This document contains a price proposal worksheet and solicitation for maintenance services for two yard craft barges. The Regional Maintenance Center at Puget Sound Naval Shipyard intends to award a firm-fixed-price contract to accomplish maintenance, repair, and preservation of Yard Craft Barge 1591 and Yard Craft Barge 1571. Services required include docking the vessels, washing and cleaning, blasting and preserving hulls and tanks, conducting visual and ultrasonic inspections, replacing hardware and covers, and air testing tanks. The contractor must be capable of accommodating Barge 1591 which is 110 feet long, 8 feet in draft, and 32 feet wide. The period of performance is from March 17, 2020 to May 27, 2020. Offerors must be registered in the System for Award Management to receive the award. Drawings of the barges will be available after January 2, 2020.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YC-1571

INSERT CONTRACTOR/COMPANY NAME HERE
Project =YC-1571DATE: =
PRIMESUBCONTRACTORPRIMEPRIME
PARAGRAPH No.TITLEM/HMATERIAL PRICETOTALLabor CostMaterial CostTOTALOther Direct Cost (ODC)*G&APROFITLine Item Total
1.4Arrival Conference$0.00$0.00$0.00$0.00$0.00
1.5Required Documents$0.00$0.00$0.00$0.00$0.00
1.6Progress Meetings$0.00$0.00$0.00$0.00$0.00
1.7Availability Requirements$0.00$0.00$0.00$0.00$0.00
1.7.1Transport Vessel$0.00$0.00$0.00$0.00$0.00
1.8Care of Vessel$0.00$0.00$0.00$0.00$0.00
1.11CFR Reports$0.00$0.00$0.00$0.00$0.00
1.13Safety Requirements$0.00$0.00$0.00$0.00$0.00
1.16.1Preservation OQE$0.00$0.00$0.00$0.00$0.00
1.17Enviromental/ Hazwaste Management$0.00$0.00$0.00$0.00$0.00
1.2Gas Free$0.00$0.00$0.00$0.00$0.00
1.21Develop & Maintain Test Plan$0.00$0.00$0.00$0.00$0.00
3.1.1Personnel & Equipment$0.00$0.00$0.00$0.00$0.00
3.1.2Docking Procedures$0.00$0.00$0.00$0.00$0.00
3.1.3Blocking Plan$0.00$0.00$0.00$0.00$0.00
3.1.4Crib and Brace Blocking$0.00$0.00$0.00$0.00$0.00
3.1.5Setting and Aligning Blocks$0.00$0.00$0.00$0.00$0.00
3.1.6Docking Conference$0.00$0.00$0.00$0.00$0.00
3.1.7Docking the Vessel$0.00$0.00$0.00$0.00$0.00
3.1.8Post Docking$0.00$0.00$0.00$0.00$0.00
3.1.9Undocking Vessel$0.00$0.00$0.00$0.00$0.00
3.1.11Final Docking$0.00$0.00$0.00$0.00$0.00
3.2.1Indentify Distinguishing Figures & Markings$0.00$0.00$0.00$0.00$0.00
3.2.2Steel Half Pipe Fenders$0.00$0.00$0.00$0.00$0.00
3.2.3Zinc's Replacement$0.00$0.00$0.00$0.00$0.00
3.2.4Rubber fenders$0.00$0.00$0.00$0.00$0.00
3.2.5Hull Blasting and Preservation$0.00$0.00$0.00$0.00$0.00
3.2.6Hull and Freeboard Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.2.7Hull and Freeboard U/T Inspection$0.00$0.00$0.00$0.00$0.00
3.4.1Open, Pump, Clean, Vent, Gas Free, Close all tanks$0.00$0.00$0.00$0.00$0.00
3.4.2Tank/Void Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.4.3Indentfy Color Schemes and Markings$0.00$0.00$0.00$0.00$0.00
3.4.4Pre-Lim Air Test$0.00$0.00$0.00$0.00$0.00
3.4.5Tank/Void Preservation$0.00$0.00$0.00$0.00$0.00
3.4.6Access Cover provide/ Preservation$0.00$0.00$0.00$0.00$0.00
3.4.7Watertight Hatch repairs$0.00$0.00$0.00$0.00$0.00
3.4.8Final Air Test$0.00$0.00$0.00$0.00$0.00
3.4.9Tank Close-out Inspection$0.00$0.00$0.00$0.00$0.00
3.5.1Main Deck Non-skid Preservation$0.00$0.00$0.00$0.00$0.00
3.5.2Main Deck Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.5.3Main Deck U/T Inspection$0.00$0.00$0.00$0.00$0.00
3.5.4Handrail Removals$0.00$0.00$0.00$0.00$0.00
Column Totals0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Scope (SOW/PWS)Labor Rate/MH:G&A Rate:Profit Rate:
Total Bid:$0.00

=MH*Labor Rate*G&A =(Prime Material Price+Subcontractor Total)*Profit Rate =(MH*Labor Rate)+Material Price =Sub Cost (F) =SUM(Prime Total+Subcontractor Total+ODC+G&A+Profit) *ODC-Defined as anything other than labor, subcontracts, and/or material that is directly attributable to a contract per FAR 31.202. Examples include rental charges and travel etc.

NOTE: Please fill in within the yellow highlighted boxes, the fixed labor rate, proposed G&A and proposed Profit rates.

NOTE: Labor rates and Profit rates used to calculate for the overall price of the base contract award shall be the basis for pricing on all modifications under this contract.

File details come from the government source that posted it. Updated .