Attachment III - Questions from Industry 21April2022.pdf
PDF 541 KB Posted
- Solicitation number
- N50054-22-Q-0068
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment II - WD 2015-4341 Rev 20.pdf | ||
| Rev 1 (final) SOW revised- repair and recoat Main St.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
CONTRACTOR POC:
REQUEST FOR SPECIFICATION CLARIFICATION
CONTRACTOR PHONE:
DATE OF REQUEST: 4/19/2022 SOLICITATION NO: N50054-22-Q-0068
TITLE: MARMC Facilities Building Support Services MARMC POC: 1. Donald Bowers (Contract Specialist)
2. Elizabeth Marston
CONTRACTOR:
MARMC EMAIL: 1. donald.bowers1@navy.mil 2.
elizabeth.a.marston.civ@us.navy.mil
CONTRACTOR QUESTION #1: Are there any drawings of the work areas that can be provided?
GOVERNMENT RESPONSE: There are no drawings available for this work. Please see the solicitation regarding the site visit and contact the Contract Specialist if a site visit is required.
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
ITEM NO:
TITLE:
PARA. NO:
PAGE NO:
GOVERNMENT RESPONSE: Total square footage is 2875 sq ft.
CONTRACTOR QUESTION #8: Are there any mandatory meetings or required site visits? Also, is there any important documentation needed for this project?
GOVERNMENT RESPONSE: There are no mandatory meetings.
Please see the solicitiation for details regarding a site visit if you firm feels this is required.
CONTRACTOR QUESTION #6: Will an equal to product be accepted? GOVERNMENT RESPONSE: An equivalent product will be accepted.
The USG is requesting the contractor to fix/repair broken away concrete and match the existing paint color.
CONTRACTOR QUESTION #7: We are hoping to find out if there is (was) an incumbent contractor performing these services, or if this is a brand new contract. If there is an incumbent, could you please provide the current / previous contract number?
GOVERNMENT RESPONSE: The subject solictation is a new, stand-alone requirement.
CONTRACTOR QUESTION #2: What is the total square footage of the areas to be replaced?
GOVERNMENT RESPONSE: No. Areas to be repaired/recoated will be clear of obsticles for contractor
CONTRACTOR QUESTION #4: Will the contractor be responsible for moving any furniture/equipment?
CONTRACTOR QUESTION #5: Is there a wage determination for this project? If so does it fall under the Service Contract Act or the Davis Bacon Act?
GOVERNMENT RESPONSE: The Service Contract Act applies, but the Davis Bacon Act does not apply. A wage determination will be included into the solicitation/contract.
CONTRACTOR QUESTION #3: Are there any pictures of the work areas that can be provided?
GOVERNMENT RESPONSE: There are no drawings available for this work. Please see the solicitation regarding the site visit and contact the Contract Specialist if a site visit is required.