RFC2_Response.pdf

PDF 117 KB Posted

Attached to
Maintenance, Repair and Preservation of IX-536
Solicitation number
N4523A18R1076
Issued by

About this file

Request for Clarification #2 Response

View the file

Other files

File Type Posted
RFC5_Response.doc DOC document
RFC4_Response.doc DOC document
N4523A18R1076_SolicitationDrawings.zipx ZIPX file
RFC3_Response.pdf PDF
RFC1_Response.pdf PDF
Attachment_J-3_Request_for_Clarification_Form.doc DOC document
N4523A18R1076_IX-536.pdf PDF
Attachment_J-2_Price_Proposal_Worksheet_IX-536.xls XLS spreadsheet
Attachment_J-4_Contract_Performance_Data_Sheet.docx DOCX document
Exhibit_A_-_CDRLs_and_DIDs_Combined_IX-536.pdf PDF
Attachment_J-1_Statement_of_Work_IX-536_dated_9MAY2018.pdf PDF
Attachment_J-7_BAVR_Instructions.docx DOCX document
Attachment_J-5_Corporate_Experience_Data_Sheet.docx DOCX document
Attachment_J-6_GFP_Attachment.pdf PDF
IX-536_Draft_SOW.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR CLARIFICATION

N4523A18R1076

Attachment J-3

DATE OF REQUEST: 07/05/2018 QUESTION NO: 2

REQUIREMENT: IX-536

REQUISITION NO.: N4523A18R1076

ITEM NO:

TITLE:

PSNS&IMF CONTRACTS POC & PHONE:

See POCs listed on RFP.

PARA. NO: PAGE NO: CONTRACTOR:

PLANNER’S NAME: ATTACH. NO: CONTRACTOR POC & PHONE:

CONTRACTOR QUESTION: (ONE QUESTION PER PAGE)

What is the performance period? Is it full 90 days? (14 November 2018 to 6 February 2019.) or there will be reduced timeframe once we take possession of the vessel.

DO NOT WRITE BELOW THIS LINE

SPEC CHG: No DWG/REF CHG. No RQMTS CHG: No MAT'L CHG: No

TECHNICAL REVIEW: SERIAL NO:

The period of performance for this requirement is as stated in page 13 of the solicitation:

14 November 2018 through 06 February 2019

ALL RFCs MUST BE RECEIVED NO LATER THAN 2:00 P.M. (PST), 25 July 2018.