RFC_-_Questions&Answers.pdf
PDF 506 KB Posted
- Attached to
- RCD TOWING SERVICES Federal contract opportunity
- Solicitation number
- N4523A19Q4031
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFC_-_Questions&Answers_4.29.2019.pdf | ||
| 52.216-4_--_ECONOMIC_PRICE_ADJUSTMENT.docx | DOCX document | |
| Attachment_1_-_Statement_of_Work_(SOW)_Rev.1.pdf | ||
| BASIS_FOR_AWARD_-_Rev.1.docx | DOCX document | |
| Exhibits_-_CDRLs_&_DIDs_-_Rev.1.zip | ZIP file | |
| ADD'L_INSTRUCTION_TO_OFFEROR.docx | DOCX document | |
| 52.212-2_--_EVALUATION_-_COMMERCIAL_ITEMS.docx | DOCX document | |
| Exhibit_Table_A_-_Pricing_Schedule.xlsx | XLSX spreadsheet | |
| 52.204-17_--_OWNERSHIP_OR_CONTROL_OF_OFFEROR.docx | DOCX document | |
| 52.216-4_--_ECONOMIC_PRICE_ADJUSTMENT.docx | DOCX document | |
| Exhibits_-_CDRLs_&_DIDs.zip | ZIP file | |
| BASIS_FOR_AWARD.docx | DOCX document | |
| Attachment_2_-_Request_for_Clarification_(RFC)_Form.pdf | ||
| 52.216-18_ORDERING.docx | DOCX document | |
| 52.212-5_--_CONTRACT_TERMS_AND_CONDITIONS.docx | DOCX document | |
| Attachment_1_-_Statement_of_Work_(SOW).pdf | ||
| 52.216-19_--_ORDERING_LIMITATIONS.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N4523A19Q4031 RFC Questions & Answers
Question #1: Ocean boats/River boats – Is it acceptable to use the same boat for the ocean portion and the river portion provided the crew and boats meet both criteria’s?
Answer #1: Boat(s) and crewing must meet the criteria laid out in the Statement of Work (SOW). These criteria include, but are not limited to, paragraphs 2.2, 7.6, 7.16, and 7.19. This answer does not constitute a change to the solicitation.
Question #2: How many river tugs are required for the transit to Benton? 2 or 4?
Answer #2: Depends on whether PSNS & IMF orders a single tow or a dual tow (SOW paragraph 3.1).
Single tows ordered in accordance with SOW paragraph 8.19 require two river tugs. Dual tows ordered in accordance with SOW paragraph 8.20 require four river tugs. This answer does not constitute a change to the solicitation.