AMENDMENT 0001.pdf
PDF 597 KB Posted
- Solicitation number
- N400857359365
About this file
This document is an Amendment 0001 to a solicitation for the replacement of an existing culvert under Air Base Road at Atlantic OLF, MCAS Cherry Point, North Carolina. The amendment responds to pre-award Requests for Information (RFIs), including confirming that a subcontractor may access the site with a temporary sponsorship request, and allowing the use of concrete pipe in lieu of corrugated metal pipe if the contractor provides supporting hydraulic calculations at no additional cost. The solicitation number is N400857359365, the procurement is restricted to Civil Paving MACC contractors, and the proposal due date remains unchanged at December 17, 2024 at 1:00 PM local time. The issuing agency is the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0003.pdf | ||
| AMENDMENT 0002.pdf | ||
| WO7359635 SpecsAsOne SIGNED.pdf | ||
| RFP 7359365.pdf | ||
| WO7359635 DrawingsAsOne SIGNED.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC
SPECIFICATION
7359365 Replace Existing Culbert
Under Air Base Road Atlantic OLF
MCAS Cherry Point, NC AMENDMENT
#0001
IMPORTANT
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of the proposal.
If your proposal has been submitted prior to the receipt of this amendment, acknowledgement should be made by telegram, which should state whether the price contained in your proposal is to remain unchanged, is to be decreased by an amount, or is to be increased by an amount. The acknowledgement must be received prior to proposal opening time.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0001 11/22/2024 7359365
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
CG MCAS Cherry Point
FACILITIES, ROICC
B-163, CURTIS ROAD
PSC BOX 8006
CHERRY POINT, NC 28533
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION
Replace Existing Culvert Under Air Base Road Atlantic OLF
9B. DATED (SEE ITEM 11)
AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR PROPOSAL 10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning 1 copy of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return original to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
7359365 Replace Existing Culvert Under Air Base Road Atlantic OLF, Marine Corps Air Station Cherry Point, NC
Amendment 0001 is being issued to respond to pre-award RFI.
The deadline to submit pre-award RFI’s REMAINS 03 December 2024 at 9:00 AM.
The proposal due date of 17 December 2024 at 1:00 PM local time REMAINS unchanged.
See Attached.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8) 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
Amendment 0001 7359365 Replace Existing Culvert Under Air Base Road Atlantic OLF
RFI Responses:
1. I have a sub-contractor that would like to look at the site. Is this a restricted area, sub has DBIDS.
Can they access site?
Response:
The subcontractor may look at the site. If they do not have flight line access, you will need to submit a temporary sponsorship request via email to Ericka Bishop (ericka.j.bishop.civ@us.navy.mil) and provide their company name, the POC’s name and the date they want to have access to look at the location. There will be no sponsored site visit.
2. Can concrete pipe be used in lieu of corrugated metal pipe?
Response:
The contractor may use concrete pipe in lieu of corrugated metal pipe if the contractor provides calculations to support that the size and number of concrete pipes are hydraulically equivalent to the CMP shown on the plans. This change will be at no additional cost to the Government.
| AMENDMENT 0001 |
| Amend Cover |
| Amendment Page 2 |
RFI 1 responses
File details come from the government source that posted it. Updated .