7474649 Amendment 0002.pdf
PDF 935 KB Posted
- Solicitation number
- N400857474649
About this file
Amendment 0002 for solicitation N400857474649 provides updates and clarifications for a contract to clean and paint markings on runways, taxiways, and aprons at Marine Corps Air Station Cherry Point, North Carolina. The amendment responds to pre-award requests for information (RFIs) and addresses specific details about the project scope, including cleaning and painting requirements for various runway and taxiway areas. Key areas include Runways 14L/32R and 5L/23R, multiple taxiways (Hotel, Bravo, Foxtrot, Cala, and others), warmup areas, displaced threshold markings, compass rose markings, and helicopter spots.
The amendment maintains the original proposal deadline of 15 May 2025 at 12:00 PM local time, with the deadline to submit pre-award RFIs remaining 5 May 2025 at 9:00 AM. The scope of work specifies contractor responsibilities for project safety, submittals, and material compliance, with the government reserving the right to sample and test materials delivered to the job site. Work hours are set for 7 am to 3:30 pm Monday through Saturday, with coordination required between the construction manager and Airfield Manager to close work areas to air traffic.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001 7474649.pdf | ||
| Bravo-1.jpg | JPG image | |
| 7474649SpecsAsOneSIGNED.pdf | ||
| RFP 7474649.pdf | ||
| Bravo-2.jpg | JPG image | |
| WU2-2.jpg | JPG image | |
| Areas for Airfield Paint-Powerwash Proposal 2025.pptx | PPTX presentation | |
| 14L-1.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC
SPECIFICATION
7474649 Clean & Paint Markings on
Runway, Taxiway, & Aprons G23
MCAS Cherry Point, NC
AMENDMENT #0002
IMPORTANT
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.
If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0002 05/06/2025 7474649
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
CG MCAS Cherry Point
FACILITIES, ROICC
B-163, CURTIS ROAD
PSC BOX 8006
CHERRY POINT, NC 28533
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION
Clean & Paint Markings on Runway, Taxiway, & Aprons G23
9B. DATED (SEE ITEM 11)
AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
7474649 Clean & Paint Markings on Runway, Taxiway, & Aprons G23, Marine Corps Air Station Cherry Point, NC
Amendment 0002 is being issued to respond to pre-award RFI's.
The deadline to submit pre-award RFI’s REMAINS 5 May 2025 at 9:00 AM.
The proposal due date of 15 May 2025 at 12:00 PM local time REMAINS unchanged.
See Attached.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
Amendment 0002 7474649 Clean & Paint Markings on Runways, Taxiways, & Aprons G23
RFI Responses:
1. Are there any quantities that can be provided for the cleaning and repainting?
Response:
The map attached shows areas to be cleaned and the areas to be cleaned and painted. They are marked with different colors.
2. At the site visit it was brought up that some current markings may need to be moved a bit. The general project description notes cleaning and restriping. Are there any areas that will need paint removal? If so, please identify and provide drawings if the markings are to be repainted in a different area.
Response:
The double-yellow new hold-short line is the only new line (essentially connecting the two hold-short lines from Hotel & Bravo Taxiway) and subsequently moving the Tower helipad as depicted in the slide. It is stated in the scope of work. Map will be added for clarification.
3. Several painted areas in the site visit had grass growing on the double edge line areas. Will the government be able to spray herbicide on these areas before work starts?
Response:
The government will spray the areas 2 weeks before start.
4. It is noted that work hours will be 7 am -3:30 Monday through Saturday. Will work areas be closed to air traffic as the work progresses from area to area?
Response:
Coordination between the CM and Airfield Manager will ensure area is closed to air traffic.
Please request 2 weeks prior to work starting.
Subj: AMENDMENT TO WO 7474649, CLEAN & PAINT MARKINGS ON RUNWAY, TAXIWAY, &
APRONS , MCAS CHERRY POINT NC
CONTINUATION SHEET
PROJECT TABLE OF CONTENTS
SECTION 01 90 00, SCOPE OF WORK is deleted and 01 90 00, SCOPE OF WORK, dated 5/5/2025, as shown in the footer, is added to the Project Table of Contents and accompanies this Amendment.
CLEAN & PAINT MARKINGS ON RUNWAY, TAXIWAY, & APRONS 7474649
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
01 14 00 11/22, CHG 4: 02/25 WORK RESTRICTIONS
01 20 00 11/20, CHG 5: 02/25 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 5:02/25 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 16.00 20 08/18, CHG 1: 08/20 SMALL PROJECT CONSTRUCTION PROGRESS
SCHEDULES
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 90 00 02/16 SCOPE OF WORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 17 23.19 11/24 AIRFIELD PAVEMENT MARKINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
DOCUMENT 01 90 00
SCOPE OF WORK
02/16
PART 1 GENERAL
1.1 CONTRACTOR RESPONSIBILITIES
The contractor will be responsible for project safety including his employees and the building occupants where they may be effected by construction activities. Provide necessary enclosures and barricades as required to effectively control access to the work area. Provided all required safety measures to insure the safety of his employees and the employees of his subcontractors. Make certain that there are no personnel under areas of construction or that would be affected by material lifting operations.
Clean only
Runway 14L/32R to include yellow diagonal markers outside the edge lines.
Runway 5L/23R to include yellow diagonal markers outside the edge lines, the yellow ALZ, and the Carrier Deck on the runway.
Clean and Paint
Warmup area's 1, 2, & 3
Displaced Threshold markings 05L & 14R
All of Hotel Taxiway including the Hold Short lines.
All of Bravo Taxiway including the Hold Short lines.
All of Foxtrot Taxiway including VMUT-2 Taxi In/Out Line from the hangar to center mat including the Hold Short line.
Compass Rose markings
Cala Taxiway including the Hold Short line.
Center line and the Hold Short lines of Taxiway's Alpha, Charlie, Echo, Golf, India, Juliet, Kilo, Lima, Mike, and November
Hold Short line separating the ARFF apron and Rwy 14L.
Helo spots A,B,C, & D adjacent to the grass at the tower.
Add new Hold Short line and move the current Helo spot South/East
1.2 SUBMITTALS
Where shop drawings and/or samples are requested, furnish six copies to the
5/5/2025 SECTION 01 90 00 Page 1 government for review and approval prior to ordering or fabrication of any materials or assemblies. Incomplete submittals will not be reviewed and will be returned to the submitter for completion.
1.3 SUBCONTRACTOR/CONTRACTOR ACCOUNTABILITY
All contractors and sub-contractors for this project will be responsible for review and compliance of all requirements covered under this contract.
It shall be the responsibility of this contractor to coordinate the work of all his sub-contractors. The government will not fund extra cost issues necessitated as a result of failure by this contractor to properly schedule and coordinate efforts made by him or his sub-contractors with the efforts of other sub-contractors. Work done out of sequence with other work, resulting in additional material requirements and effort and/or the removal and reinstallation of work already installed, will be the responsibility of this contractor at no additional cost to the government.
1.4 SAMPLES
The government reserves the right to sample any materials at random from products delivered to the job site and test them to verify the products either conform to the project requirements or approved substitution.
Products, which do not conform, shall be removed from the job site and replaced with new products that conform to the project requirements or approved substitution.
-- End of Section --