LOT I Combined List of Questions and Responses.pdf
PDF 718 KB Posted
- Attached to
- Marine Boatyard Repair and Maintenance Support LOT I for the Mid-Atlantic Regional Maintenance Center
- Solicitation number
- N50054-24-R-0007
About this file
This document is a collection of questions and responses related to a federal contract opportunity for Marine and Boatyard Maintenance Support LOT I, solicitation number N50054-24-R-0007, issued by the Department of the Navy Naval Sea Systems Command.
The key details include: This is an Indefinite Delivery Indefinite Quantity Multiple Award Contract (IDIQ-MAC) for a base year with four one-year ordering periods. The contract will be for depot-level repairs, alterations, troubleshooting, maintenance, installation, and removal of systems and equipment on various U.S. Navy vessels. The work will be performed within a 100-mile radius of Naval Station Norfolk, VA. Offerors must have an Agreement for Boat Repair (ABR) number or demonstrate equivalency. Remote site work requires an approved Remote Site Performance Plan. The solicitation is a Total Small Business Set-Aside under NAICS code 336611 with a 1,300 employee size standard. Responses must be submitted through the Procurement Integrated Enterprise Environment (PIEE) solicitation module.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N50054-24-R-0007 A0002 SF-30.pdf | ||
| N50054-24-R-0007 A0002 Conformed Copy.pdf | ||
| N50054-24-R-0007 A0001 SF-30.pdf | ||
| J-4 Past Performance Questionnaire.docx | DOCX document | |
| N50054-24-R-0007 A0001 Conformed Copy.pdf | ||
| LOT I Combined List of Questions and Responses.pdf | ||
| J-6 Other Security Measures.pdf | ||
| Exhibits LOT I.zip | ZIP file | |
| J-5 Local Work Templates.pdf | ||
| J-4 Past Performance Questionnaire.docx | DOCX document | |
| J-1. Labor and Material Burden Rates Price Sheet.xlsx | XLSX spreadsheet | |
| J-7 Sample Listing of Boats Craft Lighterage and Service Craft.doc | DOC document | |
| N50054-24-R-0007.pdf | ||
| S-1 Pre-Proposal Information Form.xlsx | XLSX spreadsheet | |
| J-3 Past Performance Reference.docx | DOCX document | |
| J-2 Capacity Sheet.xlsx | XLSX spreadsheet |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA.
PAGE NO:
ITEM NO:
TITLE:
PARA.
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
CONTRACTOR QUESTION 01: No DD Forms 1423 were provided with the RFP package. Please provide.
GOVERNMENT RESPONSE: The forms are located in the "Attachments" section of the posting on SAM.gov. They are listed as a .zip file titled "Exhibits LOT I"
CONTRACTOR QUESTION 02: Please confirm that the Contractor shall use the Navy Maintenance Database (NMD) on this Lot I contract?
GOVERNMENT RESPONSE: As stated in Section C of the solicitation, use of the Navy Maintenance Database (NMD) will be required for orders issued under the contract.
GOVERNMENT RESPONSE: Per section C and section L of the solicitation, the Offer shall provide their ABR number.
CONTRACTOR QUESTION 03: Is it satisfactory to provide offeror's ABR Contract Number? If not, please do not include the ABR in the page count of Element A.
CONTRACTOR POC:
REQUEST FOR SPECIFICATION CLARIFICATION
Attachment S-1
CONTRACTOR PHONE:
DATE OF REQUEST: SOLICITATION NO: N50054-24-R-0007
TITLE: Marine and Boatyard Maintenance Support LOT I MAC IDIQ MARMC POC: jake.a.grady2.civ@us.navy.mil
CONTRACTOR:
FORWARD ALL REQUESTS TO: kevin.r.cooper20.civ@us.navy.mil AND willie.r.ross.civ@us.navy.mil
CONTRACTOR QUESTION 04: If an offeror does not have a current Remote Site Performance Plan approved by MARMC, should the offerror submit its plan as an attacement to their Technical Proposal?
GOVERNMENT RESPONSE: Yes, if an offeror does not have a current Remote Site Performance Plan approved by MARMC, the offerror should submit its plan as an attachment to their Technical Proposal.
GOVERNMENT RESPONSE: Confirmed. The date should read 30 September 2024. This will be corrected via amendment 0001.
CONTRACTOR QUESTION 05: Will the government clarify if offerors must complete Attachment J-2 Capacity Sheet and include as part of their proposal?
GOVERNMENT RESPONSE: The attachment J-2 capacity sheet is to be utilized at the delivery order level, at the discretion of the ordering officer. The contractor will submit this capacity sheet as part of it's proposal package in response to a delivery order solicitation.
CONTRACTOR QUESTION 07: Page 117 of the solicitation states: "The Offeror shall not submit the Security Classification Specification as a part of the
GOVERNMENT RESPONSE: It is not anticipated that any of the work completed under this contract will involve classified requirements. In
CONTRACTOR QUESTION 06: Attachment J-4 Past Performance Assessment Questionnaire indicates the form is due by 16 August 2024. May offerors update the date to 30 Sep 2024?
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
Offeror shall not submit the Security Classification Specification as a part of the proposal. The DD Form 254 will, however, become a material part of any resultant delivery order, as applicable." Will the government clarify if there is a DD254 and/or what is the security classification for this requirement?
completed under this contract will involve classified requirements. In the event a specific order does include classified requirements, a DD- 254 will be provided for that specific order.
CONTRACTOR QUESTION 08: “Element A: Organization and Management: A1: Offerors must provide their Agreement for Boat Repair Number (ABR) or, if not a Current ABR holder, must demonstrate equivalency by completing and submitting an application, with all required documentation, for an ABR as defined by CNRMCINST 4280.1A. Documentation must be provided of an approved Remote Site Performance Plan, if applicable.
Additionally, for work to be accomplished at a remote site, offerors must address personnel to be utilized. Offerors who do not meet ABR requirements will be excluded from further consideration. If an offeror fails to provide an approved Remote Site Performance Plan, if applicable, or a plan for personnel at a remote site by time of award, the proposal may be excluded from further consideration.” Is additional documentation still required even though we have an ABR?
GOVERNMENT RESPONSE: The Offeror's capabilities approved in the ABR must apply to the remote site location also.
CONTRACTOR QUESTION 09: Please provide the definition of LOT I and LOT II craft.
GOVERNMENT RESPONSE: LOT I and LOT II are two separate requirements. LOT I is currently being solicited on SAM.gov under solicitation number N50054-24-R-0007, and LOT II is being solicited under solicitiation number N50054-24-R-0008. The difference between LOT I and LOT largely deals with the size of craft along with the contractor's facilities capabilities. Please see section C, paragraph 2.6 of each solicitation for a detailed explanation of the craft supported.
CONTRACTOR QUESTION 10: The Quality Assurance Surveillance Plan (QASP) was not provided with the RFP package. Please provide.
GOVERNMENT RESPONSE: There is no QASP for this requirement.
The term was included by error. This will be removed from Section C, paragraph 3.7 via amendment 0002.
CONTRACTOR QUESTION 11: When is the offeror required to submit a Contractor's Security Plan as described in paragraph 5.7 of the Statement of Work?
GOVERNMENT RESPONSE: The plan will be submitted following award for vetting by the MARMC ATFP and security team.
CONTRACTOR QUESTION 14: Recommend that the page maximum be raised to ten (10). Believe five pages is not sufficient to provide the information requested specially with regards to the equipment/machinery lists required.
GOVERNMENT RESPONSE: Page limitations will not be revised.
CONTRACTOR QUESTION 12: (B3) states "….with the appropriate clearance level". A DD254 was not provided. Is this a classified contract?
GOVERNMENT RESPONSE: Please see the response to question number 7.
CONTRACTOR QUESTION 13: Paragraph states that "...include letters of commitment from any external sources that will be providing personnel for the work effort." Please consider excluding these letters of commitment from the page count of Element B.
GOVERNMENT RESPONSE: Page limitations will not be revised.
CONTRACTOR QUESTION 15: The requirements for shop facilities differ from the RFP SOW 5.7 pages 26-27 to Section L, Element C: FACILITIES, Paragraph (C1), CNRMCINST 4280.1A, Enclosure (3), Item 5. The "definitions" differ on both. For example, Shipfitting in Section C states "Ship fitting types of work. Cutting (gas, arc and shear), rolling, shaping, grinding and fitting steel and aluminum plates and shapes" and 4280.1A, Enclosure (3), Item 5, page 2 states "Shipfitting types of work. Rip out, alteration, repair, and installation of ship’s hull and superstructure including hull plates, frame structure, metal deck plating and grating, hull fittings such as davits, fairleads, chocks, bollards, watertight, doors, hatches, fittings, scuttles, sockets, and deck
GOVERNMENT RESPONSE: Ship fitting types of work. Rip out, alteration, repair, and installation of ship’s hull and superstructure including hull plates, frame structure, metal deck plating and grating, hull fittingssuch as davits, fairleads, chocks, bollards, watertight, doors, hatches, fittings, scuttles, sockets, and deck rails.
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR QUESTION 18: The Section L (C1) requirement does not address Work Area/Storage, Access to Waterway, Services, Lift Equipment, and Forklift requirements in the SOW 5.7, page 26. (C1) adresses the requirements of CNRMCINST 4280.1A, Enclosure (3), Item 5 and facility being within 100-miles radius from Naval Station Norfolk. Please advise.
GOVERNMENT RESPONSE: The paragraph starts by stating, "The successful offeror shall have sufficient facilities in appropriate locations to fully support the work intended by the contract." This would include those requirements set forth in Section C, Statement of Work, in addition to CNRMCINST 4280.1A, Enclosure (3), Item 5 and facility being within 100-miles radius from Naval Station Norfolk which are discussed later in the paragraph.
CONTRACTOR QUESTION 17: End of paragraph states: "If the proposal facility site is not owned by the offeror, and the offeror fails to provide a letter of commitment from the owner, the proposal will be excluded from further consideration." Please consider excluding these letters of commitment from the page count of Element C.
GOVERNMENT RESPONSE: Page limitations will not be revised.
chocks, bollards, watertight, doors, hatches, fittings, scuttles, sockets, and deck rails." Also, the "work areas" do not match 1-to1. Which list takes precedence?
CONTRACTOR QUESTION 16: If the Prime Contractor possesses an ABR, must teaming partners also have one?
GOVERNMENT RESPONSE: The prime offeror who submits a proposal in response to this solicitation must comply with the requirements of Section L paragrapgh (A1).