Amendment 0001 7495221.pdf

PDF 1023 KB Posted

Attached to
Storefront Door Replacement, Building 293
Solicitation number
N400857495221
Issued by

About this file

This is Amendment #0001 to NAVFAC Specification 7495221 for Storefront Door Replacement at Building 293, Marine Corps Air Station Cherry Point, North Carolina. The amendment is issued by FEAD Cherry Point (Code N40085) and has an effective date of August 6, 2025. The key change updates the Bond Requirements paragraph to mandate that bid bonds are required in accordance with Federal Acquisition Regulation (FAR) 52.228-1, and contractors must submit an electronic copy of their bid bond with their proposal or risk having their proposal deemed nonresponsive and removed from consideration.

The amendment confirms that critical dates remain unchanged: the deadline to submit pre-award RFIs remains August 12, 2025 at 9:00 AM, and the proposal due date remains August 19, 2025 at 2:00 PM local time. Contractors must acknowledge receipt of this amendment with their proposal submission to avoid potential rejection. All other contract terms and conditions remain unchanged. The document emphasizes the importance of acknowledging the amendment and provides instructions for contractors who may have already submitted proposals prior to receiving this amendment.

View the file

Other files

File Type Posted
Amendment 0002 7495221.pdf PDF
7495221 Storefront door replacement SOW.pdf PDF
7495221 RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVFAC

SPECIFICATION

7495221 Storefront Door

Replacement, Building 293

MCAS Cherry Point, NC

AMENDMENT #0001

IMPORTANT

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.

If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

0001 8/6/2025 7495221

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code FEAD Cherry Point

PSC BOX 8006

CHERRY POINT, NC 28533

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION

Storefront Door Replacement, Building 293

9B. DATED (SEE ITEM 11)

AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

7495221 Storefront Door Replacement, Building 293, Marine Corps Air Station Cherry Point, NC

The deadline to submit pre-award RFI’s REMAINS 12 August 2025 at 9:00 AM.

The proposal due date of 19 August 2025 at 2:00 PM local time REMAINS unchanged.

See continuation pages.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

STOREFRONT DOOR REPLACEMENT, BUILDING 293 Amendment 0001 MCAS Cherry Point, North Carolina Project No. 7495221

Block 14. DESCRIPTION OF AMENDMENT (cont.)

A. This amendment updates the Bond Requirements paragraph provided in the original Request for Proposal to the following:

Bond Requirements: Bid bonds are required in accordance with Federal Acquisition Regulation (FAR) 52.228-1. An electronic copy of your bid bond must be submitted with your proposal. Failure to submit an electronic copy of your bid bond with your proposal will result in your proposal being deemed nonresponsive and your proposal removed from consideration.

B. All other contract terms and conditions remain unchanged.