Attachment 3. Contractor Questions and Answers.pdf

PDF 173 KB Posted

Attached to
Portable AC Units Lease
Solicitation number
N4523A25Q0039
Issued by

About this file

This document is an Attachment 3 Contractor Questions and Answers file dated 6/18/2025 for a Portable AC Units Lease solicitation (N4523A25Q0039) issued by the Department of the Navy Naval Supply Systems Command. The document contains two contractor questions regarding technical details of portable AC unit installation:

Question 1 addresses the heat exhaust method, with the government clarifying that the AC units will be installed on the building's roof, connected to the air handling system, with exhaust released into outside air. Question 2 inquires about power supply accessibility, and the response indicates that power is already run to the designated area, with a temporary connection to be made to the units. The document provides technical clarification for potential contractors bidding on the solicitation for one 5-Ton and four 12-Ton portable AC units.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 3 Contractor Questions 6/18/2025

Question 1:

Regarding the installation of the portable AC units, will the heat from the units be exhausted through a window or through the ceiling at the designated site?

Answer 1:

The units will be installed on the roof of the building, connected to the building’s air handling system, and the exhaust will come out of the unit into outside air.

Question 2:

What is the accessibility of the power supply to the portable AC units?

Answer 2:

The power is already run to the area and then a temp connection is made to the unit.

File details come from the government source that posted it. Updated .