N4523A19R0800__Amendment_5_Answer_To_Request_for_Clarification.pdf

PDF 10 KB Posted

Attached to
USS SSBN Submarine Engineered Refueling Overhaul (ERO) Preservation and non-SUBSAFE Structural Repairs
Solicitation number
N4523A19R0800
Issued by

About this file

Answers to Request for Clarifications

View the file

Other files

File Type Posted
N4523A19R0800_0005.pdf PDF
N4523A19R0800__Amendment_5_Summary_17_Apr_19.pdf PDF
Attachment_J-4_Pricing_Worksheet_Revised_16_Apr_19.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USS SSBN Submarine Engineered Refueling Overhaul (ERO) Preservation and non-SUBSAFE Structural Repairs

N4523A19R0800

# N4523A19R0800 Dated 25 March 2019

Amendment 5 - Answer to Requests for Clarifications

Bidder’s Question #8:

The new J4 sheet has the “CFM/Equipment & Material Total Price” blocks blacked out with the exception of item 992-10-001. Where is the bidder to enter consumable materials (weld rod, grind wheels, etc.)?

Answer: The CFM/Equipment & Material Total Price on the summary sheet is a value derived from Tab 3 CFM Equip & Mat'l.

Consumable materials should be accounted for and incorporated in the loaded labor rate (previously stated as “fully burdened”) as clarified in Section L.

Bidder’s Question #9:

Summary sheet highlighted spaces do not include WI 992-10-001.

Answer: Work Items are colored coded categories as referenced in Tab 4 of Attachment J-4, Section L and Section M. WI # 992-10-001 is not a part of the colored coded categories.

[END OF BIDDERS QUESTIONS]

End of Amendment 5.