SERVICE CONTRACT
PERFORMANCE WORK STATEMENT (PWS)
WORKSHEET
REV 8/28/15
JML #: 81590156
DD2276 : N4523A18RC94381 (Request for Contractual Procurement (RCP) Ship/Activity: C/740 Title: Enerpac jacking cylinders repair Place of Performance: Precision Hydraulics, LLC Period of Performance:
Background:
6 EA. Enerpac jacking cylinders were shipped to Precision Hydraulics, LLC. (An Enerpac preferred distributor/mechanic for our territory) for an open/inspection on 5/24/18. The Open/inspection JML doc attached to this is: 81080156. The inspections were done and a repair quote for all necessary work was obtained . C/740 is requesting the quoted work to be done to these jacks and have them shipped back to PSNS by .
Individual cylinder “serial numbers”:
1. HRA-X, model RR15013
2. HRA-AA, model RR15013
3. HRA-Y, model RR15013
4. HRA-Z, model RR15013
5. HRA-AB, model RR15013
6. HRA-E, model RR15013
1. REFERENCES:
1.1. Vendor quote is attached to JML, outlines work needed to be done and parts to replaced
1.2
2. WORK REQUIREMENTS:
2.1.1 Test cylinder HRA-Y in accordance to ASME B30.1 section 1-2.8.4 before repairs are done
2.1.2 Light polishing
2.1.3 Test V-66 holds in closed position
2.1.4. Replace seals and service pressure relief on retract side
2.1.5 Replace couplers
2.1.6 Repaint and test to ASME B30.1 section 1-2.8.4 post the above repairs
2.1.7 repairs include the following parts: 2 EA. Couplers CR400, 1. EA. Seal kit RR15013K, 1 EA.
Relief service kit C962110SR, plus labor
2.2.1: Cylinder HRA-AB requires pre service testing In accordance with ASME B30.1 section 1-2.8.4 2.2.2: Needs light polishing 2.2.3: Test V-66 holds in closed position
2.2.4 replace seals and service pressure relief on retract side
2.2.5 replace couplers
2.2.6 repaint and retest post repair in accordance to ASME B30.1 section 1-2.8.4
2.2.7 repair includes: 2 EA. Couplers CR400, 1. EA. Seal kit RR15013K, 1 EA. Relief service kit C962110SR. labor
2.3.1: Cylinder HRA-X requires pre service testing In accordance with ASME B30.1 section 1-2.8.4 2.3.2: Needs light polishing 2.3.3: Test V-66 holds in closed position 2.3.4: replace seals and service pressure relief on retract side
2.3.5 replace couplers
2.3.6 repaint and retest post repair in accordance to ASME B30.1 section 1-2.8.4 2.3.7: repair include the following parts: 2 EA. Couplers CR400, 1. EA. Seal kit RR15013K, 1 EA. Relief service kit C962110SR, plus labor
2.4.1 Cylinder HRA-AA requires pre service testing In accordance with ASME B30.1 section 1-2.8.4
2.4.2 needs light polishing
2.4.3 replace Test V-66 holds in closed position
2.4.4 replace seals and service pressure relief on retract side
2.4.5 replace couplers
2.4.6 repaint and retest post repair in accordance to ASME B30.1 section 1-2.8.4
2.4.7 repair include the following parts: 2 EA. Couplers CR400, 1. EA. Seal kit RR15013K, 1 EA. Relief
2.5.1 Cylinder HRA-Z requires pre service testing In accordance with ASME B30.1 section 1-2.8.4
2.5.2 Needs light polishing
2.5.3 Test V-66 holds in closed position
2.5.4 replace seals and service pressure relief on retract side
2.5.5 replace couplers
2.5.6 repaint and retest post repair in accordance to ASME B30.1 section 1-2.8.4
2.5.7 repair include the following parts: 2 EA. Couplers CR400, 1. EA. Seal kit RR15013K, 1 EA. Relief
2.6.1 Cylinder HRA-E requires pre service testing In accordance with ASME B30.1 section 1-2.8.4
2.6.2 Needs light polishing
2.6.3 Tested V-66 holds on closed position
2.6.4 replace seals and service pressure relief on retract side
2.6.5 replace couplers
2.6.6 repaint and retest post repair in accordance to ASME B30.1 section 1-2.8.4
2.6.7 repair include the following parts: 2 EA. Couplers CR400, 1. EA. Seal kit RR15013K, 1 EA. Relief
3. DELIVERABLE ITEMS: Cylinders were already delivered to Precision Hydraulics, LLC due to needing a preliminary inspection for repairs (JML 81080156). They will need to be shipped back to PSNS once the repairs have been completed by the vendor.
4. GOVERNMENT-FURNISHED ITEMS – PROPERTY, MATERIAL, EQUIPMENT,
SERVICES
4.1. 6 EA. Enerpac model RR15013 jacking cylinders, Each cylinder costs $7021.00 brand new, the total amount for 6 cylinders: $42,126.00
4.2. Location of GFP: Precision Hydraulics, LLC.
5. QUALITY ASSURANCE SURVEILLANCE PLAN: C/740 riggers will do a thorough inspection and operational checks of cylinders once they returned to PSNS. If there are any issues they will be addressed to the vendor ASAP.
6. SECURITY REQUIREMENTS: none
TRAVEL REQUIREMENTS: none
GOVERNMENT REPRESENTATIVE:
Jessica Ray, Code 702 Planning department. 360-476-5628, Jessica.r.ray1@navy.mil
WAAF acceptor: Tami Murphy, P: 360-476-8972, F: 360-476-0395, email: tami.murphy@navy.mil
7. ENVIROMENTAL AND SAFETY:
None.
8. ADDITIONAL CONSIDERATIONS:
11.1 Government Supported Work Hours: 0720-1602
Cog Tech Code Originator: Jessica Ray_____ Date: 05//09/2018____ mailto:Jessica.r.ray1@navy.mil
Cog Tech Code Review: ______________________ Date: ______________
Project (APS/WIM/PM) SOW Review: __________________ Date: ______________
C/413 SOW Review: _________________________ Date: ______________