View the file

Other files

File Type Posted
RFQN4019220Q5001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING COMMAND MARIANAS

PSC 455, BOX 195

FPO AP 96540-2937

IN REPLY REFER TO:

RFI-01

20 February 2020

REQUEST FOR QUOTATION (RFQ) N40192-20-Q-5001; MONITORING FOR SEA TURTLE

NESTING ACTIVITY, MILITARY LEASED LANDS, TINIAN

REQUEST FOR INFORMATION (RFI) – NOTICE 01

QUESTION 1 (Q1): How should the pages in this solicitation response be numbered? (REF: RFQ Section L, Par.1, P.19)

Answer 1(A1): The RFQ does not prescribe a specific format for page numbers. However, all Offerors shall adhere to any page limitations as indicated in the RFQ.

Q2: Are the Cover Page, Table of Contents, Acronym List, and Executive Summary

/Introduction included in the page limitations? (REF: RFQ Section L, Par.1, P.19)

A2: The RFQ does not prescribe instructions for submitting a Cover Page, Table of Contents, Acronym List, and Executive Summary.

Q3: What exactly should be included for Factor 3 – Price? A completed Section B –

Supplies/Services and Prices? (REF: RFQ Section M, Par. 5, P.21)

A3: Yes. The Offeror’s quotation shall contain a response to each of the evaluation factors and shall be in the form prescribed by this RFQ.

Q4: Can projects be in progress or must they be 100% complete? (REF: RFQ Section M, Par.

5A, P.22)

A4: Submit projects completed within a five-year period.

Q5: Page 6 of the PWS states “The Contractor shall assign a PM specifically for this task…”

Is an assigned PM required for the solicitation? Or, can a PM be assigned after contract award? (REF: RFQ Section J, PWS, PWS P.6/RFQ P.35)

A5: The assigned PM is required as part of the PWS. The Contractor shall assign a PM for this task in accordance with qualifications prescribed. The Contractor will be accountable for completing all contract requirements to include the period of performance.

==================================End of Notice==============================

Note: This RFI Notice is provided herein for information purposes only. Any changes to the RFQ shall be implemented by amendment only.

File details come from the government source that posted it. Updated .