DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND MARIANAS
PSC 455, BOX 195
FPO AP 96540-2937
IN REPLY REFER TO:
RFI-01
20 February 2020
REQUEST FOR QUOTATION (RFQ) N40192-20-Q-5001; MONITORING FOR SEA TURTLE
NESTING ACTIVITY, MILITARY LEASED LANDS, TINIAN
REQUEST FOR INFORMATION (RFI) – NOTICE 01
QUESTION 1 (Q1): How should the pages in this solicitation response be numbered? (REF: RFQ Section L, Par.1, P.19)
Answer 1(A1): The RFQ does not prescribe a specific format for page numbers. However, all Offerors shall adhere to any page limitations as indicated in the RFQ.
Q2: Are the Cover Page, Table of Contents, Acronym List, and Executive Summary
/Introduction included in the page limitations? (REF: RFQ Section L, Par.1, P.19)
A2: The RFQ does not prescribe instructions for submitting a Cover Page, Table of Contents, Acronym List, and Executive Summary.
Q3: What exactly should be included for Factor 3 – Price? A completed Section B –
Supplies/Services and Prices? (REF: RFQ Section M, Par. 5, P.21)
A3: Yes. The Offeror’s quotation shall contain a response to each of the evaluation factors and shall be in the form prescribed by this RFQ.
Q4: Can projects be in progress or must they be 100% complete? (REF: RFQ Section M, Par.
5A, P.22)
A4: Submit projects completed within a five-year period.
Q5: Page 6 of the PWS states “The Contractor shall assign a PM specifically for this task…”
Is an assigned PM required for the solicitation? Or, can a PM be assigned after contract award? (REF: RFQ Section J, PWS, PWS P.6/RFQ P.35)
A5: The assigned PM is required as part of the PWS. The Contractor shall assign a PM for this task in accordance with qualifications prescribed. The Contractor will be accountable for completing all contract requirements to include the period of performance.
==================================End of Notice==============================
Note: This RFI Notice is provided herein for information purposes only. Any changes to the RFQ shall be implemented by amendment only.