAC Paint and Marking
2.4 S6360-AE-MMA-010 Rev 10, Technical Manual for Landing Craft, Air Cushion (LCAC) Corrosion Control
2.5 802-7616004 Rev G, SLEP Plan View of Each Level, Deck & Platform
2.6 164-7403842 Rev G, LCAC Portable Armor Kit Craft Interfaces
2.7 164-7403836 Rev D, LCAC Armor Panel
2.8 164-7403841 Rev -, Portable Armor Craft Installation
2.9 635-5749105 Rev F, LCAC Insulation Instl, Hull
2.10 7614-947911 Rev A, Process Specification For Cleaning, Chemical & Mechanical LCAC
2.11 7614-947915 Rev A, Process Specification For Adhesive Bonding
SSP: BOST-515-16 2 of 3 ITEM NO: 631-90-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Materials LCAC
3. REQUIREMENTS:
3.1 Accomplish surface preparation and preservation of surfaces for LCAC Craft Change Document 445 Rev 01, Incr 01, Limited Compartment Painting, in each compartment listed in 1.2, using 2.2 through 2.5 for guidance.
3.2 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line 23, Column A, for surface preparation of entire deck surfaces, and 6 inches above deck of bulkhead surfaces for each compartment listed in
1.2.1 through 1.2.10.
3.2.1 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 26, Column A, for surface preparation of exterior bulkhead surfaces, from the Main Deck up to 24 inches above the Main Deck for entire bulkhead periphery of each area listed in 1.2.11 and 1.2.12.
3.2.1.1 Extend bulkhead surface preparation up to the underside of the A/C unit located on the inboard bulkhead of the area listed in 1.2.11.
(V)(G) "STRUCTURAL INSPECTION"
3.2.2 Accomplish a joint visual inspection with the SUPERVISOR of each prepared surface for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion.
Report: Inspection Results Date: + 3
3.2.2.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report listing results of the requirements of 3.2.2 to the SUPERVISOR.
3.2.3 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 27, Columns B, D and E, for preservation of prepared surfaces for each compartment listed in 1.2.1 through 1.2.6.
3.2.4 Accomplish the requirements of 009-32 of 2.1, including Table 3, Line 27, Columns B, D, E and F, for preservation of prepared surfaces for each compartment listed in 1.2.7 through 1.2.10.
3.2.5 Accomplish the requirements of 009-32 of 2.1, including Table 2, Line 26, Columns B, D, and G, for preservation of prepared surfaces for each compartment listed in 1.2.11 and 1.2.12.
3.3 Remove existing armor panels and associated bolted support structure in way of preservation of aluminum bulkhead surfaces in each area listed in 1.2.11 and 1.2.12 using 2.6 through 2.8 for guidance. Retain panels and hardware for installation upon completion of preservation in 3.2.
3.4 Remove existing and install new bulkhead insulation in way of preservation of aluminum bulkhead surfaces in each area listed in 1.2, in accordance with 2.9.
3.4.1 Accomplish the requirements of 009-11 of 2.1.
SSP: BOST-515-16 3 of 3 ITEM NO: 631-90-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.4.2 Clean structure prior to bonding insulation in accordance with 2.10.
3.4.3 Bond insulation to structure in accordance with 2.11.
3.5 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.
4. NOTES:
4.1 Accomplish structural repairs and welding prior to application of coating materials.
4.2 Insulation handling is covered on Work Item 077-01-001, Hazardous Waste Produced on Naval Vessels; control.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 713-85-001
COAR: 16 PCN: LC80-B571
CMP: NONE
PLANNER: NICASIO,
CHRISTOPHER
SSP: BOST-515-16 1 of 2 ITEM NO: 713-85-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: LCAC Craft Change Document CCD-571 Rev 00, LCAC Weapon Stowage Modification; accomplish
1.2 Location of Work:
1.2.1 Personnel and Equipment Module (1-2-4-C)
1.3 Identification:
1.3.1 Quantity (One EA), Weapon Stowage Rack Assembly
1.3.1.1 Quantity (One EA), Locker Gun Rack Assembly P/N:
6386230-013
2. REFERENCES:
2.1 Standard Items
2.2 LCAC Craft Change Document CCD-571 Rev 00, LCAC Weapons Stowage Modification
2.3 713-8430431 Rev A, CCD 571, LCAC, Armament Stowage Mod Installation and Details
2.4 713-6386230 Rev K, LCAC, Armament Stowage Details and Installation
2.5 713-5750119 Rev N, Armament Stowage Installation
2.6 635-5749105 Rev F, LCAC Insulation Instl, Hull
2.7 7614-947911 Rev A, Process Specification For Cleaning, Chemical, and Mechanical LCAC
2.8 7614-947915 Rev A, Process Specification For Adhesive Bonding of Materials
3. REQUIREMENTS:
3.1 Accomplish removals, modifications and installations for LCAC Craft Change Document CCD-571 Rev 00, LCAC Weapon Stowage Modification for the equipment listed in 1.3 and located in 1.2 in accordance with 2.2 and 2.3, using 2.4 and 2.5 for guidance.
3.1.1 Accomplish the requirements of 009-12 of 2.1, including Table 4, Column C, Lines One through 7.
3.1.2 Turnover the removed equipment listed in 1.3 to the SUPERVISOR for disposition.
3.1.3 Install Government Furnished Material (GFM) provided in 5.1.
3.2 Accomplish the requirements of 2.6 for removals and installation of insulation in way of repairs.
3.2.1 Accomplish the requirements of 009-11 of 2.1.
3.2.2 Clean structure prior to bonding insulation in accordance with
SSP: BOST-515-16 2 of 2 ITEM NO: 713-85-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
2.7.
3.2.3 Bond insulation to structure in accordance with 2.8.
3.3 Accomplish the requirements of 009-32 of 2.1 for new and disturbed surfaces.
4. NOTES:
4.1 Insulation handling is covered on Work Item 077-01-001, Hazardous Waste Produced on Naval Vessels; control.
4.2 Insulation removed in the P&E Module may be contaminated with lead.
4.3 Preservation of deck surfaces for compartment listed in 1.2.1 is accomplished in Work Item 631-90-002, LCAC Craft Change Document 445 Rev 01, Incr 01, Limited Compartment Painting; accomplish.
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART PIECE NO. REF NO.
NATIONAL
STOCK NO.
REQ
PARA NO.
1. 4 EA
Universal Barrel Clip, 7095-96-1 18 2.3 N/A 3.1.3
2. 4 EA
Standard Butt Cup, 208-88-7 19 2.3 N/A 3.1.3
3. 2 EA
Standard Clip .50 Cal., 208- 88-4 20 2.3 N/A 3.1.3
4. 1 EA
Butt Clip for
MK19, 208-88-3 21 2.3 N/A 3.1.3
5. 1 EA
Barrel Clip for
MK19, 208-88-1 22 2.3 N/A 3.1.3
5.2 PUSH MATERIAL:
1. None.
SHIP: ASSAULT CRAFT UNIT ACU 5 (ACU 45411) ITEM NO: 992-31-001
COAR: 16 PCN: LC80-B993
CMP: NONE
PLANNER: DEMERS, RAY
SSP: BOST-515-16 1 of 7 ITEM NO: 992-31-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Cleaning and Pumping; accomplish
1.2 Location of Work:
1.2.1 Command Module (01-2-1-C)
1.2.2 Personnel and Equipment Module (1-2-4-C) with Observer
Platform (01-2-2-C)
1.2.3 Starboard APU Engine Compartment (01-11-1-Q)
1.2.4 Port APU Engine Compartment (01-11-2-Q)
1.2.5 Starboard Engine Compartment (01-12-1-Q)
1.2.6 Starboard Engine…