This is Amendment 0002 to a federal solicitation issued by FEAD Cherry Point (Code N40085) for the procurement requisition 7415686 titled "Provide Swing Gates Station BEQ's." The amendment was effective September 14, 2026, and is being issued to provide Preaward Inquiry (PPI) responses. The proposal due date remains Wednesday, September 16, 2026, at 3:00 P.M. local time, and this amendment must be acknowledged with proposal submission. The estimated cost range for the project is between $100,000 and $250,000.
The Preaward Inquiry Form addresses six substantive questions submitted by potential bidders on September 10, 2026. Government responses clarify that contractors should bid in accordance with the provided plans and specifications, with revised plan sheets addressing questions regarding demolition/installation limits, grounding/bonding details, and foundation details for gate posts and bollards. The government confirmed that the gate design has been successfully constructed twice previously with sufficient detail to execute the work. For gate equipment and controls, the government clarified that gates are manually operated with no automatic controls required. Regarding contractor scheduling, the government directed bidders to section 01 14 00 Work Restrictions, paragraph 1.3, for special scheduling requirements governing work at multiple locations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12939795.pdf | ||
| 12939792.pdf | ||
| 12939791.pdf | ||
| 12939786.pdf | ||
| 00 01 15.pdf | ||
| Amendment 0001.pdf | ||
| 7415686 SpecsAsOne.pdf | ||
| 7415686 RFP.pdf | ||
| Master PPI Form.xlsx | XLSX spreadsheet | |
| 7415686 DrawingsAsOne.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
FEAD CHERRY POINT
PSC BOX 8006
CHERRY POINT, NC 28533
AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL
is extended is not extended original
PREAWARD INQUIRY FORM
PAGE SECTION PARAGRAPH
8/19/2026 RFP Please provide the Government's estimated cost range for this project. This information is requested to determine whether a bid bond will be required and to allow our surety to evaluate the appropriate bonding limits, as the estimated cost range is required for their review. Providing this information in advance will help avoid the unnecessary risk associated with requesting a bid bond on the day of bid submission and ensure sufficient time for the surety to issue the bond, allowing us to comply with the solicitation's Bond Requirements, which require the bid bond to be submitted with the proposal.
The Estimated cost range is between $100,000 and $250,000.
9/10/2026 4,6 Provide a plan clarification or marked-up demolition/installation limit plan for each gate identifying exact tie-in points and required restoration scope.
See revised plans sheets
9/10/2026 211 Issue a grounding/bonding detail or note identifying conductor sizes/materials, bonding points, and the required connection to existing/new grounding electrodes or systems.
See revised plan sheets.
9/10/2026 211212 Issue foundation details or a structural schedule for gate posts and hold-open bollards, including pier/footing sizes, reinforcing, and embedment requirements by gate type/location
Bid in accordance with plans and specifications.
NOTE: This same gate deisgn has been sucessfully constructed with the same level of detail two previous times. There is sufficient detail to execute the work required under this projects scope of work.
9/10/2026 6, 211 Issue a gate equipment/control schedule or detail identifying the required operator assembly, power, safety devices, and control interfaces for each gate location.
Bid in accordance with plans and specifications.
NOTE: There are no controls for these gates, they are manually operated.
9/10/2026 Will the contractor be able to work at multiple locations or is their limitations requiring phasing Bid in accordance with plans and specificaitons.
NOTE: See section 01 14 00 WORK
RESTRICTIONS; PARA 1.3 SPECIAL
SCHEDULING REQUIREMENTS
POSTED ON
AMENDMENT #
REFERENCE
QUESTION GOVERNMENT RESPONSEDATE
SUBMITTED