ATTACHMENT 5 - Availability Schedule.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
USS JOHN S. MCCAIN Hull Preservation Federal contract opportunity
Solicitation number
N4523A24R0569
Issued by
Department of the Navy Naval Supply Systems Command

About this file

This document is an Attachment 5 - Availability Schedule that is part of a Request for Quote (RFQ) for the USS JOHN S. McCAIN (DDG-56) Docking Selective Restricted Availability (DSRA) execution. The schedule outlines key milestones and dates for the availability, including the start date, docking, inspections, conferences, system light-offs, crew moves, production completion, and dock/sea trials. The related federal contract opportunity is for the USS JOHN S. MCCAIN Hull Preservation, solicitation number N4523A24R0569, with an NAICS code of 325510 Paint and Coating Manufacturing. The purpose is to provide paint coatings and related products to the U.S. Navy fleet, with delivery locations in Seattle, WA, Everett, WA, and/or Portland, OR. This is an unrestricted procurement using Simplified Acquisition Procedures under FAR Part 13.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Attachment 5 Availability Schedule - Request for Quote
ADVANCED PLANNING MILESTONES USS JOHN S. McCAIN (DDG-56) DSRA
EXECUTION MILESTONES
EventMilestoneProjected Date
AVAIL STARTTuesday, Fedruary 11, 2025
Crew Move Ashore9Thursday, February 20, 202520-Feb-25
Dock Ship21Tuesday, March 04, 20254-Mar-25
20% Open/Inspect Complete (docking)48Monday, March 31, 202531-Mar-25
20% Open/Inspect Complete (ALL)64Friday, April 18, 202518-Apr-25
25% Conference73Monday, April 27, 202527-Apr-25
50% Conference145Friday, July 11, 202511-Jul-25
Undock Ship (Key Event)166Friday, Aug 01, 20251-Aug-25
Firemain Light Off209Saturday, September 13, 202513-Sep-25
HAB Complete - Restore FM / PW / VCHT / CW212Tuesday, September 16, 202516-Sep-25
Crew Move Aboard220Wednesday, September 24, 202524-Sep-25
75% Conference220Wednesday, September 24, 202524-Sep-25
(PCD) Production Complete229Friday, October 03, 20253-Oct-26
(C5ILO) COMMAND, CONTROL, COMMS,226Tuesday, September 30, 202530-Sep-25
Work Complete241Wednesday, October 15, 202515-Oct-25
Light Off Assessment247Tuesday, October 21, 202521-Oct-25
(DT) Dock Trials254Tuesday, October 28, 202528-Oct-25
(FC) Fast Cruise256Thursday, October 30, 202530-Oct-25
(ST) Sea Trials261Wednesday, November 05, 20255-Nov-25
(AC) Availability Completion267Monday, November 10, 202510-Nov-25