N4523A18R1060 Small Boat MAC Questions and Answers
The table below shows all questions (with answers) the Government has received resulting from
N4523A18R1060 Small Boat MAC Pre‐Solicitation Briefing as well as all questions asked during the
Synopsis.
PWS
Reference
Text
Question
Answer
1 Paragraph 1.5 Certain vessels are not trailered and will be available for pickup at one of several Government locations (Naval Magazine Indian Island, Naval Base Kitsap Bangor, CNRNW Naval Base Everett, or Naval Base Bremerton).
Non-trailered vessels must be towed, not driven to the contractor’s facility.
Will the Government provide a quantity of non-trailered boats by location?
Vessel locations will be given at task order level.
2 Paragraph 1.3 The Contractor should project specified work to take place from approximately June 2018 through September 2020.
FedBizOpps.gov website Expected Period of Performance section indicates July 2018 start date. Which start date, June or July, is more accurate?
The Government expects ordering period for this contract to begin in July 2018.
3 Paragraph 1.3 Work is estimated to take no more than 21 days per vessel, dependent on the number of tasks to be assigned.
FedBizOpps.gov website Expected Period of Performance section indicates work is estimated to take up to 35 days per vessel. Which duration, 21 or 35 days, is more accurate?
Each vessel’s duration is expected not to exceed 35 days. Each vessel will have a specific availability, identified at the task order level.
4 Paragraph 1.8.1 In the event that deficiencies are discovered during the warranty period, an opportunity will be afforded the contractor to witness, inspect and comment on such deficiencies.
What are the expected warranties?
Standard commercial warranty will apply
IAW FAR 52.212-4.