J1-_Labor_and_Material_Price_Sheet_Non-Complex_Norfolk.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- LCAC PSE/FMP and SSC availabilities
- Solicitation number
- N50054-17-R-0005
About this file
J1 - Labor and Material Burden Rates Price Sheet
View the file
Other files
| File | Type | Posted |
|---|---|---|
| L1_-_Acronyms_(miscellaneous).docx | DOCX document | |
| S3_-_Request_For_Pre-Proposal_Info_Form.docx | DOCX document | |
| S1_-_Management_&_Technical_Experience.docx | DOCX document | |
| J5_Capacity_Eval_Form.doc | DOC document | |
| S2_-_Past_Perf_Questionnaire.docx | DOCX document | |
| J2_LWT_042-37.pdf | ||
| J6_-_CDRL_A001-A005.pdf | ||
| S4_Bidders'_Questions_Form.doc | DOC document | |
| N50054-17-R-0005.pdf | ||
| S1_-_Management_&_Technical_Experience.docx | DOCX document | |
| J1-_Labor_and_Material_Price_Sheet_Non-Complex_Norfolk.xlsx | XLSX spreadsheet | |
| S4_Bidders'_Questions_Form.doc | DOC document | |
| J5_Capacity_Eval_Form.doc | DOC document | |
| L1_-_Acronyms_(miscellaneous).docx | DOCX document | |
| N50054-17-R-0005.pdf | ||
| S3_-_Request_For_Pre-Proposal_Info_Form.docx | DOCX document | |
| S2_-_Past_Perf_Questionnaire.docx | DOCX document | |
| J6_-_CDRL_A001-A005.pdf | ||
| J2_LWT_042-37.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
Offeror Name:
| CLIN 1001 (BASE) | |||||
| Fully Burdened Ship Repair Labor Rate | TOTAL | ||||
| Hours | Rate | Price | Total Hours | Total Price | |
| Direct Production Labor Hours | 110,000 | $0.00 | $0 | 110,000 | $0 |
| Total Labor | 110,000 | $0 |
| Material Burden Rate | Insert Rate -> | |
| Material | $1,450,000 | |
| Total Material Price | $1,450,000 |
Total Base Year 110,000 $1,450,000
| CLIN 2001 (OPTION PERIOD 1) | |||||
| Fully Burdened Ship Repair Labor Rate | TOTAL | ||||
| Hours | Rate | Price | Total Hours | Total Price | |
| Direct Production Labor Hours | 110,000 | $0.00 | $0 | 110,000 | $0 |
| Total Labor | 110,000 | $0 |
| Material Burden Rate | Insert Rate -> | |
| Material | $1,450,000 | |
| Total Material Price | $1,450,000 |
Total Option Period 1 110,000 $1,450,000
| CLIN 3001 (OPTION PERIOD 2) | |||||
| Fully Burdened Ship Repair Labor Rate | TOTAL | ||||
| Hours | Rate | Price | Total Hours | Total Price | |
| Direct Production Labor Hours | 110,000 | $0.00 | $0 | 110,000 | $0 |
| Total Labor | 110,000 | $0 |
| Material Burden Rate | Insert Rate -> | |
| Matieral | $1,450,000 | |
| Total Material Price | $1,450,000 |
Total Option Period 2 110,000 $1,450,000
| CLIN 4001 (OPTION PERIOD 3) | |||||
| Fully Burdened Ship Repair Labor Rate | TOTAL | ||||
| Hours | Rate | Price | Total Hours | Total Price | |
| Direct Production Labor Hours | 110,000 | $0.00 | $0 | 110,000 | $0 |
| Total Labor | 110,000 | $0 |
| Material Burden Rate | Insert Rate -> | |
| Material | $1,450,000 | |
| Total Material Price | $1,450,000 |
Total Option Period 3 110,000 $1,450,000
| CLIN 5001 (OPTION PERIOD 4) | |||||
| Fully Burdened Ship Repair Labor Rate | TOTAL | ||||
| Hours | Rate | Price | Total Hours | Total Price | |
| Direct Production Labor Hours | 110,000 | $0.00 | $0 | 110,000 | $0 |
| Total Labor | 110,000 | $0 |
| Material Burden Rate | Insert Rate -> | |
| Material | $1,450,000 | |
| Total Material Price | $1,450,000 |
Total Option Period 4 110,000 $1,450,000
Total Evaluated Price Base & Options = Sum of Base and Option Year Totals 550,000 $7,250,000
| NOTES: | Attachment J1 |
| 1. Fully Burdened Ship Repair Labor Rates must be entered as dollars and cents. | |
| 2. Labor Price is calculated as follows: Rate*Hours | |
| 3. Total Material is calculated as follows: Material * (1+ Material Burden Rate) |
File details come from the government source that posted it. Updated .