SOW_991-11-003.doc
DOC document 44 KB Posted
- Attached to
- JLG 60" BOOM MANLIFTS (5 EA)
- Solicitation number
- N55236-15-Q-0194
About this file
STATEMENT OF WORK
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT_No_0001.pdf | ||
| Request_for_Specification_Clarification_Form.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK STATEMENTPRIVATE
SHIP: USS Pasadena Hull: SSN-752 Work Item: 991-11-003
JSN: 21413-WKMC-Q846
COAR:
SSP 036-15
SURVEYOR: Tom Loepfe
1. SCOPE:
1.1 Title: Temporary Services; provide 1.2 Location of Work:
1.2.1 Submarine Base Point Loma South Pier / Drydock Basin 1.3 Identification:
1.3.1 Quantity: (5) Each, Man-lifts, JLG-600 or 800 series, Diesel Powered, 60 Foot Boom Minimum.
2. REFERENCES:
2.1 NAVSEA Standard Items
3. REQUIREMENTS:
3.1 Provide temporary services identified in 1.3.1 to location identified in 1.2.1 as directed by the SUPERVISOR.
3.1.1 Man-lifts must be Certified for use from a floating vessel per ANSI/SIA A92.5-1992. “Boom-supported Elevating Work Platforms” Section 7.11.12. Tires must be foam filled.
3.1.2 Each Equipment listed in 1.3.1 shall be available for use 24 hours per day, 7 days per week for the duration of Dry-dock (61) days (01OCT2015-30NOV2015) 3.1.3 Each Equipment listed in 1.3.1 shall include Fuel. Provide and refuel 40 gallons of fuel per week to ensure equipment remains in working order. Each equipment will not be refueled to full status prior to return at the end of the POP.
3.1.4 When parking each equipment listed in 1.3.1 ensure berms are in-place to collect/maintain any contaminants. Berms shall be drained and cleaned on a daily Basis.
3.2 Submit one legible copy in hard copy or approved electronic media, of a report to the SUPERVISOR that the services staged in 1.3.1 are tested and ready to support ships force and shipyard use.
3.3. Temp Services identified in 1.3.1 shall be removed upon completion of work as directed by the SUPERVISOR.
4. NOTES:
4.1 Primary point of contact is SBS Tom Loepfe 619-571-2668 4.2 Ships Force point of contact is the 3MC.
4.3 Period of Performance is 21SEPT2015- 04DEC2015
5. GOVERNMENT FURNISHED MATERIAL:
5.1 None.