ATTACHMENT 5.1 - Availability Schedule.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
USS JOHN S. MCCAIN Hull Preservation Federal contract opportunity
Solicitation number
N4523A24R0569
Issued by
Department of the Navy Naval Supply Systems Command

About this file

This document appears to be Attachment 5.1 - Availability Schedule related to a Request for Quote (RFQ) for the USS JOHN S. McCAIN (DDG-56) Depot-Level Ship Repair Availability (DSRA) contract. The RFQ, identified as Solicitation Number N4523A24R0569, was issued by the Department of the Navy Naval Supply Systems Command as an unrestricted procurement under FAR Part 13, Simplified Acquisition Procedures.

The Availability Schedule provides detailed milestones and projected dates for the DSRA execution, including key events such as dock ship, 20% open/inspect complete, 25/50/75% conferences, undock ship, production complete, dock trials, sea trials, and availability completion. The applicable NAICS code is 325510 Paint and Coating Manufacturing, and the purpose of the contract is to provide paint coatings and related products to the US Navy fleet. The Contractor is responsible for delivering the full range of products to various locations in the Pacific Northwest region.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Attachment 5 Availability Schedule - Request for Quote
ADVANCED PLANNING MILESTONES USS JOHN S. McCAIN (DDG-56) DSRA
EXECUTION MILESTONES
EventMilestoneProjected Date
AVAIL STARTA+0Tuesday, February 11, 2025
Paint Arrival at shipyardA+0Tuesday, February 11, 2025
Crew Move AshoreA+9Thursday, February 20, 2025
Dock ShipA+21Tuesday, March 04, 2025
Paint Representative at ShipyardA+29Wednesday, March 12, 2025
20% Open/Inspect Complete (docking)A+48Monday, March 31, 2025
20% Open/Inspect Complete (ALL)A+64Friday, April 18, 2025
25% ConferenceA+73Monday, April 27, 2025
50% ConferenceA+145Friday, July 11, 2025
Undock Ship (Key Event)A+166Friday, Aug 01, 2025
Firemain Light OffA+209Saturday, September 13, 2025
HAB Complete - Restore FM / PW / VCHT / CWA+212Tuesday, September 16, 2025
Crew Move AboardA+220Wednesday, September 24, 2025
75% ConferenceA+220Wednesday, September 24, 2025
(PCD) Production CompleteA+229Friday, October 03, 2025
(C5ILO) COMMAND, CONTROL, COMMS,A+226Tuesday, September 30, 2025
Work CompleteA+241Wednesday, October 15, 2025
Light Off AssessmentA+247Tuesday, October 21, 2025
(DT) Dock TrialsA+254Tuesday, October 28, 2025
(FC) Fast CruiseA+256Thursday, October 30, 2025
(ST) Sea TrialsA+261Wednesday, November 05, 2025
(AC) Availability CompletionA+267Monday, November 10, 2025

File details come from the government source that posted it. Updated .