N4523A17R0034
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
CLIN
Number
SWOB-25: Maintenance and Preservation
FFP
Job
Accomplish maintenance, repair and preservation of one SWOB-25 (Ship Waste Oil Offload Barge) in accordance with the Statement of Work (SOW),Attachment J-1.
FOB: Destination
NET AMT
Over and Above Work - SWOB-25
Additional repairs not specified in CLIN 0001 (e.g. within scope growth work identified during execution of the contract), per DFARS 252.217-7028, "Over and Above Work
(DEC 1991)".
DD Form 1423 CDRLs
Contract Data Requirements List: Submittals as required by CLIN's 0001/0002. See Exhibit A-1. NOT SEPARATELY PRICED (NSP).
CLAUSES INCORPORATED BY FULL TEXT
HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)
(a) As part of the negotiated fixed price or total estimated amount of this contact, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term “residual dollar amount” shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.
(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.
HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)
This entire contract is fixed price.
Section C - Descriptions and Specifications
STATEMENT OF WORK
Statement of Work (SOW) for the SWOB-25 requirement is incorporated under Attachment J-1.
5252.217-9107 GROWTH AND NEW WORK (SEP 1990)
(a) It is the Government's intention to ensure that, where it is determined that the work will be performed by the private sector, any growth or new work identified during the overhaul will be awarded to the initial prime Contractor only if a fair and reasonable price can be negotiated for such work. If a fair and reasonable price cannot be negotiated for the above actions, the Government may, at its election, pursue any or all of the following courses of action: (1) defer the work to a repair period after completion of the instant contract; (2) accomplish the work using Government employees during the original overhaul period. (Government employees may engage in and complete the assigned work while the ship is undergoing overhaul in the initial prime Contractor's facility pursuant to the "ACCESS TO VESSEL" clause (DFARS 252.217 7011)); and/or (3) conduct a separate, competitive procurement for growth or new work. Performance will be during the original overhaul period. The initial prime Contractor and other Master Ship Repair Agreement (MSRA) holders may enter this competition. If other than the initial prime Contractor is successful, the successful Contractor may engage in and complete the work while the ship is undergoing overhaul in the initial prime Contractor's facility pursuant to the "ACCESS TO VESSEL" clause.
(b) The offeror shall include in its proposed price the cost of supporting one or more third parties (including Government employees and/or other Contractors' workers) at the overhaul site in performance of growth and/or new work, should the Government elect to pursue such a course. Increased costs that may result from third party presence as described above, may include, but are not limited to: insurance; physical plant security; reasonable access for third party workers who must transit the Contractor's facility or any other work site provided by the Contractor at which the ship may be berthed; utilities used aboard the ship or in proximity of the ship in support of the overhaul; and similar requirements. Third party presence will occur only if the prime ship repair Contractor proposes other than a fair and reasonable price. The Contractor shall price anticipated added expenses associated with third party presence as a contingency into the fixed price offered for performance of the specified work package. The Contractor shall be guided in arriving at this contingency price based on a risk assessment relative to the probability of proposing fair and reasonable prices versus reaching a potential impasse with the Government which would precipitate third party presence.
(c) This requirement does not preclude the Government from using Government employees to perform new or growth work at any time during the availability provided the use of Government employees is in the best interests of the Government.
ACCESS TO THE VESSEL(S) (NAVSEA) (SEP 2016)
Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.
HQ C-2-0005 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (SEP 2016)
(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST
5510.3 ( ).
(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:
(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.
(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.
(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.
(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.
(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.
(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.
(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO.
(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.
(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.
(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non- U.S. citizens of hostile and/or communist-controlled countries.
(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non-U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated or default in accordance with the clause entitled "DEFAULT (FIXED-PRICE SUPPLY AND SERVICE)" (FAR 52.249-8), "DEFAULT (FIXED-PRICE RESEARCH AND DEVELOPMENT)" (FAR 52.249-9) or "TERMINATION (COST REIMBURSEMENT)" (FAR 52.249-6), as applicable.
(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.
(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.
(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.) except that, with respect to access to the vessel and worksite, the restrictions shall not apply to uniformed U.S.
Navy personnel who are non-U.S. citizens and who are either assigned to the ship or require access to the ship to perform their duties.
HQ C-2-0006 ADDITIONAL PROVISIONS RELATING TO GOVERNMENT PROPERTY (NAVSEA) (SEP 2009)
(a) For purposes of paragraph (h) of the clause entitled "GOVERNMENT PROPERTY" (FAR 52.245-1) in addition to those items of property defined in that clause as Government Property, the following shall also be included within the definition of Government Property:
(1) the vessel;
(2) the equipment on the vessel;
(3) movable stores;
(4) cargo; and
(5) other material on the vessel
(b) For purposes of paragraph (b) of the clause entitled "GOVERNMENT PROPERTY", notwithstanding any other requirement of this contract, the following shall not be considered Government Property:
(1) the vessel;
(2) the equipment on the vessel;
(3) movable stores; and
(4) other material on the vessel
HQ C-2-0007 APPROVAL BY THE GOVERNMENT (AT) (NAVSEA) (JAN 1983)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
HQ C-2-0014 CONTRACTOR'S PROPOSAL (NAVSEA) (MAR 2001)
(a) Performance of this contract by the Contractor shall be conducted and performed in accordance with detailed obligations to which the Contractor committed itself in Proposal in response to NAVSEA Solicitation No.
N4523A17R0034.
(b) The technical volume(s) of the Contractor's proposal is incorporated by reference and hereby made subject to the provisions of the "ORDER OF PRECEDENCE" (FAR 52.215-8) clause of this contract. Under the "ORDER OF PRECEDENCE" clause, the technical volume of the Contractor's proposal referenced herein is hereby designated as item
(f) of the clause, following "the specification" in the order of precedence.
HQ C-2-0016 DEPARTMENT OF LABOR SAFETY AND HEALTH STANDARDS FOR SHIP REPAIR (NAVSEA)
(APR 2015)
Attention of the Contractor is directed to the Occupational Safety and Health Act of 1970 (29 USC 651-678), and to the Safety and Health Regulations for Ship Repairing (29 CFR 1915), promulgated under Public Law 85-742, amending Section 41 of the Longshoremen's and Harbor Workers' Compensation Act (33 USC 941), and adopted by the Department of Labor as occupational safety or health standards under Section 6(a) of the Occupational Safety and Health Act of 1970 (See 29 CFR 1910.15). These regulations apply to all ship repair and related work, as defined in the regulations performed under this contract on the navigable waters of the United States including any dry dock and marine railway. Nothing contained in this contract shall be construed as relieving the Contractor from any obligations, which it may have for compliance with the aforesaid regulations.
HQ C-2-0018 DISPOSAL OF SCRAP (NAVSEA) (JAN 2008)
(a) All Government scrap resulting from accomplishment of any job order is the property of the Contractor to be disposed as it sees fit. Scrap is defined as property that has no reasonable prospect of being sold except for the recovery value of its basic material content. The determination as to which materials are scrap and which materials are salvage, will be made, or concurred in, by the duly appointed Property Administrator for the cognizant SUPSHIP or RMC Office.
(b) As consideration for retaining the Government's scrap, the Contractor's price for the performance of the work required herein shall be a net price reflecting the value of the Government scrap.
(c) This requirement is not intended to conflict in any way with the clauses of this contract entitled "PERFORMANCE" (DFARS 252.217-7010) or "GOVERNMENT PROPERTY" (FAR 52.245-1) under the Master Contract in effect at the time of job order award, nor does it relieve the Contractor of any other requirement under such clauses.
HQ C-2-0021 DRYDOCK CERTIFICATION (NAVSEA) (APR 2015)
The drydocking of all vessels on or after 1 January 1980 shall be accomplished in dry docks certified in accordance with MIL-STD-1625D(SH) dated 27 August 2009 as invoked by NAVSEA Standard Item 009-01.
HQ C-2-0023 EXCLUSION OF MERCURY (NAVSEA) (MAY 1998)
Mercury or mercury containing compounds shall not be intentionally added or come in direct contact with hardware or supplies furnished under this contract.
HQ C-2-0028 GOVERNMENT SURPLUS PROPERTY (NAVSEA) (SEP 1990)
No former Government surplus property or residual inventory resulting from terminated Government contracts shall be furnished under this contract unless (i) such property is identified in the Special Contract Requirements or (ii) is approved in writing by the Contracting Officer. Notwithstanding any such identification in the Special Contract Requirements or approval by the Contracting Officer, the Contractor agrees all items or components described in this requirement shall comply in all respects with the specifications contained herein.
HQ C-2-0029 HEAVY WEATHER PLAN (NAVSEA) (JUN 1999)
In order to ensure that Naval vessels and material are protected during gales, storms, hurricanes and destructive weather, the Contractor is required to have a written Heavy Weather Plan (HWP) which assigns responsibilities and prescribes actions to be taken on the approach of and during heavy weather conditions as delineated in NAVSEA Standard Item (SI) 009-69. In accordance with SI 009-69, the Contractor shall furnish to the cognizant Shipbuilding, Conversion and Repair, U.S. Navy, a copy of such HWP, and shall make such changes in the plan as the Supervisor considers necessary and reasonable to protect and care for vessels and machinery and equipment to be installed therein.
In the event the Supervisor directs the Contractor to implement the HWP pursuant to SI 009-69 the Contractor may submit to the Contracting Officer a request for reimbursement for costs resulting from such actions together with any documentation that the Contracting Officer may reasonably require. The Government shall reimburse the Contractor for all reasonable, allowable and allocable costs resulting from the Contractor's implementation of the HWP based on such Government direction.
HQ C-2-0030 INFORMATION AND DATA FURNISHED BY THE GOVERNMENT (FIXED-PRICE) (NAVSEA)
(SEP 2009)
(a) Contract Specifications. The Government will furnish, if not included as an attachment to the contract, any unique contract specifications set forth in Section C.
(b) Contract Drawings and Data. The Government will furnish contract drawings, design agent drawings, ship construction drawings, and/or other design or alteration data cited or referenced in Section C or in the contract specification as mandatory for use or for contract performance.
(c) Government Furnished Information (GFI). GFI is defined as that information essential for the installation, test, operation, and interface support of all Government Furnished Material enumerated on NAVSEA Form 4205/19 or Schedule A, as applicable, attached to the contract. The Government shall furnish only the GFI identified on the NAVSEA Form 4340/2 or Schedule C, as applicable, attached to the contract. The GFI furnished to the contractor need not be in any particular format. Further, the Government reserves the right to revise the listing of GFI on the NAVSEA Form 4340/2 or Schedule C, as applicable, as follows:
(1) The Contracting Officer may at any time by written order:
(i) delete, supersede, or revise, in whole or in part, data listed or specifically referenced in NAVSEA Form 4340/2 or Schedule C, as applicable; or
(ii) add items of data or information to NAVSEA Form 4340/2 or Schedule C, as applicable; or
(iii) establish or revise due dates for items of data or information in NAVSEA Form 4340/2 or Schedule C, as applicable.
(2) If any action taken by the Contracting Officer pursuant to subparagraph (1) immediately above causes an increase or decrease in the costs of, or the time required for, performance of any part of the work under this contract, the contractor may be entitled to an equitable adjustment in the contract price and delivery schedule in accordance with the procedures provided for in the clause of this contract entitled "CHANGES--FIXED-PRICE"
(FAR 52.243-1).
(d) Except for the Government information and data specified by paragraphs (a), (b), and (c) above, the Government will not be obligated to furnish the Contractor any specification, standard, drawing, technical documentation, or other publication, notwithstanding anything to the contrary in the contract specifications, the GFI listed on the NAVSEA Form 4340/2 or Schedule C, as applicable, the clause of this contract entitled "GOVERNMENT PROPERTY" (FAR 52.245-1) or "GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES " (FAR 52.245-2), as applicable, or any other term or condition of this contract.
(e) Referenced Documentation. The Government will not be obligated to furnish Government specifications and standards, including Navy standard and type drawings and other technical documentation, which are referenced directly or indirectly in the contract specifications set forth in Section C and which are applicable to this contract as specifications. Such referenced documentation may be obtained:
(1) From the ASSIST database via the internet at http://assist.dla.mil/ ; or
(2) By submitting a request to the Department of Defense Single Stock Point (DoDSSP) Building 4, Section D 700 Robbins Avenue Philadelphia, Pennsylvania 19111-5094 Telephone (215) 697-6396 Facsimile (215) 697-9398.
Commercial specifications and standards, which may be referenced in the contract specification or any sub-tier specification or standard, are not available from Government sources and should be obtained from the publishers.
HQ C-2-0034 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (SEP 1990)
In accordance with the clause of this contract entitled "INSURANCE--WORK ON A GOVERNMENT INSTALLATION" (FAR 52.228-5), the Contractor shall procure and maintain insurance, of at least the kinds and minimum amounts set forth below:
(a) Workers' Compensation and Employer's Liability coverage shall be at least $100,000, except as provided in FAR 28.307(a).
(b) Bodily injury liability insurance coverage shall be written on the comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.
HQ C-2-0037 ORGANIZATIONAL CONFLICT OF INTEREST (NAVSEA) (JUL 2000)
(a) "Organizational Conflict of Interest" means that because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the Government, or the person's objectivity in performing the contract work is or might be otherwise impaired, or a person has an unfair competitive advantage. "Person" as used herein includes Corporations, Partnerships, Joint Ventures, and other business enterprises.
(b) The Contractor warrants that to the best of its knowledge and belief, and except as otherwise set forth in the contract, the Contractor does not have any organizational conflict of interest(s) as defined in paragraph (a).
(c) It is recognized that the effort to be performed by the Contractor under this contract may create a potential organizational conflict of interest on the instant contract or on a future acquisition. In order to avoid this potential conflict of interest, and at the same time to avoid prejudicing the best interest of the Government, the right of the Contractor to participate in future procurement of equipment and/or services that are the subject of any work under this contract shall be limited as described below in accordance with the requirements of FAR 9.5.
(d) (1) The Contractor agrees that it shall not release, disclose, or use in any way that would permit or result in disclosure to any party outside the Government any information provided to the Contractor by the Government during or as a result of performance of this contract. Such information includes, but is not limited to, information submitted to the Government on a confidential basis by other persons. Further, the prohibition against release of Government provided information extends to cover such information whether or not in its original form, e.g., where the information has been included in Contractor generated work or where it is discernible from materials incorporating or based upon such information. This prohibition shall not expire after a given period of time.
(2) The Contractor agrees that it shall not release, disclose, or use in any way that would permit or result in disclosure to any party outside the Government any information generated or derived during or as a result of performance of this contract. This prohibition shall expire after a period of three years after completion of performance of this contract.
(3) The prohibitions contained in subparagraphs (d)(1) and (d)(2) shall apply with equal force to any affiliate of the Contractor, any subcontractor, consultant, or employee of the Contractor, any joint venture involving the Contractor, any entity into or with which it may merge or affiliate, or any successor or assign of the Contractor.
The terms of paragraph (f) of this Special Contract Requirement relating to notification shall apply to any release of information in contravention of this paragraph (d).
(e) The Contractor further agrees that, during the performance of this contract and for a period of three years after completion of performance of this contract, the Contractor, any affiliate of the Contractor, any subcontractor, consultant, or employee of the Contractor, any joint venture involving the Contractor, any entity into or with which it may subsequently merge or affiliate, or any other successor or assign of the Contractor, shall not furnish to the United States Government, either as a prime contractor or as a subcontractor, or as a consultant to a prime contractor or subcontractor, any system, component or services which is the subject of the work to be performed under this contract. This exclusion does not apply to any recompetition for those systems, components or services furnished pursuant to this contract. As provided in FAR 9.505-2, if the Government procures the system, component, or services on the basis of work statements growing out of the effort performed under this contract, from a source other than the contractor, subcontractor, affiliate, or assign of either, during the course of performance of this contract or before the three year period following completion of this contract has lapsed, the Contractor may, with the authorization of the cognizant Contracting Officer, participate in a subsequent procurement for the same system, component, or service. In other words, the Contractor may be authorized to compete for procurement(s) for systems, components or services subsequent to an intervening procurement.
(f) The Contractor agrees that, if after award, it discovers an actual or potential organizational conflict of interest, it shall make immediate and full disclosure in writing to the Contracting Officer. The notification shall include a description of the actual or potential organizational conflict of interest, a description of the action which the Contractor has taken or proposes to take to avoid, mitigate, or neutralize the conflict, and any other relevant information that would assist the Contracting Officer in making a determination on this matter. Notwithstanding this notification, the Government may terminate the contract for the convenience of the Government if determined to be in the best interest of the Government.
(g) Notwithstanding paragraph (f) above, if the Contractor was aware, or should have been aware, of an organizational conflict of interest prior to the award of this contract or becomes, or should become, aware of an organizational conflict of interest after award of this contract and does not make an immediate and full disclosure in writing to the Contracting Officer, the Government may terminate this contract for default.
(h) If the Contractor takes any action prohibited by this requirement or fails to take action required by this requirement, the Government may terminate this contract for default.
(i) The Contracting Officer's decision as to the existence or nonexistence of an actual or potential organizational conflict of interest shall be final.
(j) Nothing in this requirement is intended to prohibit or preclude the Contractor from marketing or selling to the United States Government its product lines in existence on the effective date of this contract; nor, shall this requirement preclude the Contractor from participating in any research and development or delivering any design development model or prototype of any such equipment. Additionally, sale of catalog or standard commercial items are exempt from this requirement.
(k) The Contractor shall promptly notify the Contracting Officer, in writing, if it has been tasked to evaluate or advise the Government concerning its own products or activities or those of a competitor in order to ensure proper safeguards exist to guarantee objectivity and to protect the Government's interest.
(l) The Contractor shall include this requirement in subcontracts of any tier which involve access to information or situations/conditions covered by the preceding paragraphs, substituting "subcontractor" for "contractor" where appropriate.
(m) The rights and remedies described herein shall not be exclusive and are in addition to other rights and remedies provided by law or elsewhere included in this contract.
(n) Compliance with this requirement is a material requirement of this contract.
HQ C-2-0038 PERMITS AND RESPONSIBILITIES (NAVSEA) (SEP 1990)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any applicable Federal, State, and Municipal laws, codes, and regulations, in connection with any movement over the public highways of overweight/overdimensional materials.
HQ C-2-0039 PLANS AND OTHER DATA (FT) (NAVSEA) (JAN 1983)
Whenever the Department shall so require, the Contractor shall, at the cost of reproduction, furnish to whomsoever may be designated by the Department (including other shipbuilding Contractors), copies of working plans (including reproducibles), selected record plans, indices, material schedules, plan schedules, purchase specifications and other data relating to the construction of the vessel. The furnishing of such data shall not constitute any guaranty or warranty, either express or implied, by the Contractor other than that they are correct copies of such data.
HQ C-2-0044 PROTECTION OF THE VESSEL (NAVSEA) (SEP 1990)
(a) The Contractor shall exercise reasonable care, as agreed upon with the Supervisor, to protect the vessel from fire, and shall maintain a system of inspection over the activities of its welders, burners, riveters, painters, pipe fitters, and similar workers, and of its subcontractors, particularly where such activities are undertaken in the vicinity of the vessel's magazines, fuel oil tanks, or store rooms containing inflammable materials. All ammunition, fuel oil, motor fuels, and cleaning fluids shall have been off-loaded and the tanks cleaned, except as may be mutually agreed upon between the Contractor and the Supervisor prior to work on the vessel by the Contractor. Fire hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in dry dock. All tanks under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe to the extent necessary, and the Contractor shall furnish the vessel's Gas Free Officer and the Supervisor with a "Gas Chemists' Certificate" before any hot work is done. The Contractor shall maintain a fire watch aboard the vessel in areas where the Contractor is working. All other fire watches aboard the vessel shall be the responsibility of the Government.
(b) Except as otherwise provided in contractually invoked technical specifications or NAVSEA furnished directives, while the vessel is at the Contractor's plant and when the temperature becomes as low as thirty-five degrees Fahrenheit, the Contractor shall assist the Government when requested in keeping all pipe-lines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected by the Contractor from frost damage by applied heat through the use of a salamander or other proper means.
(c) The work shall, whenever practicable, be performed in such manner as not to interfere with the work performed by military personnel attached to the vessel, and provisions shall be made so that personnel assigned shall have access to the vessel at all times, it being understood that such personnel will not unduly interfere with the work of the Contractor's workmen.
(d) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by its employees, or the work performed by the Contractor in accordance with this contract, and at the completion of such work shall remove all rubbish from and about the site of the work, and shall leave the work in its immediate vicinity "broom clean", unless more exactly specified by the Supervisor.
HQ C-2-0047 REMOVALS (NAVSEA) (SEP 1990)
The Contracting Officer may, by written notice to the Contractor, direct removal of any or all of the property from storage. Within the shortest practicable time after receipt of such notice, but in no event more than thirty (30) days thereafter, unless a longer period is agreed to by the parties hereto, the Contractor will dismantle, prepare for shipment and load the item of property affected, on a common carrier at the place of storage in accordance with sound industrial practice and such instructions as the Contracting Officer may issue. The Contracting Officer may, by written notice to the Contractor direct the return of any item of the property removed, and the Contractor shall store the property at the Plant as provided for in Section F. In the event such items are removed and forwarded to a Government depot or to a party other than the Contractor, removal and return to storage of said items shall be at the expense of the Government.
HQ C-2-0051 SPECIFICATIONS AND STANDARDS (NAVSEA) (AUG 1994)
(a) Definitions.
(i) A "zero-tier reference" is a specification, standard, or drawing that is cited in the contract (including its attachments).
(ii) A "first-tier reference" is either: (1) a specification, standard, or drawing cited in a zero-tier reference, or (2) a specification cited in a first-tier drawing.
(b) Requirements.
All zero-tier and first-tier references, as defined above, are mandatory for use. All lower tier references shall be used for guidance only.
HQ C-2-0057 TESTS AND TRIALS - ALTERNATE I (NAVSEA) (MAY 1993)
During the conduct of required tests and trials, the vessel shall be under the control of the Contractor and the Contractor's crew with representatives of the Contractor and the Government on board to determine whether or not the work done by the Contractor has been satisfactorily performed. The Contractor shall provide and install all fittings and appliances which may be necessary for dock and sea trials to enable the representatives of the
Government to determine whether the requirements of the contract have been met, and the Contractor shall install and remove instruments and apparatus furnished by the Government for such trials, as required by the specifications.
HQ C-2-0059 UPDATING SPECIFICATIONS AND STANDARDS (NAVSEA) (AUG 1994)
If, during the performance of this or any other contract, the contractor believes that any contract contains outdated or different versions of any specifications or standards, the contractor may request that all of its contracts be updated to include the current version of the applicable specification or standard. Updating shall not affect the form, fit or function of any deliverable item or increase the cost/price of the item to the Government. The contractor should submit update requests to the Procuring Contracting Officer with copies to the Administrative Contracting Officer and cognizant program office representative for approval. The contractor shall perform the contract in accordance with the existing specifications and standards until notified of approval/disapproval by the Procuring Contracting Officer. Any approved alternate specifications or standards will be incorporated into the contract.
Section D - Packaging and Marking
HQ D-2-0008 MARKING OF REPORTS (NAVSEA) (SEP 1990)
All reports delivered by the Contractor to the Government under this contract shall prominently show on the cover of the report:
(1) name and business address of the Contractor
(2) contract number
(3) contract dollar amount
(4) whether the contract was competitively or non-competitively awarded
(5) sponsor:
(Name of Individual Sponsor)
(Name of Requiring Activity)
(City and State)
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 N/A N/A N/A N/A 0003 N/A N/A N/A N/A
CLAUSES INCORPORATED BY REFERENCE
52.246-2 Inspection Of Supplies--Fixed Price AUG 1996 52.246-16 Responsibility For Supplies APR 1984
HQ E-2-0002 ADDITIONAL PROVISIONS RELATING TO CORRECTION OF DEFECTS (NAVSEA) (OCT 1990)
In case any work done or materials or supplies furnished by the Contractor under this contract for any vessel, or the equipment thereof, shall within sixty (60) days of delivery of the vessel to the Government, or the date of final acceptance, whichever occurs first, prove defective or deficient, such defects or deficiencies shall, as required by the Government, be corrected or repaired by the Contractor to the satisfaction of the Contracting Officer; provided, however, that with respect to any individual work item which is incomplete or deficient at the time of delivery or acceptance, the Contractor's obligation under this requirement to correct or repair such deficiency shall extend sixty
(60) days from the date of such correction or repair, whichever occurs first. The Contractor shall be entitled to allowable costs for corrections or repairs performed in accordance with this requirement but shall not be entitled to any additional fee for such work.
HQ E-2-0005 FINAL ACCEPTANCE (AT) (NAVSEA) (MAY 1995)
Each vessel shall be finally accepted upon the expiration of its guaranty period.
HQ E-2-0015 QUALITY MANAGEMENT SYSTEM REQUIREMENTS (NAVSEA) (APR 2017)
Quality Management System Requirements. The Contractor shall provide and maintain a quality management system that, as a minimum, adheres to the requirements of ANSI/ISO/ASQ 9001-2015 Quality Management Systems and supplemental requirements imposed by this contract. The quality management system procedures, planning, and all other documentation and data that comprise the quality management system shall be made available to the Government for review. Existing quality documents that meet the requirements of this contract may continue to be used. The Government may perform any necessary inspections, verifications, and evaluations to ascertain conformance to requirements and the adequacy of the implementing procedures. The Contractor shall require of subcontractors a quality management system achieving control of the quality of the services and/or supplies provided. The Government reserves the right to disapprove the quality management system or portions thereof when it fails to meet the contractual requirements.
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 08-JAN-2018 TO
16-MAR-2018
N/A PUGET SOUND NAVAL SHIPYARD CODE
JOHN MUSANTE
1400 FARRAGUT AVE
BREMERTON WA 98314
360-476-4065 FOB: Destination
N4523A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
52.211-17 Delivery of Excess Quantities SEP 1989 52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984 52.247-34 F.O.B. Destination NOV 1991
HQ F-2-0004 F.O.B. DESTINATION (NAVSEA) (APR 2015)
All supplies hereunder shall be delivered with all transportation charges prepaid, in accordance with the clause hereof entitled "F.O.B. DESTINATION" (FAR 52.247-34) in accordance with the delivery instructions specified herein.
The Contractor shall not ship directly to a military air or water port terminal without authorization by the cognizant Contract Administration Office.
Except when the Material Inspection and Receiving Report (MIRR) (DD 250) is used as an invoice, the Contractor shall enter unit prices on all MIRR copies. Contract line items shall be priced using actual prices, or if not available, estimated prices. When the price is estimated, an "E" shall be entered after the price.
All data to be furnished under this contract shall be delivered prepaid to destination(s) at the time(s) specified on the Contract Data Requirements List(s), DD Form 1423.
Section G - Contract Administration Data
252.204-0001 Line Item Specific: Single Funding SEP 2009
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
(End of clause)
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
(Contracting Officer: Insert applicable document type(s). Note: If a “Combo” document type is identified but not supportable by the Contractor's business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
(Contracting Officer: Insert inspection and acceptance locations or “Not applicable”.)
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____ Inspect By DoDAAC ____ Ship To Code ____ Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____
(*Contracting Officer: Insert applicable DoDAAC information or “See schedule” if multiple ship to/acceptance locations apply, or “Not applicable.”)
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
(Contracting Officer: Insert applicable email addresses or “Not applicable.”)
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
HQ G-2-0002 Enter below the address (street and number, city, county, state and zip code) of the Contractor's facility which will administer the contract if such address is different from the address shown on the SF 26 or SF 33, as applicable.
HQ G-2-0009 SUPPLEMENTAL INSTRUCTIONS REGARDING INVOICING (NAVSEA) (APR 2015)
(a) For other than firm fixed priced contract line item numbers (CLINs), the Contractor agrees to segregate costs incurred under this contract/task order (TO), as applicable, at the lowest level of performance, either at the technical instruction (TI), sub line item number (SLIN), or contract line item number (CLIN) level, rather than on a total contract/TO basis, and to submit invoices reflecting costs incurred at that level. Supporting documentation in Wide Area Workflow (WAWF) for invoices shall include summaries of work charged during the period covered as well as overall cumulative summaries by individual labor categories, rates, and hours (both straight time and overtime) invoiced; as well as, a cost breakdown of other direct costs (ODCs), materials, and travel, by TI, SLIN, or CLIN level. For other than firm fixed price subcontractors, subcontractors are also required to provide labor categories, rates, and hours (both straight time and overtime) invoiced; as well as, a cost breakdown of ODCs, materials, and travel invoiced. Supporting documentation may be encrypted before submission to the prime contractor for WAWF invoice submittal. Subcontractors may email encryption code information directly to the Contracting Officer (CO) and Contracting Officer Representative (COR). Should the subcontractor lack encryption capability, the subcontractor may also email detailed supporting cost information directly to the CO and COR; or other method as agreed to by the CO.
(b) Contractors submitting payment requests and receiving reports to WAWF using…