Answer to question 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Revised_J-2_Admiral's_Barge_Price_Breakdown_Spreadsheet.xls | XLS spreadsheet | |
| N4523A-17-R-0007_Amendment_2.pdf | ||
| RFC_001_Wood_repairs_ANS.docx | DOCX document | |
| RFC_003_Gypsy_head_ANS.docx | DOCX document | |
| N4523A-17-R-0007_Amendment_1.pdf | ||
| N4523A-17-R-0007_CDRLs_and_DIDs_2_of_2.pdf | ||
| J-2_Admiral's_Barge_Price_Breakdown_Spreadsheet.xls | XLS spreadsheet | |
| N4523A-17-R-0007_CDRLs_and_DIDs_1_of_2.pdf | ||
| J-3_REQUEST_FOR_SPECIFICATION_CLARIFICATION.docx | DOCX document | |
| N4523A-17-R-0007_Solicitation_.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR SPECIFICATION CLARIFICATION
| DATE OF REQUEST: 11/17/16 |
| QUESTION NO: 005 |
| REQUIREMENT: |
| REQUISITION NO.: N4523A-17-R-0007 |
ITEM NO:
TITLE:
ISSUING OFFICE POC (CODE 446):
J. Brian Fergus
(360) 476-4470 James.Fergus@navy.mil
| PARA. NO: 3.6.1 |
| PAGE NO: |
| CONTRACTOR: |
| PLANNER’S NAME: |
| ATTACH. NO: |
| CONTRACTOR POC & PHONE: |
CONTRACTOR QUESTION: - The windshield has been in previous contracts "to re-do the gasketing and hinges to make the windshield watertight". The entire frame around the windows is out of plane with the windows and the windows and frame need to be rebuilt from scratch. Otherwise this will be a repeated problem in every contract. Can this contract be re-written to make this a rebuild of windows and window frames?
DO NOT WRITE BELOW THIS LINE
| SPEC CHG: N |
| DWG/REF CHG. N |
| RQMTS CHG: N |
| MAT'L CHG: N |
| TECHNICAL REVIEW: C/411.1JT |
| SERIAL NO: 005 |
Accomplish the requirements of the SOW. During contract execution and after the removal of the windshield assemblies, the contractor may submit a CFR documenting actual conditions found and proposed repairs. The contract will not be changed at this time.